Loading…
Loading…
Tender Value
₹2.3 L
EMD Value
₹4,560
Closing Date
26 Aug 2026, 5:00 pm2d left
Ashok Kumar
Municipal Committee Meham
IPB Work, drain , brick work etc
2026_HRY_542226_1
202607A7DC09 FCA1 4AF5 9CA8 7A4D9696AEDC317ULB
Open Tender
Civil Works
Works
70 days
Meham
Recall CONST OF STREET AND DRAIN FROM SANDEEP TO BIJENDER
2 documents required · 2 mandatory
₹500
₹4,560
Yes
20 Aug 2026
20 Aug 2026
27 Aug 2026
20 Aug 2026
26 Aug 2026
20 Aug 2026
20 Aug 2026 - 22 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | [10.7]Providing and laying of conglomerate floor 50mm thick cement concrete topping 1:2:4 [Through Rate] | 1 | Sqm | 216 | ₹215.78 |
| 2 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] | 1 | Sqm | 113 | ₹112.89 |
| 3 | [17.15.2]Granular Sub-Base with Coarse Graded Material - Grading-I or II or III (Table:- 400-2)
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORTandH specifications 2. Grading II material [Through Rate] | - | cum | 1,044 | - |
| 4 | [17.69.2]Interlocking Concrete Block Pavement 2. Providing and Laying 80 mm thick ISI marked Interlocking Paver Blocks conforming to IS 15658:2006/IRC SP 63: 2004 of all shapes and colours in design mix cement M 40 over the bed of 30 mm thick fine sand complete in all respect. [Through Rate] | 1 | Sqm | 655 | ₹654.35 |
| 5 | [17.8.1]Compaction 1. Extra for laying earth/fly ash as per specifications in 20 cm layers and dressing but excluding the cost of rolling [Through Rate] | - | cum | 48 | - |
| 6 | [17.8.2]Compaction 2. Extra for watering the earth/fly ash laid in 20 cm layers as per specifications [Through Rate] | - | cum | 27 | - |
| 7 | [17.8.3]Compaction 3. Extra for rolling to specifications [Through Rate] | - | cum | 27 | - |
| 8 | [2.HO001] HO001. Royalty for good earth [Rate] | - | cum | 36 | - |
| 9 | [21.53]Constructing standard drain type I drain moulded and laid over lime concrete foundation rendered and finished smooth with 6 mm thick rendering concrete to be of 1.3.6 parts by volume of cement sand stone bajri and rendering to be 1:1 cement sand mortar [Through Rate] | - | Metre | 160 | - |
| 10 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km] | - | cum | 83 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.77 MB
BOQ_621692.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].