| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹91.8 LAccepted-AOC 41 21 A KMC TOWERS C2 C2 SCHEME ROAD THENI 625531 | THENI | TAMIL NADU | 625531 | ₹91.8 L | 1 | Accepted-AOC Lowest tenderer |
| 2 | 2₹93.1 LRejected-AOC 17 NETHAJI ROAD MADURAI 625001 | MADURAI | TAMIL NADU | 625001 | ₹93.1 L | 2 | Rejected-AOC . |
| Sl No | Description | Qty | Unit | KMC Associates, Theni L1 | SHRI PRAKASH INFRA L2 |
|---|---|---|---|---|---|
| 1.00Road | |||||
| 1.01 | Clearing Scrub Jungle with uprooting including all cutting charges and depositing of the products and clearing as directed by the departmental officers including all labour charges etc., complete. | 2,088 | sqm | 6.3 ₹13,154.40 | 6 ₹12,528 |
| 1.02 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. | 937.76 | Cum | 140.4 ₹1.3 L | 142 ₹1.3 L |
| 1.03Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS | |||||
| 1.04 | Km 0/0 - 1/0 | 229.58 | Cum | 569.2 ₹1.3 L | 578 ₹1.3 L |
| 1.05 | Km 1/0- 1/8 | 192 | Cum | 569.2 ₹1.1 L | 578 ₹1.1 L |
| 1.06 | Picking the existing metal surface 7.5 cm much removing the picked up stuff to the sides, collection all useful metal leveling and sectioning top camper power roller ansolidation by power roller etc., | 1,794.93 | Sqm | 23.3 ₹41,821.87 | 23 ₹41,283.39 |
| 1.07 | Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) . | 539.5 | Cum | 2,358.7 ₹12.7 L | 2,397 ₹12.9 L |
| 1.08 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5 | 809.25 | Cum | 2,411.7 ₹19.5 L | 2,451 ₹19.8 L |
| 1.09 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 5,395 | sqm | 87.18 ₹4.7 L | 88 ₹4.7 L |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
20 Feb 2026, 3:00 pmClosed
Project Director
1st floor, DRDA, Theni
Strengthening of Road from Nagalapuram - Balakrishnapuram Road Km 0/0 - 1/800(R-58) including 5 years maintenance in Theni Block of Theni District under NABARD RIDF 2026-2027
2026_RDTN_657106_1
294/2026/D4 Date 12.02.2026
Open Tender
Civil Works - Roads
180 days
Theni
As per tender documents
3 documents required · 3 mandatory
₹0
₹1.1 L
1st floor, DRDA, Theni
10 Mar 2026
13 Feb 2026
20 Feb 2026
13 Feb 2026
20 Feb 2026
13 Feb 2026
16 Feb 2026
Clearing Scrub Jungle with uprooting including all cutting charges and depositing of the products and clearing as directed by the departmental officers including all labour charges etc., complete.
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Picking the existing metal surface 7.5 cm much removing the picked up stuff to the sides, collection all useful metal leveling and sectioning top camper power roller ansolidation by power roller etc.,
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying Bituminous Concrete to 25mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20 mm high at centre, 250 mm wide placed at 1 m centre-to-centre at approved locations to control speed, marked with white strips of road marking paint.
Supplying and Fixing of HM stone etc 0.65 x 0.15 x 0.10
Supplying and Fixing of KM stone etc 1.26 x 0.35 x 0.25
Retro- Reflectarised Traffic Signs ( With definition board ) Type IV
60cm Equilatral Triangle Sign Board
80cm x 60cm Rectangular Board
Construction of Retaining Wall at Ch 1200 m
Earth work excavation for foundation in all soils and sub-soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring, strutting and bailing out water wherever necessary and refilling the sides of foundation with
Plain Cement Concrete 1:4:8 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Cenetering Shuttering including necessary support for plane surface in foundation and Basement and in all floors usingmild steel sheets of size 90x60 cm and 10 gauge stiffened , welded with steel angles of size 25mmx 25mmx3mm for boarding laid over silver
Plain Cement Concrete in CM 1 : 3 : 6 mix using 40 mm gauge hard brocken granite stone jellay for foundation including watering wherever necessary and laid in layers not more than 15 cm thick compacting et., complete complying with standard specification
Provision for PVC Pipe for Wheep holes
Construction of Cause Way Wearing Coat at Ch 250 m
Centering shuttering including necessary support for plane surface in Foundation and Basement and in all floors using mild steel sheets of size 90x60 cm and 10 gauge stiffened, welded with steel angles of size 25mmx25mm x3mm for boarding laid over silver oak (country wood) joints of 10cm size x6.5cm size spaced at about 90 cm center to center and supported casuarina props of 10 cm to 13 cm dia spaced at 75 cm center to center complete complying with standard specification.
Construction of Un-Reinforced ,dowel jointed at expansion and Construction joint only,plain cement concrete pavement thickness as per design,over a prepared sub base,with 43 grade cement or any other type as per clause 1501.2.2 M30 (Grade),Coarse an
Supply and Fixing of Bitumen Pad
Maintenance of the road
Towards the charges for routline maintenance of the road work executed under NABARD including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.30 MB
Tendernotice_2.pdf
PDF • 0.66 MB
BOQ_788011.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid