₹3,148
Closing Date
10 Mar 2020, 6:55 pmClosed
Executive Engineer
Executive Engineer RCC Lower Division Hiranagar
Construction of Tractor Crossing on Main Ujh Canal RD 6090M
2020_IFC_94116_2
e-NIT No. 11 of 2019-20
Open Tender
Civil Works - Canal
Item Rate
25 days
Hiranagar
As per SBD
2 documents required · 2 mandatory
₹600
Executive Engineer RCC Lower Division Hiranagar
₹3,148
Executive Engineer RCC Lower Division Hiranagar
14 Mar 2020
3 Mar 2020
11 Mar 2020
3 Mar 2020
10 Mar 2020
3 Mar 2020
3 Mar 2020 - 7 Mar 2020
7 Mar 2020
Amount
Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (Not exceeding 1.5 mtr in width) and for shafts, wells, cesspits and the like not exceeding 10sqm on plan, depth upto 1.5mtr. Including disposal of excavated earth upto 1mtr from cutting edge, disposed earth is to be levelled and neatly dressed in: All kind of soil
Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level. 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate 40mm nominal size) (A) Crushed
Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level.: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size) : Crushed
Dumping stone excluding cost of stones.: In Horizontal on level
Dry stone pitching (any thickness) excluding cost of stones. a) On Horizontal
Grouting of stone pitching using M-1 0 nominal mix concrete (max. size of aggregates; 20mm nominal) @ 3.65 cum per 100 sq m on horizontal/side slopes; complete including curing. (a) Crushed
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering -All work upto plinth level 1:2:4(1 cement:2coarse sand:4graded stone aggregate 20mm nominal size i:Crushed
Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centenng. shuttering, finishing and reinforcement-All work upto plinth level. 1:2"4 (1 cement: 2 coarse sand: 4 graded stone aggregate 20mm nominal size)
Reinforcement for R.C.C. work including straighteing, cutting, bending, placing in position and binding all complete. Cold twisted bars
Centring and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns etc. for mass concrete.
Centring and shuttering including strutting, propping etc. and removal of form for : Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc.
Centring and shuttering including strutting, propping etc. and removal of form for : Suspended floors, roofs, landings, balconies and access platform.
Centring and shuttering including strutting, propping etc. and removal of form for : Edges of slabs and breaks in floors and walls
Supply of Nallah stones
Carriage of Materials from Source to site of work Carriage of sand and stone agg. Below 40mm av. 7 Km by Mechanical Transport
Carriage of Materials from Source to site of work Carriage of Nallah Stone av. 5 Kms by Mechanical Transport
Earth work in rough excavation, banking excavated earth in layers not exceeding 20 em in depth, breaking clods, ,- watering, rolling each layer with half tonne roller or wooden Lor steel rammers, and rolling every third and top -most layer with power roller of minimun 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or tilling up ground depressions lead upto 50 mtr and lift upto 1. 5 mtr. in All kinds of soil:
HARMEET SINGH
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .