| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.0 LAccepted-AOC MYOREPUR ANPARA ANPARA ANPARA SONBHADRA UTTAR PRADESH 231225 | SONBHADRA | UTTAR PRADESH | 231225 | L1 | Accepted-AOC L1 BIDDER | |
| 2 | L2₹22.6 L+₹2.6 L (13.1%)Rejected-AOC | L2 | Rejected-AOC L2 BIDDER | |
| 3 | L3₹23.1 L+₹3.0 L (15.2%)Rejected-AOC | L3 | Rejected-AOC L3 BIDDER |
Tender Value
₹20.1 L
EMD Value
₹40,000
Closing Date
5 Nov 2022, 6:00 pmClosed
SE OMC-V ATPS Anpara
office of SE OMC-V ATPS Anpara
Maintenance of Lighting system, Electrical Hoist, Cable laying and maintenance of suspended magnets and Daily Site Store handling of CHP, 3x210MW, ATPS, Anapra
2022_RVUNL_737702_1
02/CHD-II/ATPS/2022-23
Open Tender
Electrical Works
Fixed-rate
365 days
office of SE OMC-V ATPS Anpara
As per PQC
3 documents required · 3 mandatory
₹1,180
Dy CAO CFA and BO ATPS Anpara
₹40,000
28 Aug 2023
14 Oct 2022
7 Nov 2022
14 Oct 2022
5 Nov 2022
14 Oct 2022
Amount
MAINTENANCE OF LIGHTING SYSTEM, ELECTRICAL HOIST, CABLE LAYING AND MAINTENANCE OF SUSPENDED MAGNETS INSTALLED IN CHP, ATPS
Routine maintenance and attending breakdown of lighting / welding system of coal handling plant of 3x210 MW units for proper lighting and welding supply including checking and minor maintenance of associated equipment.
Operation of Hoist on clock wise
RATE SCHEDULE (b) HOIST
Repositioning of entangled steel wire rope, replacement of steel wire rope
Attending fault in the control panel of overhead system including replacement of defective components.
Maintenance of hoist which includes replacement of motors, bearings, cleaning of panels, control circuit, cleaning of monorail & other accessories.
Doing steel wire rope of single/double drum hoists in single rope by removing hook pulley for positioning of conveyor belt and for other works.
Repositioning of steel wire rope with hook pulley in single/double drum hoist after positioning of conveyor belt and other works.
Bringing down the hoist unit from mono-rail of the respective floor for attending the breakdown complete overhauling and repositioning
Bringing down the hoist unit from mono-rail of the respective floor for attending the breakdown,complete overhauling and repositioning
Shifting of hook pulley from hoist to another / replacement by new hook pulley.
Railing/Travelling hoist Motor Breakdown maintenance(along with Motor alignment)
RATE SCHEDULE (c)ELECTRICAL WIRING & POWER CABLE
Providing & Installation of 7” x 4” sun mica top wooden board
Providing & Installation of 15A, 240V Anchor make switch socket combined unit with sun mica top wooden board.
Providing & Installation of 15A, 240V Anchor make fuse type switch with sun mica top wooden board.
Providing & Installation of 15A, 240V flush type anchor/ standard quality make switch with three pin socket with sun mica top wooden board.
Installation of Junction box off size
CABLE LAYING / SALVAGING upto 10mm2
CABLE LAYING / SALVAGING Power XLPE Aluminum Cable Above 10 mm2 upto 50 mm2
CABLE LAYING / SALVAGING Power XLPE Aluminum Cable Above 50 mm2 upto 240 mm2
CABLE LAYING / SALVAGING of Power XLPE Aluminum Cable Above 240 mm2 upto 300 mm2
TERMINATION & CABLE GLANDING upto 10mm2
TERMINATION & CABLE GLANDING of Power XLPE Aluminum Cable above 10 mm2 upto 50 mm2
TERMINATION & CABLE GLANDING of Power XLPE Aluminum Cable Above 50 mm2 upto 240 mm2
TERMINATION & CABLE GLANDING of Power XLPE Aluminum Cable Above 240 mm2 upto 300 mm2
STRAIGHT THROUGH JOINT OF CABLE upto 10 mm2
STRAIGHT THROUGH JOINT OF CABLE above 50 mm2 to 240 mm2
STRAIGHT THROUGH JOINT OF CABLE 240 mm2 to 300 mm2
RATE SCHEDULE (d) SUSPENDED MAGNET
Attending the fault in the control panel of Oil cooled Suspended Magnets and motors of traveling trolley including replacement of defective components.
Maintenance of Suspended Magnets which include cleaning of control panel, Transformers, Complete cleaning of S/M, Monorail, Checking and maintaining of oil level, maintenance of silica Jel etc.
Maintenance of motorized trolley, Chain pully which includes replacement of motors, bearings and other associated works
Centrifuging of oil of Suspended magnets
RATE SCHEDULE (e) PF & TT
Maintenance/ overhauling of PF & TT slip ring assembly,electrical control pannel and other associated work.
Fortnightly checking of electrical control pannel of TT & PF, slip ring assembly , multi core flexible cable of slip ring assembly, DE/DS system and other control cable of panel.
Repairing of LDBS /Junction Box of locating in different places of CHP including fixing of doors, Welding of hinges of doors, repairing/replacing of door lock sysyem, replacement of burnt aluminium/copper bus bar relugging and termination of cables and recommissioning
Daily Site Store handling and cartage of material from Central Store to Site Store and vice-Versa of CHP, 3x210MW, ATPS, Anpara
Daily Site Store handling.
Cartage of following materials from central store to the site store of CHD-II, Steel of different sections
Spare parts of machines, plant equipment, consumables and electric items Up to 30 Kg
Spare parts of machines, plant equipment, consumables and electric items Above 30 Kg up to 100Kg.
Spare parts of machines, plant equipment, consumables and electric items Above 100Kg up to 250 Kg
Spare parts of machines, plant equipment, consumables and electric items Above 250 Kg.
Bolts, nuts washer, consumables including welding electrodes, jutes, cloths etc.
Cartage of other material which will be used in CHP from central / plant store to site & vice –versa. This will include rubber items, gaskets, sheets, cork sheets, hose pipe etc.
Cartage of lubricant from different plant store to site store and vice-versa.
Cartage of scraps from site store of CHP, welding and their stacking in central store steel scrap yard.
Cartage of cable /conveyor belt bunches / drums from central store to site store and vice-versa.
Removal of foreign materials form the container placed below the Suspended Magnet at Pent House of TP-1, over conveyor 5A/ 5B near TP-4 and cartage to steel scrap yard of CHP.
Repairing of Hydraulic Jack 100 MT
Repairing of Hydraulic Jack 50 MT
Repairing of Hydraulic Jack 20 MT
M/S SHAKTI REFRIGERATION WORKS
M/S ALOK ENTERPRISES
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .