| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹21.5 LAccepted-AOC | 1 | Accepted-AOC bid qualified |
Tender Value
Refer Docs
EMD Value
₹69,500
Closing Date
17 Feb 2021, 12:00 pmClosed
Executive Engineer
Irrigation Division Ganga Sinchai Bhawan Telibagh Lucknow
REPAIRING Of V.R.B./P.R.B./D.R.B. FROM K.M.104.150 TO K.M.119.680 OF S.S.F.C.
2021_UPIDC_548622_3
06/EE/2020-21 (LOT 1)
Open Tender
Civil Works - Canal
Item Rate
30 days
Sharda shayak Feeder Channal
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹69,500
Yes
19 Jul 2021
12 Feb 2021
17 Feb 2021
12 Feb 2021
17 Feb 2021
12 Feb 2021
12 Feb 2021 - 17 Feb 2021
Amount
Demolishing R.C.C. manaually /by mechanical means including disposal of material within 50 mtr
Demolishing Brick work manaually /by mechanical means including stacking of serviceable mmaterial and including disposal of unserviceablematerial within 50 mtr lead
Removing of mortar frok bricks and cleaning bricks including stacking within a lead of 50 mtr( stacks of clean bricks shall be measured)
Drilling Suitable holes in reinforced or Plain Cement Concrete with power driven drill machine to a minimum depth of 100 mm up to 200 mm in R.C.C. or P.C.C. to introduse steel bars including fixing the steel bars in position using epoxy resin anchor grout approved make but excluding the cost of reinforcement , all complete.
Bending,Binding,Cutting and Placing in position reinforcement including all cost of labour and material T&P etc. required for porper completion of the work/MT.
Centring and shuttering For R.C.C. Work including rent of shuttering & all cost of labour and material T&P etc. required for porper completion of the work/M2.
Laying Reinforced Cement Concrete in foundation , wall, slab etc. in 1:1.5:3 with stone grit including cost of material, labour, T&p etc, complete.
Class 150 Brick work in 1:4 CM including 3 M lift and 60 M lead including all cost of material, labour, T&P etc. complete.
Brick work using old brick in 1:4 CM including 3 M lift and 60 M lead including all cost of material, labour, T&P etc. complete.
Struck deep pointing on B.W. with 1:3 cement mortar including all cost of Material labour T&P etc for proper completion of work.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .