| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹65.6 LAccepted-AOC 207 A KARKARDOOMA GALI NO 17 NEW DELHI 92 | NEW DELHI | EAST DELHI | DELHI | 110092 | ₹65.6 L | L1 | Accepted-AOC First Lowest |
| 2 | L2₹65.8 LRejected-AOC D 151 SHYAM PARK EXTENSION SAHIBABAD GHAZIABAD | GHAZIABAD | GHAZIABAD | UTTAR PRADESH | ₹65.8 L | L2 | Rejected-AOC Second Lowest |
| 3 | Rejected-Technical OPPOSITE POLICE STATION MUSSORIE NH 24 DISTRICT GHAZIABAD | GHAZIABAD | GHAZIABAD | UTTAR PRADESH | - | - | Rejected-Technical Technically Not Qualify |
| 4 | Rejected-Technical | - | - | Rejected-Technical Technically Not Qualify |
Tender Value
₹78.4 L
EMD Value
₹1.6 L
Closing Date
12 May 2026, 2:00 pmClosed
General Manager, UPPCL, Zone-6 Noida
K-2, Sector-116, Noida Gautambudha Nagar
Construction work of Dormitory (16 capacity) at District Jail Ghaziabad in District Ghaziabad
2026_UPPRC_1143569_1
21/PCL/GM/Zone-6/Noida/2026-27 Dt 28.04.2026
Open Tender
Civil Works
Percentage
180 days
District Jail Ghaziabad in District Ghaziabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹11,800
₹1.6 L
13 Jul 2026
29 Apr 2026
12 May 2026
29 Apr 2026
12 May 2026
29 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | CIVIL WORK
Excavation of foundation in ordinary soil (loam clay or sand) including lift upto 1.50 meter and lead upto 30 meter and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of sur-plus earth as directed by the Engineer incharge up to a distance of 30 meters from the foundation trenches. | - | CUM | 194.19 | - |
| 2 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. | - | CUM | 522.6 | - |
| 3 | Providing and laying in position ready mixed or site batched design mix cementconcrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete.Concrete of M10 grade with minimum cement content of 220 kg /cum | - | CUM | 6,591.33 | - |
| 4 | Sand filling in plinth under floors including watering, ramming, consolidating and dressing complete including lead up to 50m and lift upto 1.5m and including cost of sand. | - | CUM | 1,584.39 | - |
| 5 | Providing and injecting chemical emulsion for preconstructional antitermite treatment and creating a chemical barrier under and alround the column pits wall trenches basement excavation top surface if plinth filling junction of wall and floor, along the the external perimeter of binding expansion joints, surrounding of pipes and conduits etc, complete (plinth area of the building at ground floor only shall be measured as per I.S.6313(PartII 1981)Alderine emulsifiable concentrate or any other approved material such as Heptrachlor or Chlordane will be used. The rate of application of chemical emulsion shall be as follows : (1)Treatment for masonary & foundation 5 liters per sqm. (2) Back fill in immediate contact with foundation 7.5 liters/sqm (3) Treatment of top surface of plinth filling 5 liters/sqm (4)Treatment junction of wall and the floor 7.5 liters /sqm (5)Treatment of soil along external perimeter of building 7.5 liters/sqm. (6) Treatment of soil under apron along external perimter 5 liters/sqm. (As per manufacturer's standard dilution) | - | SQM | 231.31 | - |
| 6 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-lll) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) Ground floor | - | CUM | 6,748.44 | - |
| 7 | First floor | - | CUM | 8,583.5 | - |
| 8 | As in item no. 6 above but for slabs (Using 1:1.5:3(1 cement : 1.5 coarse sand : 3 stone aggregates) Mix concrete) (M-20)Ground floor | 1 | CUM | 8,583.5 | ₹8,574.92 |
| 9 | First floor | - | CUM | 8,583.5 | - |
| 10 | As in item 6 but for the lighter beams i.e. having spans upto 6 m. (Using 1:1.5:3(1 cement : 1.5 coarse sand : 3 stone aggregates) Mix concrete) (M-20)Ground floor | 1 | CUM | 8,583.5 | ₹8,574.92 |
stage.html
html • 0.05 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.09 MB
Tender21.pdf
Tender Documents • 3.53 MB
DGZB.pdf
Additional Documents • 3.71 MB
BOQ_2136246.xls
BOQ • 0.59 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].