| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹38.1 LAccepted-AOC N A | NA | NA | 121004 | L1 | Accepted-AOC Lowest Quoted Bidder | |
| 2 | L2₹44.8 L+₹6.2 L (16.0%)Rejected-Finance | L2 | Rejected-Finance Other than Lowest | |
| 3 | L3₹49.4 L+₹10.8 L (27.9%)Rejected-Finance | L3 | Rejected-Finance Other than Lowest | |
| 4 | L4₹52.8 L+₹14.2 L (36.8%)Rejected-Finance RZ D 29A GALI NO 05 SYNDICATE ENCLAVE NEAR DABRI MORE NEW DELHI 110045 | SOUTH WEST DELHI | DELHI | 110045 | L4 | Rejected-Finance Other than Lowest | |
| 5 | L5₹53.0 L+₹14.4 L (37.3%)Rejected-Finance | L5 | Rejected-Finance Other than Lowest |
Tender Value
₹49 L
EMD Value
₹98,000
Closing Date
12 Jan 2024, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
GE WEST DELHI CANTT 10
GE WEST DELHI CANTT 10
REPAIR REHABILITATION OF RCC CHAJJA COLUMNS BEAMS ROOF CEILING AND PARAPET WALL AND COPING CHAJJA IN THE AREA OF AGE BR II UNDER GE WEST DELHI CANTT 10
2023_MES_618837_1
GE/DW-87/2023-24
Open Tender
Civil Works
Item Rate
180 days
DELHI CANTT
Please refer Tender documents.
8 documents required · 8 mandatory
₹500
GE WEST DELHI CANTT
₹98,000
9 Mar 2024
16 Dec 2023
15 Jan 2024
16 Dec 2023
12 Jan 2024
30 Dec 2023
Amount
Impregnating cream for injection into masonry or concrete wall 230mm thick against capilary rising humidity. Rising bar super strong Injection No. 306) of chowgale building chemicals or equivalent Pidilite/Dr fixit/Sika/Fosroc complete all as secified and directed. Method of Appliction. Methodology. (a) The surface must be sound. absorbent, clean, free of dust, oil, paint, curing agents, loose cement or lime plaster & concrete, debris or any separation layer. (b) The plaster must be knocked off at least 50 cm beyond the visibly penetrated area. (c) Damaged mortar joints are to be scraped out to a depth of approximately 2-3 cm. All sharp edges/Joints need to be levelled. Loose concrete to be removed. (d) Drill boreholes at ground level horizontally. The bore holes are drilled horizontally into the masonry. (e) The holes should be drilled until a depth of approx 5 cm (for a 6mm thick wall) befor the end of the wall is reached. The boreholes should have a diameter of 12mm upto a maximum of 15mm and should be spaced approx 100 to 120mm apart and the vertical offset is 6cm max. (f) Before inserting Rising bar super strong or equivalent the boreholes must be cleaned from boring dust by using air pressure. It is not necessary to pre-wet the boreholes. (g) For applying the rising bar super strong or equivalent the dosing system inserted as fas as possible into the boreholes. While dosing the product uniformy, the injection nozzle is pulled out leading to a completely filled boreholes. (h) Treatment of highly absorbent masonry might require repeated filling of the boreholes. Depending upon extent of damage. RisingBar Super Strong or equivalent can be re-injected in the same hole after 24 hours. Depending on absorbency, application or masonry thickness 0.1 to 0.15 litre/m with 10cm wall thickness.
PMM repairs (FOR PATCH REPAIRS) (i) Contractor or his authorised rep will report daily at 0900 hrs and onwards at complaint cell for collection of complaints from the concerned JE;s/MES rep and distribute to all complaints/ detailing to tradesman, monitoring the work done and taking the complaint slip from trademans on every working day and re-submit the same after rectifying the complaint at complaint cell, failing which a recovery of Rs 1000/- per day shall be recovered from the contractor's due payments.
25-30 mm average thickness ( in 2 layers) up to 8th floor level
50-60 mm average thickness ( in 3 layers ) up to 8th floor level
PMM repairs at 3 and 4 above shall be done as per following methodology (From sub items 6 to 11 below)
i) Chipping of plaster and unsound/weak concrete material till reinforcement bars are exposed, which enable their rust removal vides item ii) below, from slabs, beams, and columns etc. with standard power driven percussion type or pneumatic chisel of standard make as directed by Engineer-incharge including tapering all edges, making square shoulders of cavities etc complete and disposal of debris up for all lifts and leads .
ii) ) Rust removal by Providing and applying Fosroc Reebaklens RR or equivalnet from SIKA/ BASF, a combination of acid based material, corrosion inhibitors and dispersing agents rust remover, for removal of all rust/ scales/corrosion from reinforcement bars before microconcreting or patch repair,It Shall be applied with brush for complete wetting of rusted metal surface at coverage of 2- 2.5 Sqm/ltr. & allow it to react for 16-24 hours. After 24 hours, a white layer will appear which will protect further corrosion of metal /steel for about 5-7 days. Before applying any protective coating, the surface should be wire brushed and thoroughly cleaned for dust with dry cloth.
iii) Anticorrosive treatment by Providing and applying Nitozinc Primer an epoxy based zinc rich anti corrosive primer having adhesive bond strength ≥ 1.5 MPa as per ASTM D4541, & shall comply to per ASTM B-117 to be applied on well cleaned, fully exposed and all loose scale , rust free rust free surface obtained by grit blasting or suitable means , to be done with coverage @4.5sqm/litres to achieve a minimum thickness of 40microns DFT or as per direction of Engineer-In charge.
iv) Epoxy bonding for Old concrete & New concrete by providing and applying bond coat on the prepared surface with two component epoxy based bonding coat Nitobond EP of Fosroc make or equivalent, having specific gravity 1.15 to 1.2 gm/cc, Compressive strength(BS 6319 Pt.2)- 50 Mpa at 7 days, Flexural strength strength(BS 6319 Pt.3)- 35 Mpa at 7 days, Tensile strength (BS 6319 Pt.7)- 20 Mpa at 7 days, Shear Strength (BS 6319 Pt.4)- 10 Mpa at 7 days, having an over lay time of 6 hrs and 30 ̊C. Bonding agent shall have coverage not less than 2.5sqm/litres Laying of reinstatement polymer modified mortar or micro concrete shall be completed within the overlay time of bonding coat. Item rate is inclusive of materials all labour, tools and tackles. complete as per specification and as directed by Engg.-in-charge.
v) PMM by providing and laying single component, polymer modified, fibre reinforced cementitious repair mortar, Rendroc SP40 or equivalent from SIKA/BASF over the tacky bond coat, that achieves Compressive strength (BS 1881 Pt.116) > 20 MPa at 1 day , > 45 Mpa at 28 days, Tensile Strength > 2.5MPa, Flexural Strength > 7Mpa at 28 days, Finishing the same with trowel carefully compacting the same around the rebars and finishing to bring it in line with existing concrete surface on the beams, slabs, piles etc., complete in all aspect as per manufactur's methodology. Rates include cost of all labour, materials, Tools and Plants,propping, scaffolding, shuettering, safety arrangment, quality control, testing complete as per specifications and direction of engineer in charge.
vi) Item rates of PMM 25 mm and PMM 50 mm (against items 3 and 4 respectively ) are inclusive of all materials, labour, tools and plants, propping, scaffolding, safety arrangement, quality control, testing and all items of works from 6 to 10 above quality control etc. complete in all respect, as per specifications and as directed by Engg.-in-charge. Work shall be complete only after proper wet curing has been done by contractor and surface has been evaluated for satisfactory quality by sounding/tapping with a blunt metal instrument, and testing of PMM cubes filled up and cured by contractor during the application of PMM (75mm size cube crushing strength at the end of 28-day to be not less than 45 N/sqmm) in addition to NDT Testing as per under item of "Testing of works"
Rebar Fixing using Chemical Anchor up to 8th floor level Drilling suitable holes in reinforced cement concrete with power driven drill machine to a minimum depth of 10D(D-Dia of Bar in mm) in RCC beams, lintels, columns and slabs to introduce new steel bars including fixing the steel bars in position using Lokfix E75 a two-component epoxy anchoring material, supplied in 3:1 ratio having compressive Strength (EN196) >110 MPa, Flexural Strength (EN196) >40MPa, E Modulus (EN196) 10,800 MPa. or of equivalent make but excluding the cost of reinforcement, all complete as per direction of Engineer-In- Charge.
8mm Shear Connectors
Anchoring bars for 10mm Dia
Anchoring bars for 12mm Dia
MICROCONCRETING in Columns (for Repairs and Strengthening) up to 8th floor level
Providing and applying a non shrink, polymer modified cementitious micro-concrete Rendroc RG or equivalent from SIKA/BASF having compressive strength (BS 4551-80)-50 Mpa at 28 Days, Tensile strength- 2 Mpa @ 28 Days, Flexural Strength(BS 4551-80)-5 Mpa at 28 Days. product shall have A1 Class Fire Rating confirming to EN1504 cl 5.5, Thermal conductivity of 1.5W/m degree C. Renderoc RG can be applied in sections upto 100mm deep. Pouring the same into the formwork using suitable arrangement or if required using pumping device for uniform flow of micro concrete. Rate is inclusive of preparatory works from item 18 to item 22 below, rates also includes cost of materials labour, tools and plants, cost of shuttering & scaffolding, safety arrangement quality control and testing etc. complete as per specification and as directed by Engineer.-in-charge.
i) Chipping of plaster and unsound/weak concrete material till reinforcement bars to exposed to enable their rust removal vides item ii) below average thickness from slabs, beams, columns etc. with standard power driven percussion type or pneumatic chisel of standard make as directed by Engineer-incharge including tapering all edges, making square shoulders of cavities etc complete and disposal of debris up for all lifts and leads .
ii) Rust removal by Providing and applying Fosroc Reebaklens RR or equivalnet from SIKA/ BASF, a combination of acid based material, corrosion inhibitors and dispersing agents rust remover, for removal of all rust/ scales/corrosion from reinforcement bars before microconcreting or patch repair,It Shall be applied with brush for complete wetting of rusted metal surface at coverage of 2- 2.5 Sqm/ltr. & allow it to react for 16-24 hours. After 24 hours, a white layer will appear which will protect further corrosion of metal /steel for about 5-7 days. Before applying any protective coating, the surface should be wire brushed and thoroughly cleaned for dust with dry cloth.
iii) Anticorrosive treatment by Providing and applying Nitozinc Primer an epoxy based zinc rich anti corrosive primer having adhesive bond strength ≥ 1.5 MPa as per ASTM D4541, & shall comply to per ASTM B-117 to be applied on well cleaned, fully exposed and all loose scale , rust free rust free surface obtained by grit blasting or suitable means , to be done with coverage @4.5sqm/litres to achieve a minimum thickness of 40microns DFT or as per direction of Engineer-In charge.
iv) Epoxy bonding for Old concrete & New concrete by providing and applying bond coat on the prepared surface with two component epoxy based bonding coat Nitobond EP of Fosroc make or equivalent, having specific gravity 1.15 to 1.2 gm/cc, Compressive strength(BS 6319 Pt.2)- 50 Mpa at 7 days, Flexural strength strength(BS 6319 Pt.3)- 35 Mpa at 7 days, Tensile strength (BS 6319 Pt.7)- 20 Mpa at 7 days, Shear Strength (BS 6319 Pt.4)- 10 Mpa at 7 days, having an over lay time of 6 hrs and 30 ̊C. Bonding agent shall have coverage not less than 2.5sqm/litres Laying of reinstatement polymer modified mortar or micro concrete shall be completed within the overlay time of bonding coat. Item rate is inclusive of materials all labour, tools and tackles. complete as per specification and as directed by Engg.-in-charge.
v) Work will complete only after proper wet curing has been done and testing of Microconcrete cubes filled up and cured by contractor during column jacketing work (100 mm size cube crushing strength at the end of 28-day to be not less than 45 N/sq.mm) and NDT tests mandated under item "Testing of works"
PLASTERING on ceiling and outer walls and other structural elements upto a floor 8 level over PMM/shotcrete repairs or otherwise as replaster as per details given under sub items 24,25 and 26 below;
10 mm thick cement plaster of in the ratio of 1 cement and 4 clean sand zone III added with Polymer SBR @2% of cement weight, on ceiling over PMM repairs, shotcrete repairs or as replaster of damaged plaster including preparation of surface by demarketing of PMM repaired surface in regular shape or removal of damaged plaster, direction of engineer in charge.
15mm thick cement plaster in the ratio of 1 cement to 5 sand added with Polymer SBR @2% of cement weight over outer walls, columns or beams either over repaired surfaces like PMM , Microconcrete etc. including preparatory works like roughening of surface where required as per direction of engineer-in-charge
Rate quoted against this item vides sub items 24 and 25 above shall include all materials, labour, Tools and Plants, Scaffolding, safety arrangement and preparation of surface as mentioned vide 24 and 25 above complete in all respects as per specifications and direction of Engineer in charge
Guniting (for Repairs and Strengthening) up to 8th floor level
Dismantling loose concrete cover of RCC coloums, beams slabs, Chajjas, and the like as directed, roughening and cleaning concrete surfaces with steel wire brushes, washed with water and allowed to dry, including dusting of steel reinforcement, providing fabric mild steel wire mesh 75 mm x 75 mm of 2 mm dia as reinforcement to concrete surfaces, applying adhesive/admixture over steel mesh and providing 25 mm thick (average thickness) guniting mix (using 1 part of ordinary portland cement 53 grade and 2 parts of Badarpur sand mixed with adhesive/admixture at the rate as per manufacturers instruction or 2% by wt of cement all as directed with a pressure of 2 to 2.5 kgs per sqm by guniting machine and surfaces finished even and fair, including plaster to make proper Geographic shape as per site requirement, necessary padding, steel scaffolding and shuttering for working platform/formwork etc complete all as directed. Notes :- (i) Wherever steel reinforcement is required to be provided the same shall be measured separately under relevant item) (ii) Before placing the additional reinforcement all concrete surfaces shall be thoroughly scrubbed with brushes, washed with water and alllow to dry. To this prepared surface apply chemistic Zinc chromate primer at the rate of 2% by weight of cement or all as per manufacturers instructions. (iii) When plymix coating is in tackey condition guniting is done with plycrete admixture at the rate of 2% by weight of cement or all as per manufacturers instructions. Plycrete admixture shall be procured from Chemical Adhesive Pvt Ltd Co. or their authorized dealer. (iv) Cost of the above aspects shall be deemed to be included in the quoted rate of the respective item and nothing extra shall be paid on any account.
Demolition of Brick /stone walling built in cement mortor including all quoins ,coping etc complete all as specified and directed..
M&L Brick work with class `B’ bricks straight or curved on plan exc 6 M in radius using old size bricks built in CM 1:6 complete all as specified and directed.
All as per item no 30 above but except bricks.
M & L for framed work such as grills, grating etc with ends of bars shouldered or riveted, framed guard bars, barred iron doors, ladders, frame balusters, walk ways, railing and similar work conforming to Fe - 290 Ge E-165 etc complete all as specified and directed.
Material and labour for providing cement concrete type B1 1:2:4 (using 20 mm graded aggregate) as in cill, bands, copings, kneelers, apex stone, bed plates, kerbs and like incl weathering, slightly rounded or chamfered angles and throating incl demolition of cement concrete (unreinforced) of any description and in any position all as specified and directed.
Demolition of reinforced cement concrete of any description and in any position including rubbish removal out slide of rubbish of of the premises complete all as specified and directed.
M&L for pre-painted galvalume aluminum zinc coating GI based corrugated steel sheet 0.50mm thick of approved colour and circular in shape having tensile strength of 550 Mpa as in roof fixed with self tapping screws etc incl cutting chases if required complete all as specified and directed.
M&L mild steel framed work for sunshades, chajjas etc with angle iron welded together ends of angle shouldered and fixing of same to brick/concrete surfaces with necessary steel fasteners of required size and numbers as directed by Engr-In-Charge confirming to Fe-410-W (Gde-E-250) quality 'B' complete all as specified and directed.
M&L for preparation of new steel or iron surfaces of any description over 10 cm in width or girth not otherwise described and applying two coats of synthetic enamel paint over a coat of red oxide primer complete all as specified and directed.
M&L for Mild steel bars TMT 10mm dia and over, cut to length, bent to shape required, including cranking, bending spirally for hooping for columns, hooking ends and binding with and including mild steel wire (annealed) not less than 0.9mm dia or securing with clips complete all as specified & directed.
All as per item no 38 above but 6 to 8mm dia.
All as per item no 38 above but 5mm dia and over upto and including 10mm dia in stirrups, spacers and binders complete all as specified & directed.
Taking down cement plaster or any description including raking out joints, hacking for key, scrubbing down with water etc and removal of debris to a distance not exc 50 mts and depositing where directed.
M&L for 15mm thick ready mix plasatering mortar in CM (1:4) of approved make on wall surfaces, finish the surface even and smooth without using extra cement etc complete all as specified and directed.
M & L for preparation of newly plastered surface of walls and applying two coats of OBD over a coat of Primer alkali resistant over wall Putty of min 1mm thick uniform finish including cleaning of paint stains on floor/window/joinery surfaces, complete all as specified and directed complete all as specified and directed .
M&L for preparation of new plastered surface and applying two coats of weather proof exterior acrylic emulsion paint and a coat of primer of approved make & shade including necessary scaffolding/Ladder etc complete all as specified and directed.
M&L preparation of new plastered surfaces and applying two coats of cement base paint over a coat of primer on external surfaces of walls complete all as specified and directed.
M&L preparation of newly plastered surfaces of ceiling and applying two coats of OBD over a coat of primer all as specified and directed.
M&L preparation of newly plastered surfaces of ceiling and applying three coats of white wash all as specified and directed.
Deduct Credit: for demolished/dismantled material of (-) Rs 45750.00 (Minus) as listed in Schedule 'A' Part II (Credit Schedule) Note: Tenderer's shall not quote against this item. The amount of Credit Schedule is tentative, however the same shall be considered to arrive at the contract sum.
M/S Ayub Khan
M/s M M BAHL
SHREE RAM BUILD TECH
Maninder Singh Lohia
imran construction company
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .