| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.6 CrAdmitted-Finance 11TH FLOOR ECO CENTRE BUSINESS TOWER P NO 4 EM BLOCK SECTOR V KOLKATA 91 | KOLKATA | 24 PARAGANAS NORTH | WEST BENGAL | 700091 | -0.25% | ₹2.6 Cr | L1 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Blue Star Limited L1 |
|---|---|---|---|---|
| 1.00Non BSR ITEM | ||||
| 2.00Supply, installation, testing and commissioning of factory fabricated Double Skinned DX Coil Air- handling unit fabricated out of extruded aluminium section with 0.8mm pre-plasticized / pre-coated Galvanised steel sheet outside & 0.8 mm polished SS sheet inside complete with supply & exhaust blower section with single / multiple AMCA certified backward curved plug fan with aerofoil design blades, VFD with built in harmonic filters for both supply & exhaust fan motor, power control panel with necessary switchgears incoming & outgoing for VFD, HRW & humidifier, blower suitable for static pressure as required (Fan Static given below is for guideline), blower motor TEFC (IE3) type suitable for operation on 415 volts ± 10%, 50 Hz ± 5% AC supply, 8 row cooling & 2 row heating coil made of Aluminium finned Copper tube, Copper header with coil section, pre-filter section with non woven synthetic media MERV 8 filters in extruded aluminium frame in both the supply & exhaust side of AHU, fine filter section with MERV 13 filters in extruded aluminium frame in supply after fan, (Hepa filters shall be at terminals along with laminar flow plenum & not to be included in the cost), Heat Recovery Wheel with HRW Section, mixing chamber, polished stainless steel drain pan made out of 22 G sheet duly insulated etc. without face and bypass dampers, coilotron UV section only of 600 mm in length in floor mounted AHU (Coilotron UV System quantified separately). The AHU panels shall be insulated with 48mm thick & 36 Kg/m³ density PU foam & shall have thermal break. The motor & blower assembly shall be mounted on Aluminium extruded section only. These AHUs shall have air inlet / outlet connection made of aluminium 20 G & all fixing arrangement / blank off shall be of SS The complete AHU shall conform to standard specication. The face velocity across cooling / heating coil shall be limited to 152 MPM maxm. The capacity of Air-handlers shall be as follows: | ||||
| 3.00 | 2800 CFM (7.0 TR ) ESP - 120 mm FOR OT-01+02 1st FLOOR | 2 | Nos. | 3,17,106 ₹6,34,212 Lowest |
| 4.00 | 2000 CFM (5.0 TR ) ESP - 120 mm FOR OT-03+04 1st FLOOR | 2 | Nos. | 3,91,626 ₹7,83,252 Lowest |
Tender Value
₹2.4 Cr
EMD Value
₹4.9 L
Closing Date
8 Jun 2026, 6:00 pmClosed
Executive Engineer Medical and Health Div Churu
Executive Engineer Medical and Health Div Churu
HVAC WORK AT CONSTRUCTION OF Sub DISTRICT- HOSPITAL IN RAJGARH (CHURU) , RAJASTHAN
2026_MEDIC_564460_1
NIT 03/2026-27 EE MH Churu
Open Tender
Electrical Works
Percentage
60 days
Churu
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,000
Executive Engineer Medical and Health Div Churu
₹4.9 L
8 Jul 2026
3 Jun 2026
9 Jun 2026
3 Jun 2026
8 Jun 2026
3 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Supply , Installation, Testing and Comissioning of factory assembeled double skin central evaporative cooling plant having specifications as per A, B, C, D, E | - | - | - | - |
| 2 | A. Air washer comprising of 2nos Pre-Filters. First filter shall be 50mm thick Aluminium wiremesh filter & second filter shall be 50 mm thick MERV-8 synthetic media filter with efficiency 90 % down to 10 microns. Both filters to be placed over the common frame. | - | - | - | - |
| 3 | B. Humidification section comprising of Wet pads 200 mm thick impregnated cellulose paper media ( Celdec pads ) with 2 bend PVC eliminator. The End plates of Pad & Eliminator shall be in SS 304 construction. Also, the inner blank offs of Wet section shall be in SS304 construction. | - | - | - | - |
| 4 | C. Fan Section comprising of belt driven, DIDW Backward curved AMCA certified centrifugal fan with maximum air outlet velocity of 10m/s suitable for required cfm at 50 mm static pressure (Total static of the unit shall be verified by the OEM before the design & supply of the units). Fan & Motor should be mounted over Aluminium channel of suitable thickness and should be isolated from the unit's bottom panel by means of Spring isolators. | - | - | - | - |
| 5 | D. TEFC High efficiecny IE-3 class motors as required with pulley, belt , Guard | - | - | - | - |
| 6 | E. The unit shall be fabricated with frame work hollow extruded aluminium profile with 0.80 mm preplasticised GSS on outside and 0.80mm 275gsm plain GSS on inside complete with 25 mm thick CFC free PUF insulation of minimum 40 kg/cum density sandwiched in between inner and outer skins. Unit should have MS powder coated legs to give height to unit's base channel from the floor surface. SS-304 ( 18 g ) Sump, UPVC Internal piping, make up, drain & quick fill and drain connection, Butterfly/Gate valves for pumps, make up, drain & quick fill and drain connections of sump, 2 no. Vertical Pumps of suitable capacity to be placed inside the unit's housing (external pumps are not acceptable) ,Y strainers and necessary fittings, Concrete Blocks / M S stand, anti vibration pads etc.as required. All as per pre approved by Engineer in charge. | - | - | - | - |
| 7 | 15000 CFM | 45,000 | per cfm | 26 | ₹11,70,000 |
| 8 | 20000 CFM | 20,000 | per cfm | 23 | ₹4,60,000 |
| 9 | SITC of Wall mounting cubical type Starter panel made out of 1.6 mm thick sheet steel powder coated enclosure designed as per Switchgear OEM type -2 coordination chart and suitable for operation of following cfm range Air Washer's Blower motor, pump comprising of over load protection relay, short circuit & single phasing protection, ON / OFF push buttons, ammeter, voltmeter, indicating lamps, MCB etc. complete in all respect. All as per pre approved by Engineer in charge. | - | - | - | - |
| 10 | 20000 CFM | 1 | Each | 32,394 | ₹32,394 |
stage.html
html • 0.02 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.51 MB
BID_HVAC.pdf
Tender Documents • 14.97 MB
BOQ_1004581.xls
BOQ • 0.44 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .