Loading…
Loading…
Tender Value
₹69 L
EMD Value
₹1.4 L
Closing Date
25 Aug 2026, 6:55 pmDue tomorrow
office of the Executive Engineer PMGSY Div MDR
office of the Executive Engineer PMGSY Div MDR
boq
2026_JKRRD_149263_8
EE.PMGSY.M.14 OF 2026-27 DT. 17-08.2026
Open Tender
CIVIL
Percentage
180 days
Mendhar
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,200
office of the Executive Engineer PMGSY Div MDR
₹1.4 L
Yes
19 Aug 2026
19 Aug 2026
26 Aug 2026
19 Aug 2026
25 Aug 2026
19 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil : | 467.05 | Cum | 256.85 | ₹1,19,961.79 |
| 1.02 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 233.15 | Cum | 5,202.9 | ₹12,13,056.14 |
| 1.03 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 206.82 | Cum | 5,733.6 | ₹11,85,823.15 |
| 1.04 | CAST-IN-SITU
Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 8.7 | Cum | 7,788.4 | ₹67,759.08 |
| 1.05 | Providing and laying factory made chamfered edge Cement Concrete
paver blocks in footpath, parks, lawns, drive ways or light traffic parking
etc, of required strength, thickness & size/ shape, made by table vibratory
method using PU mould, laid in required colour & pattern over 50mm
thick compacted bed of sand, compacting and proper embedding/laying of
inter locking paver blocks into the sand bedding layer through vibratory
compaction by using plate vibrator, filling the joints with sand and cutting
of paver blocks as per required size and pattern, finishing and sweeping
extra sand complete all as per direction of Engineer-in-Charge.
80 mm thick C.C. paver block of M-30 grade with approved
color design and pattern | 1,574 | sqm | 929.85 | ₹14,63,583.9 |
| 1.06 | Random Rubble masonry with hard stone in foundation and plinth
including leveling up with cement concrete Cement mortar 1:6 (1 Cement : 6 coarse sand) | 327.13 | Cum | 5,402.9 | ₹17,67,450.68 |
| 1.07 | Dry random rubble masonry with hard stone in foundation and plinth:
With bond stone. | 45.68 | Cum | 3,262.1 | ₹1,49,012.73 |
| 1.08 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Cold twisted bars | 354.75 | Kg | 123.2 | ₹43,705.2 |
| 1.09 | Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS : 280 and IS : 4826 in 100 mm x 100 mm mesh (woven daigonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specs Clause 1301 including all carriages, leads and lifts etc. and cost of wire crates complete | 43.2 | Cum | 2,090 | ₹90,288 |
| 1.1 | Back Filling behind R/wall Abutment Wing wall Retaining wall with available stone from earthwork completed as per drawing and techinical specification clause 1204.3.8 labour rate (50% Earth and 50% Stone) | 244.06 | Cum | 578.15 | ₹1,41,103.29 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.29 MB
BOQ_234827.xls
BOQ • 0.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].