| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹11.3 L+₹1.5 L (14.9%)Rejected-Finance | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | J Sankaran L1 | Perumal S L2 |
|---|---|---|---|---|---|
| 1.01Construction of RCC 1.5M slab culvert @ PUP School in Kurur panchayat | |||||
| 1.02 | Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and boiling out water whenever necessary et complete complying with. | 119.63 | m3 | 255 ₹30,505.65 Lowest | 1,255 ₹1,50,135.65 |
| 1.03 | Cement Concrete 1:4:8 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed. | 6.19 | m3 | 5,363.88 ₹33,202.42 Lowest | 6,000 ₹37,140 |
| 1.04 | Cement concrete 1:3:6mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete . | 52.39 | no | 5,640.24 ₹2,95,492.17 Lowest | 5,640.24 ₹2,95,492.17 Lowest |
| 1.05 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete . | 3.36 | no | 6,673.99 ₹22,424.61 Lowest | 6,673.99 ₹22,424.61 Lowest |
| 1.06 | Supplying and Fabricating and placing in position MS Steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and blinding wire all floors etc., complete complying with standard specification. | 0.3 | m3 | 89,666.2 ₹26,899.86 Lowest | 89,666.2 ₹26,899.86 Lowest |
| 1.07 | Supplying and Erection centering for sides and soffiots including necessaary supports and strutting as directed by the departmental officers. Rate for 10m2 for the following items (RCC floor slab, roff slab, Rectangular / Square, Tee/ Ell beams, Lintels, | 114.45 | m3 | 544.19 ₹62,282.55 Lowest | 544.19 ₹62,282.55 Lowest |
| 1.08 | Rainforcement Cement Concrete 1:1.5:3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of reinforcement and fabricating charges, centering and shuttering but icluding curing and providing fixtures like fan clamps in the RCC floor or roof s | 3.31 | m2 | 9,012.49 ₹29,831.34 Lowest | 9,012.49 ₹29,831.34 Lowest |
| 1.09 | Provision for name board charges | 1 | m3 | 1,300 ₹1,300 Lowest | 1,300 ₹1,300 Lowest |
| 1.10 | Provision for photo charges | 1 | m3 | 1,000 ₹1,000 Lowest | 1,000 ₹1,000 Lowest |
Tender Value
₹10 L
EMD Value
₹10,000
Closing Date
12 Dec 2025, 3:00 pmClosed
BDO(VP), Merkanam Block
Merkanam Block
Construction of Culvert Near PUP School and KMR Nagar in Kurur Panchayat
2025_RDTN_629045_2
Merkanam/PMAGY-2025-26/P-5
Open Tender
Civil Works
Works
90 days
Block Development Office, Merkanam.
Merkanam/PMAGY-2025-26/P-5
3 documents required · 3 mandatory
₹0
₹10,000
Yes
14 Jan 2026
9 Dec 2025
12 Dec 2025
9 Dec 2025
12 Dec 2025
9 Dec 2025
Amount
Construction of RCC 1.5M slab culvert @ PUP School in Kurur panchayat
Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and boiling out water whenever necessary et complete complying with.
Cement Concrete 1:4:8 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:3:6mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete .
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete .
Supplying and Fabricating and placing in position MS Steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and blinding wire all floors etc., complete complying with standard specification.
Supplying and Erection centering for sides and soffiots including necessaary supports and strutting as directed by the departmental officers. Rate for 10m2 for the following items (RCC floor slab, roff slab, Rectangular / Square, Tee/ Ell beams, Lintels,
Rainforcement Cement Concrete 1:1.5:3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of reinforcement and fabricating charges, centering and shuttering but icluding curing and providing fixtures like fan clamps in the RCC floor or roof s
Provision for name board charges
Provision for photo charges
Construction of RCC 1.5M slab culvert @ KMR Nagar in Kurur panchayat
Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and boiling out water whenever necessary et complete complying with.
Cement Concrete 1:4:8 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:3:6mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete .
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete .
Supplying and Fabricating and placing in position MS Steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and blinding wire all floors etc., complete complying with standard specification.
Supplying and Erection centering for sides and soffiots including necessaary supports and strutting as directed by the departmental officers. Rate for 10m2 for the following items (RCC floor slab, roff slab, Rectangular / Square, Tee/ Ell beams, Lintels,
Rainforcement Cement Concrete 1:1.5:3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of reinforcement and fabricating charges, centering and shuttering but icluding curing and providing fixtures like fan clamps in the RCC floor or roof s
Provision for name board charges
Provision for photo charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Perumal S (BID ID -1531843)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.77 MB
BOQ_753718.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .