| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 CrAccepted-AOC | ₹2.1 Cr Quoted ₹1.7 Cr | L1 | Accepted-AOC 1st lowest |
| 2 | L2₹1.9 Cr+₹18.3 L (10.5%)Rejected-Finance | ₹1.9 Cr+₹18.3 L (10.5%) | L2 | Rejected-Finance other than 1st lowest |
| 3 | L3₹1.9 Cr+₹18.8 L (10.9%)Rejected-Finance NOT AVAILABLE | NORTH | DELHI | 110006 | ₹1.9 Cr+₹18.8 L (10.9%) | L3 | Rejected-Finance other than 1st lowest |
Tender Value
₹1.8 Cr
EMD Value
₹1.8 L
Closing Date
16 Mar 2026, 5:00 pmClosed
Executive Engineer,Central Tender Cell
Central Tender Cell,UG FLOOR,ICOMC TOWER
Fishery pond front development, Right parallel road, Land development of footpath, Plantation and beautification work at Laxmi Sagar in Ward No 43
2026_ORULB_126642_6
BMC-EE-Tender Cell-74/2025-26 dt. 25.02.2026
Open Tender
Civil Works - Others
Percentage
180 days
BMC AREA
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹1.8 L
Yes
Office chamber of the EE,Central Tender Cell
8 Sept 2026
28 Feb 2026
17 Mar 2026
28 Feb 2026
16 Mar 2026
28 Feb 2026
28 Feb 2026 - 9 Mar 2026
9 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork by using hydraulic excavator of 1 cum bucket and depositing the excavated materials within 5 km lead including loading and unloading with all cost conveyance T&P sundries etc. complete as per direction of Engineer-In-Charge | 312.5 | cum | 209.95 | ₹65,609.38 |
| 2 | Dismantlling and removing cement concrete including stacking the useful materials for re-use and removing the debries within 50mtr lead. | 20 | cum | 858.58 | ₹17,171.6 |
| 3 | Dismantling and removing R.C.C. columns beams slab staircase landing lintels including stacking the useful materials for reuse and removing the debris within 50m lead as per the direction of the engineer in charge. | 106.7 | cum | 1,696.95 | ₹1,81,064.57 |
| 4 | Compacting and waterring upto OMC rolling earth work with PRR in embankment in layers not exceeding 0.23m depth by PRR including hire & running charges of PRR. etc. complete.. | 300 | cum | 80.15 | ₹24,045 |
| 5 | Providing and spreading moorum and consolidation with HRR including watering cost and conveyance of moorum | 445.6 | cum | 1,263.51 | ₹5,63,020.06 |
| 6 | Filling in foundation and plinth with excavated materials, moorum including watering and ramming as directed by the Engineer-in-charge of earth work. | 300 | cum | 114.48 | ₹34,344 |
| 7 | Filling plinth with sand in layers not exceeding 20 cm in depth, well watered and compacted, top surface dressed and levelled to proper gradient Including cost and conveyance of sand, all taxes and royalties, loading and unloading, all labour sundries T&P etc. complete as per direction of Engineer in-Charge | 168.5 | cum | 519.79 | ₹87,584.61 |
| 8 | Providing and laying 60mm thick factory made cement concrete interlocking paver block of M-30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50mm thick compacted bed of coarse sand, filling the joints with line sand etc. all complete as per the direction of Engineer-in-charge | 2,910 | sqm | 608.4 | ₹17,70,444 |
| 9 | Rough stone dry packing on Aprons and Revetments with hard stone 30cm 9 and above size including cost, conveyance royality of all materials and labour charges etc.complete as per direction of Engineer-In-Charge. | 488 | cum | 2,181.95 | ₹10,64,791.6 |
| 10 | Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessoriesfor walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutott/holes of required sizes for services. yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of Mechanical, Electrical and Plumbing inserts will be paid separately). | 277.9 | cum | 20,818.78 | ₹57,85,538.96 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.33 MB
DTCN.pdf
Tender Documents • 0.95 MB
BOQ_583026.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .