| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹5.1 LAccepted-Finance | 1 | Accepted-Finance Satisfied | |
| 2 | 2₹5.5 L+₹39,625 (7.72%)Accepted-Finance 36 137 THANGAMAPURIPATTINAM METTUR DAM 636 401 | METTUR DAM | SALEM | TAMIL NADU | 636401 | 2 | Accepted-Finance Satisfied |
Tender Value
Refer Docs
EMD Value
₹7,200
Closing Date
16 May 2022, 2:00 pmClosed
Superintending Engineer /Mechanical-I/MTPS-I
Office of the Superintending Engineer / Mechanical -I Mettur Thermal Power Station- I Mettur Dam-636406
MTPS I TM I Unit I Annual Maintenance works in Main Turbine and its Auxiliaries Overhauling of Centrifuge during Boiler Statutory inspection 2022 23
2022_EB_230971_1
CE/ MTPS-I/ SE / M-I / TM / OT. 86 / 2022-23
Open Tender
Power/Energy Projects/Products
Works
6 days
Mettur Thermal Power Station-I / Mettur Dam
As per the Tender Specifications
4 documents required · 4 mandatory
₹0
₹7,200
Yes
19 May 2022
2 May 2022
17 May 2022
2 May 2022
16 May 2022
2 May 2022
Amount
Dismantling, overhauling and assembling of HP & IP Control Valve Columns. Dismantling the control valve columns after loosening the bolts, dismantling its liners, spring assembly liner sliding pin, dismantling the roller bearings, cleaning the above items, inspection of liner key way and measuring the dimension, welding and grinding to the dimension required, greasing the bearing, assembling the dismantled parts and setting the roller clearance as per the direction of engineer in charge.
Dismantling, Inspection and changing of HP & IP Control Valves: a). Cutting the spindle leak off lines, heating the cap nut of steam chest by gas, dismantling the control valve assembly from steam chest, cleaning of all parts removal of steam strainer and cleaning spare valve and valve seat lapping and checking blue matching, steam chest flange lapping and blue matching, checking valve stem and liner clearance, valve stem DYE penetrant checking etc., Assembling the spare valve with steam chest and tightening the cap nut etc., checking Idle lift connecting the spindle leak off lines and welding as per the direction of the Engineer-in- charge.
b). Drilling the hole in the stem for providing spilt pin, providing the split pin, checking the washer clearance, checking valve lift etc.
Dismantling, overhauling and assembling of HP & IP Cam Shaft arrangement: Dismantling the cam shaft arrangements from its plumber blocks. Inspection of all bearings, changing the damaged bearings, metal building and machining if required in the bearing seating area, cam inspection and changing the damaged cam. Greasing of all bearings and assembling.
Dismantling the Bearing cover, checking the Bearing Interference and assembling after C & I work: Dismantling the bearing cover by loosening the cap nuts, checking the bearing to cover Interference attending correction if any and assembling after cleaning the parting plane and after completion of C & I works.
Checking the hot governing characteristics and adjusting the valve openings as per the instruction of Engineer in-charge including tools and tackles.
MOT Filter Cleaning: Charges for main oil tank filters cleaning including dismantling of filter cover plate, lifting of filters, cleaning of filters by air, inspection of Filters and assembling of Filter Cover plate, cleaning of spillage oil in and around the Main oil tank.
Inspection and cleaning of ESV/IV Pilot valve: Checking the necessary clearances in the pilots with liners and assembling with renewal of wornout spares.
Renewal of LPT diaphragm: Removal of old gasket, cutting new gasket to the existing contour and renewing the new gasket and complete tightening of outer rings.
Inspection and Cleaning of MOT: Draining the oil to clean oil tank through centrifuge, Removal of MOT strainers, Cleaning the tank after removing the slag, Drawl of new oil and devolution of empty barrel, Topping up of oil from clean oil tank through centrifuge.
CENTRIFUGE OVERHAULING –ALFA LAVAL: a) Dismantling of oil inlet and outlet pipe lines to centrifuge, dismantling of motor, break drum, bowl assembly and pump assembly. Cleaning, inspection, Renewal of damaged spares, bearings, oil seals and assembling, successful commissioning of the centrifuge.
b).Cleaning of Oil line, renewal of oil line gaskets and painting etc
Charges for Consumables and T&P’s item for Sl.No:1 to 12
SRI V M A ENTERPRISES
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .