| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹21.1 LAdmitted-Finance | +0.00% | ₹21.1 L | L1 | Admitted-Finance |
| 2 | L1₹21.1 LAdmitted-Finance | +0.00% | ₹21.1 L | L1 | Admitted-Finance |
| 3 | L1₹21.1 LAdmitted-Finance | +0.00% | ₹21.1 L | L1 | Admitted-Finance |
Tender Value
₹25 L
EMD Value
₹25,000
Closing Date
14 Aug 2026, 6:00 pmClosed
EXECUTIVE OFFICER
JHARSUGUDA MUNICIPLAITY
IMPROVEMENT OF TANK
2026_ORULB_136867_1
EO/JMC/05/2026-27
Open Tender
Civil Works - Others
Percentage
120 days
CHOWKIPADA
Scan copy of regd. cert, PAN, GST clearance cert., experience cert., and other documents as per DTCN
3 documents required · 3 mandatory
₹6,000
₹25,000
Yes
8 Sept 2026
24 Jul 2026
17 Aug 2026
24 Jul 2026
14 Aug 2026
24 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | De-Watering:- Supplying all materials, labours, T&P, 5.00 HP Diesel Pump set with POL, Pump Operation etc. and DE-Watering the Clear/Muddy Water etc. all complete as per the required specification and direction of Engineer in Charge. | - | HR | 1 | - |
| 2 | Deweeding-uprooting rank vegetation and weeds by digging the area to a depth of 60 cm, removing all weeds and other growth roots by forking reapeadly breaking clods rough dressing flooding with water uprooting fresh growth after 10 to 15 days and than fine dressing for panting new grass etc. as per the required specification nd direction of the EIC. | 1 | SQM | - | - |
| 3 | De-silting- Supplying all materials labour T&P excavation of any available type of soil by machanical means loading into and transportation by mechanical means and unloading the soil within the pond area on propoerly prapared and unloading the soil within the pond area on properly prepared and scientifically approved surface including spreading and levelling the earth in 22.5 cm layers to make ready for watering and compaction by mecabical means but excluding watering and compaction in dams and dykes for all heights including construction, maintanance, watering and lighting of haul road and borrow area etc. complete as per the required specification and direction of the EIC. | - | CUM | - | - |
| 4 | Supplying all materials labour T&P, Excavation of any available type of soil by mechanical measn loading into and transportation by mechanical means unloading ther soil within the pond area on propoerly preapred and scientifically approved surface including spreading and levelling the earth in 22.5 cm layers to make ready for watering nad compaction nu mechcanical means but sxluding watering and compaction in dams and dykes for all heights including construction, maintanance, watering and lighting oa haul road and borrow area etc. complette as per the required specification and direction of the EIC. | 1 | CUM | - | - |
| 5 | Supplying all materials labour T&P, watrering earthwork upto OMC condition and compaction by mechanical means in layers not exceeding 22.5 cm to 95% dry density including hire and running charges of all mechancial etc complete as per the required specification and direction of the EIC. | - | SQM | - | - |
| 6 | Horticulture (Wedella, Vetfver Grass):- Supplying all materials labour and T&P etc. for removig vegetation and making up undulation not exceeding 15cm. In depth including disposal of rubbish, plantation of sepling - i) Wedeila Plantation @ 1 Nos./ 2 Sqft. ii) Vetiver Grass - Spread across the area, all Complete as per the specification and direction of EIC. | - | SQM | - | - |
| 7 | Earth Work excavation in hard soil including moorum stony earth and earth mixed with boulder within 50 m initial lead and 1.5 m initial lift including dressing and breaking clods levelling the bed up to required depth and depositing the excavated materials with all leads and lifts T and P etc. complete as per direction of Engineer-in-charge. | - | CUM | 1 | - |
| 8 | Earth Work excavation in hard soil including moorum stony earth and earth mixed with boulder within 50 m initial lead and 1.5 m initial lift including dressing and breaking clods levelling the bed up to required depth and depositing the excavated materials with all leads and lifts T and P etc. complete as per direction of Engineer-in-charge. | - | CUM | - | - |
| 9 | Cement Concrete (1:4:8) with 4 cm size HBG metal of approved quality from approved quarry including lowering laying concrete water curing to required level not exceeding 150 mm thick including cost, conveyance, royalty taxes of all materials etc. complete as per direction of Engineer-in-charge. | 1 | CUM | 1 | ₹1 |
| 10 | C.C (1:2:4) with 12mm size HG chips including all cost, conveyance, royalty & taxes etc. comp. to work site as per the specification approved by the department & direction of Engineer-in-charge. | - | CUM | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.21 MB
NIT.pdf
Tender Documents • 2.19 MB
DTCN.pdf
Additional Documents • 7.45 MB
BOQ_603000.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .