| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹69.1 LAdmitted-Finance NAGPUR DIST NAGPUR | NAGPUR | MAHARASHTRA | 440001 | +2.15% | ₹69.1 L | L1 | Admitted-Finance |
| 2 | L2₹76.5 LAdmitted-Finance | +13.11% | ₹76.5 L | L2 | Admitted-Finance |
Tender Value
₹67.7 L
EMD Value
₹1.4 L
Closing Date
25 May 2026, 12:00 pmClosed
XEN OFD DIVISION-I CAD IGNP BIKANER
XEN OFD DIVISION-I CAD IGNP BIKANER
CONSTRUCTION OF PUCCA WATER COURSES IN BHAKHRA CANAL PROJECT ( AS PER CAD BSR 2024) CHAK 16 PBN-B -01
2026_CECAD_558970_1
NIT02/2026-2027
Open Tender
Civil Works
150 days
PILIBANGA
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,000
XEN OFD DIVISION-I CAD IGNP BIKANER/MD RISL
₹1.4 L
Yes
26 May 2026
15 May 2026
26 May 2026
15 May 2026
25 May 2026
15 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1.01 | Earth work for water courses in ordinary soil with all leads and lifts, undressed as per Specification. | 10,771.86 | Cubic Meter | 29.3 | ₹3,15,615.5 | BI01010001010000000000000515BI0100001113 |
| 1.02 | Dressing of Earth Work | 10,771.86 | Cubic Meter | 2 | ₹21,543.72 | BI01010001010000000000000515BI0100001118 |
| 1.03 | Ramming of Earth work for ordinary soil in layers by wooden or Iron rammers as per specification. | 10,771.86 | Cubic meter | 6.5 | ₹70,017.09 | BI01010001010000000000000515BI0100001123 |
| 1.04 | Watering, ramming and dressing of subgrade including removal of irregularities upto 15 cm(6inch) depth | 5,648.8 | Square Meter | 9.5 | ₹53,663.6 | BI01010001010000000000000515BI0100001128 |
| 1.06 | Brick masonry in cement mortar (1:5) including cost of all materials including mechanical mixing of mortar with all leads & lifts and stacking etc. complete in all respect. | 905.18 | cubic meter | 4,322 | ₹39,12,187.96 | BI01010001010000000000000515BI0100001138 |
| 1.07 | 10 mm thick cement plaster in cement mortar (1:4) as per design and specification including cost of all materials including mechanical mixing of mortar with all leads and lifts and stacking etc with curing for specified period complete in all respect. | 9,238.69 | Square Meter | 171.3 | ₹15,82,587.6 | BI01010001010000000000000515BI0100001143 |
| 1.08 | Earth work excavation in foundation trench in ordinary soil for structures and then refilling soil in 15 cm. layers with all leads and lifts | 1,555.09 | Cubic Meter | 29.3 | ₹45,564.14 | BI01010001010000000000000515BI0100001148 |
| 1.09 | cement concrete (1:4:8) including cost of all materials including mechanical mixer with aggregate size 40 mm with all leads and lifts and stacking etc. complete in all respect. | 55.9 | cubic meter | 3,153 | ₹1,76,252.7 | BI01010001010000000000000515BI0100001153 |
| 1.1 | Brick masonry in cement mortar (1:6) including cost of all materials including mechanical mixing of mortar with all leads and lifts and stacking etc. complete in all respect. | 107.19 | cubic meter | 4,304 | ₹4,61,345.76 | BI01010001010000000000000515BI0100001158 |
| 1.11 | 8 mm thick cement plaster in cement mortar (1:6) as per design and specification including cost of all materials including mechanical mixing of mortar with all leads and lifts and stacking etc. complete in all respect. | 471.39 | Square Meter | 154.4 | ₹72,782.62 | BI01010001010000000000000515BI0100001163 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.23 MB
ENIT2.pdf
Tender Documents • 3.61 MB
BOQ_995149.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid