Superintending Engineer
Electricity Civil Transmission Circle 220 KV Sub Station Sector 20 Noida
Construction of 01 No. 33 KV Ashok Vihar Bay at 220 KV Sub-Station Loni, Ghaziabad
2026_UPCTL_1162845_1
E-Tender Notice 12/2026-27 Sl No-23/2026-27
Open Tender
Civil Works
30 days
GHAZIABAD
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
E.E. E.C.T.D.
₹5,500
22 Jun 2026
22 Jun 2026
24 Jul 2026
22 Jun 2026
23 Jul 2026
22 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic
excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-incharge. All kind of soils | 49.41 | CUM | 135.34 | ₹6,687.15 |
| - | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 0.95 | CUM | 1,619.31 | ₹1,538.34 |
| - | Providing and laying in position cement concrete of specified grade 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources)excluding the cost of centering and shuttering - All work up to plinth level : | 3.1 | CUM | 4,970.28 | ₹15,407.87 |
| - | Providing and laying in position cement concrete of specified grade1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) excluding the cost of centering and shuttering - All work up to plinth level : | 5.53 | CUM | 6,359.7 | ₹35,169.14 |
| - | Providing and laying in position specified grade of reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources), excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : | 10.3 | CUM | 6,897.17 | ₹71,040.85 |
| - | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | 49.3 | SQM | 299.01 | ₹14,741.19 |
| - | Centering and shuttering including strutting, propping etc. and removal of form for columns, Pillars, Piers, Abutments, Posts and Struts | 4.22 | SQM | 732.97 | ₹3,093.13 |
| - | Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). | 0.14 | Cum | 8,071.5 | ₹1,130.01 |
| - | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 595.36 | KG | 82.23 | ₹48,956.45 |
| - | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in Cement mortar 1:4 (1 cement : 4 coarse sand). | 1.86 | CUM | 5,619.95 | ₹10,453.11 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.20 MB
BOQ_2179738.xls
BOQ • 0.40 MB
PQR23.pdf
Tender Documents • 1.66 MB
Download all tender documents and submit your bid