| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.9 LAccepted-AOC SAROJA CONTRACTOR SENJI TAMIL NADU TN | ₹10.9 L | L1 | Accepted-AOC L1 |
| 2 | L2₹11.0 L+₹11,446.77 (1.05%)Rejected-AOC KRISHNAGIRI | TAMIL NADU | 635001 | ₹11.0 L+₹11,446.77 (1.05%) | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | R RAJENDIRAN L2 | Saroja L1 |
|---|---|---|---|---|---|
| 1.00Construction of RCC Slab Culvert @ Kulakkarai Near in Melpapampadi Pt | |||||
| 1.01 | Earth work excavation for foundation in all classes of soils except hard rock requiring blasting with initial lead and lift etc including levelling the site etc. complete with standard specification in hard stiff cllay, black cotton soil, hard fred earth, shale murums, gravel stoneyearth, and earth mixed with 50 % fair sized boulders, and hard graveily soil, in foundation.as per SS 20 B | 64.06 | M3 | 266.42 ₹17,066.72 | 263.65 ₹16,889.3 Lowest |
| 1.02 | Cement Concrete 1:4:8 Using 40mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 7.54 | M3 | 5,895.03 ₹44,448.5 | 5,833.74 ₹43,986.41 Lowest |
| 1.03 | Centering charges for corewall including all cost of labour charges | 34.2 | m2 | 552.98 ₹18,911.75 | 547.23 ₹18,715.14 Lowest |
| 1.04 | Centering charges for corewall including all cost of labour charges | 73.68 | m2 | 1,105.95 ₹81,486.4 | 1,094.45 ₹80,639.26 Lowest |
| 1.05 | Cement Concrete 1:3:6 Using 40mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 43.85 | m3 | 6,171.75 ₹2,70,631.08 | 6,107.58 ₹2,67,817.59 Lowest |
| 1.06 | Cement Concrete 1:2:4 Using 20mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 2 | m3 | 7,211.04 ₹14,422.07 | 7,136.07 ₹14,272.14 Lowest |
| 1.07 | Cement Concrete 1:1.5:3 Using 20mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 2.87 | m3 | 9,673.93 ₹27,764.18 | 9,573.36 ₹27,475.55 Lowest |
| 1.08 | Supply and Fabrication for Steel work including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc | 0.35 | mt | 92,853.63 ₹32,498.77 | 91,888.32 ₹32,160.91 Lowest |
| 1.09 | Supply and Filling Well Gravel Layer including cost and Conveyence of all charges | 4.95 | m3 | 344.01 ₹1,702.83 | 340.43 ₹1,685.13 Lowest |
Tender Value
₹11 L
EMD Value
₹11,000
Closing Date
29 Jun 2026, 3:00 pmClosed
BDO BP
Block Development Office, Gingee
Construction of RCC Slab Culvert at Kulakkarai Near in Melpapampadi Pt, Construction of Retainingwall at New PHC Building in Gengavaram Pt
2026_RDTN_680709_4
Gingee/General Fund 2025-26
Open Tender
Civil Works
Works
Gingee
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹11,000
Yes
25 Jul 2026
12 Jun 2026
29 Jun 2026
12 Jun 2026
29 Jun 2026
12 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of RCC Slab Culvert @ Kulakkarai Near in Melpapampadi Pt | |||||
| 1.01 | Earth work excavation for foundation in all classes of soils except hard rock requiring blasting with initial lead and lift etc including levelling the site etc. complete with standard specification in hard stiff cllay, black cotton soil, hard fred earth, shale murums, gravel stoneyearth, and earth mixed with 50 % fair sized boulders, and hard graveily soil, in foundation.as per SS 20 B | 64.06 | M3 | 263.78 | ₹16,897.75 |
| 1.02 | Cement Concrete 1:4:8 Using 40mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 7.54 | M3 | 5,836.66 | ₹44,008.42 |
| 1.03 | Centering charges for corewall including all cost of labour charges | 34.2 | m2 | 547.5 | ₹18,724.5 |
| 1.04 | Centering charges for corewall including all cost of labour charges | 73.68 | m2 | 1,095 | ₹80,679.6 |
| 1.05 | Cement Concrete 1:3:6 Using 40mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 43.85 | m3 | 6,110.64 | ₹2,67,951.56 |
| 1.06 | Cement Concrete 1:2:4 Using 20mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 2 | m3 | 7,139.64 | ₹14,279.28 |
| 1.07 | Cement Concrete 1:1.5:3 Using 20mm ISS size Hand Broken granite stone jelly including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc complete. | 2.87 | m3 | 9,578.15 | ₹27,489.29 |
| 1.08 | Supply and Fabrication for Steel work including labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc | 0.35 | mt | 91,934.29 | ₹32,177 |
| 1.09 | Supply and Filling Well Gravel Layer including cost and Conveyence of all charges | 4.95 | m3 | 340.6 | ₹1,685.97 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.95 MB
BOQ_817973.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .