| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.8 CrAccepted-AOC METRO HEIGHTS 2ND FLOOR SEVOKE ROAD SILIGURI | SILIGURI | ₹3.8 Cr | L1 | Accepted-AOC lowest bid |
| 2 | L2₹3.9 Cr+₹8.7 L (2.27%)Rejected-Finance 21 SISIR BAHADUR SARANI KHUDIRAM PALLY SILIGURI 734001 | SILIGURI | JALPAIGURI | WEST BENGAL | 734001 | ₹3.9 Cr+₹8.7 L (2.27%) | L2 | Rejected-Finance Quoted Higher Rate |
| 3 | L3₹4.0 Cr+₹19.5 L (5.12%)Rejected-Finance RANGLI RANGLIOT TEA GARDEN DARJEELING | DARJEELING | DARJEELING | WEST BENGAL | ₹4.0 Cr+₹19.5 L (5.12%) | L3 | Rejected-Finance Quoted higher Rate |
Tender Value
₹3.8 Cr
EMD Value
₹7.6 L
Closing Date
8 Apr 2025, 4:00 pmClosed
Executive Engineer,Bijanbari Engineering Division
Lowis Jublee Complex, Darjeeling.
Construction of road from Gairi Gaon, Simbongdera Mazuwa, Darjeeling, GTA (3.50Km).
2025_GTA_828351_1
GTA/EE/BED/NIeT-94/2025
Open Tender
CIVIL WORKS
Percentage
Darjeeling
Pre Qualification Form X,Y, Declaration, EMD.
2 documents required · 2 mandatory
₹2,505
₹7.6 L
21 Sept 2026
18 Mar 2025
10 Apr 2025
18 Mar 2025
8 Apr 2025
18 Mar 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m In mixed hard soil (i,e hard moorum and soil containing laterite and boulders which do not require blasting) | 2,445.25 | Cum | 130.98 | ₹3,20,278.85 |
| 2 | Earthwork in cutting to form road section in correct profile in ordinary soil including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m | 1,956.2 | Cum | 95.22 | ₹1,86,269.36 |
| 3 | Excavation in Hard Rock (blasting prohibited) Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines,grades and cross sections as per Clause 301 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (Mode of measurement: pre works and post works) | 489.05 | Cum | 529.16 | ₹2,58,785.7 |
| 4 | Construction of dry rubble flooring at cross drainage works for relatively less important works. | 2,027.81 | Cum | 3,176.15 | ₹64,40,638.26 |
| 5 | Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with cement content as per IRC:15-2011, coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batch mix plant / RMC and appropriate weigh batcher using approved mix design (as per IRC:44 2008), laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates spreading the concrete with shovels, rakes,compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, polysulphide sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 for Rural Roads. | 2,433.37 | Cum | 6,592.18 | ₹1,60,41,213.05 |
| 6 | Hire and labour charges for shuttering with or without staging upto 4.0 m height using approved stout props with wooden planks/ply wood/steel sheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert, crossdrain etc. The rate is inclusive of fitting, fixing and striking out after completion of work as per specification and direction. | - | Sqm | 421.9 | - |
| 7 | Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause 1104 for Rural Roads of MORD including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling
with approved material. | 704.1 | Cum | 135.9 | ₹95,687.19 |
| 8 | Plum Concrete work with 40 % Cement Concrete with 30 mm down graded stone metal and 60% stone boulder of size 150 mm and above, placed in position as directed excluding shuttering if any.(i) (1:3:6) proportion. | 1,055.94 | Cum | 3,937.71 | ₹41,57,985.5 |
| 9 | Hire and labour charges for shuttering with or without staging upto 4.0 m height using approved stout props with wooden planks/ply wood/steel sheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert, crossdrain etc. The rate is inclusive of fitting, fixing and striking out after completion of work as per specification and direction. | 1,069.94 | Sqm | 255.05 | ₹2,72,887.18 |
| 10 | Providing weep holes in Brick masonry / Plain /Reinforced concrete abutment, wing wall / return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V:20H towards drawing face. Complete as per drawing and Technical specifications. | 996 | No | 139.44 | ₹1,38,882.24 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
BOQ.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .