| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹78.5 LAccepted-AOC 154 I C C T P NAGAR KORBA CG 495677 | KORBA | CHHATTISGARH | 495677 | ₹78.5 L | L1 | Accepted-AOC Technically and Financially eligible L1 Bidder. |
| 2 | L2₹79.9 L+₹1.4 L (1.76%)Rejected-Finance BHAIROTAL SURAKACHHAR TEH KATGHORA KORBA CHHATTISGARH 495454 | KORBA | KORBA | CHHATTISGARH | 495454 | ₹79.9 L+₹1.4 L (1.76%) | L2 | Rejected-Finance Not L1 Bidder |
| 3 | Rejected-Technical 120 RAMAYAN KOSABADI DIST KORBA CHHATTISGARH 495677 | KORBA | CHHATTISGARH | 495677 | - | - | Rejected-Technical Checked and Reject by the tender committe |
Tender Value
₹1.1 Cr
EMD Value
₹1.4 L
Closing Date
16 Nov 2023, 5:00 pmClosed
STAFF OFFICER (CIVIL), KORBA AREA
Office of the General Manager, South Eastern Coalfields Limited, CIVIL DEPARTMENT, KORBA AREA KORBA- 495 677(CG), Mo-9425533108/ 7587390644
Construction of Cement Concrete Road (Rigid Pavement) from Main Road to Boom Barrier Shed at Saraipali OCP of Korba Area.
2023_SECL_292339_1
SECL/GM/KA/C/e-Tender/23-24/31 Dt. 30.10.2023
Open Tender
Civil Works - Roads
Item Rate
180 days
Office of the General Manager Korba Area
As per NIT
5 documents required · 5 mandatory
₹1.4 L
2 Apr 2024
31 Oct 2023
18 Nov 2023
1 Nov 2023
16 Nov 2023
1 Nov 2023
1 Nov 2023 - 9 Nov 2023
Amount
Granular Sub-base with Well Graded Material (CBR>30 or more (Table:- 400-1 & Table 400-2) Construction of granular sub-base by providing well graded material like natural sand crushed gravel or crushed stone having CBR >30, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator or plant mix method at OMC, and compacting with vibratory rollers of 80 to 100 kN static weight to achieve the desired density, complete as per Clause 401 of Specification.
Wet Mix Macadum:-Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying inuniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density in accordance to Table No. 400-12, 400-13 and as per clause of section 406 of specifications
Dry Lean Cement Concrete sub base :-Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing as per clause 601 of specification complete in all respect.
Cement Concrete Pavement: Construction of un-reinforced, dowel jointed, plain cement concrete pavement M-40 grade concrete over a prepared sub base with cement , coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, admixtures as approved, curing compound, finishing to lines and grades as per drawing as per IRC 15 2011 and as per relevant clauses of section 602 of specifications complete but excluding cost of steel in dowel bar and tie rods etc.
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical Specification and as per relevant clauses of sections 1500, 1700 and 2300 :in RCC Grade M20
Painting on concrete surface:- Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m.
Add extra in item no. 6.3, 6.4 ,6.6 & 6.10 above for the cost of steel in dowel bar and tie rod including craddle, laps etc complete required as per design. Mild steel
Add extra in item no. 6.3, 6.4 ,6.6 & 6.10 above for the cost of steel in dowel bar and tie rod including craddle, laps etc complete required as per design. TOR steel
Total impact of GST for the purpose of CTC
M/S GOYAL GROUP
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .