| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹10.6 LAdmitted-Finance | -0.30% | ₹10.6 L | L1 | Admitted-Finance |
| 2 | L2₹10.8 LAdmitted-Finance 0 BELCHAURA MAUNATH BHANJAN MAU MAU UTTAR PRADESH 275101 | MAU | UTTAR PRADESH | 275101 | +2.00% | ₹10.8 L | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | - | Rejected-Technical Bid Under Evaluation |
Tender Value
₹10.6 L
EMD Value
₹1.1 L
Closing Date
20 Apr 2026, 5:00 pmClosed
EO, NPP Baraut
NPP Baraut
44 - Kasba Baraut ward no 20 gali maliyan mai Dharampal Chai wale makan se Mukesh Sharma ke makan tk CC sadak/ Nali nirman karya.
2026_DOLBU_1132204_44
818/2025-26, Dt. 28-03-2026
Open Tender
Miscellaneous Works
180 days
Baraut
Tender Fee EMD and other documents as per tender documents/NIT
2 documents required · 2 mandatory
₹1,250
EO, NPP Baraut
₹1.1 L
16 May 2026
8 Apr 2026
21 Apr 2026
8 Apr 2026
20 Apr 2026
8 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
Dismentling of old cc road in tile complite / possition S.I 638 | - | sqm | - | - | BI01010001010000000000000515BI0100001113 | |
Disposal of old tile road material from site. In 3.0km lead | 1 | cum | - | - | BI01010001010000000000000515BI0100001114 | |
Cc in (1:4:8) in nalla bed with 4cm gauge b/ballast cement c/sand in comp.position (s.i-281) | - | cum | - | - | BI01010001010000000000000515BI0100001115 | |
Construction of embankment /patri with material obtained from borropit cartage 5.00km . Construction of embankment / patri with material obtained from borropits cartage 2.00 km . Construction of embankment /patri with approved material obtained from borrow pits with all lift and leads transporting to site spreading grading to required slope and compacting to meet requirement of table 300.2 | - | cum | - | - | BI01010001010000000000000515BI0100001116 | |
Contruction of granular sub- base by providing well graded material spreading in uniform layers with motor grader on prepared surface ,mixing by mix in place method with rotavtor at OMC,and compacting with smooth wheel roller to achieve the desired drnsity ,as per MORD,specification 401 | - | cum | - | - | BI01010001010000000000000515BI0100001117 | |
CC work in (1:2:4) mortar with approved stone grit cement c/sand in nalla wall and bed including ,labour ,toools ,plant .and supply of all material and necessary cen tring shuttering in comp position (s.i-279a) | - | cum | - | - | BI01010001010000000000000515BI0100001118 | |
Cement Concrete Pavement.construction of un - reinforcement dowel jointed at expansion and construction joint only, plain cement concrete pavement thickness as per design over a prepared sub base with 43 grade cement or any other as per clause 1501.2.2 M 30 (Grade) coarse and fine aggregates conforming to is 383 maximum size of coarse aggregate not exceeding 25 mm mixed in a concrete mixer of not less than 0.2 cum capacity and opproriate weigh batcher using approved weigh batcher using mix design ,laid in approved fixed side formwork (steel channel laying and fixing of 125 micron thick polythen film wedges steel plates including leveling the formwork as per drawing) spreeding the concrete with shovels rakes compacted using needle screed and plate vibrators and finished in continuous opertion including provision of contraction and expansion construction joint applying debonding strips primer sealant dowel bars near approaches to bridge / culvert and construction joints admixture as approved curing of concrete slab for 14 days using curing compound (where specified) and water finishing to lines and grade as per drawing and technical specification clause 1501 | 1 | cum | - | - | BI01010001010000000000000515BI0100001119 | |
STEEL WORK WELDED IN BUILT UP SECTIONS / FRAMED WORK INCLUDING CUTTING HOISTING FIXING IN POSITION AND APPLYING A PRIMING COAT OF APPROVED STEEL PRIMER USING STRUCTURAL STEEL ETC AS REQUIRED . IN GRADING FRAMES GUARD BAR LADDER RALLING BRACKETS GATES AND SIMILAR WORKS IN DSR 10.25 .2 | - | qtl | - | - | BI01010001010000000000000515BI0100001120 | |
s/fixing sign board at site in comp .position | - | nos | - | - | BI01010001010000000000000515BI0100001121 | |
DEDUCT THE AMOUNT FOR OLD TILES | - | NOS | - | - | BI01010001010000000000000515BI0100001122 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 11.52 MB
Tendernotice_2.pdf
PDF • 0.89 MB
BOQ_2114859.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid