| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.7 LAdmitted-Fee/PreQual/Technical/Finance | -33.50% | ₹2.7 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹2.7 L+₹7,998.85 (3.01%)Admitted-Fee/PreQual/Technical/Finance | -31.50% | ₹2.7 L+₹7,998.85 (3.01%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L3₹2.8 L+₹14,837.87 (5.58%)Admitted-Fee/PreQual/Technical/Finance | -29.79% | ₹2.8 L+₹14,837.87 (5.58%) | L3 | Admitted-Fee/PreQual/Technical/Finance |
| 4 | L4₹4.0 L+₹1.3 L (50.3%)Admitted-Fee/PreQual/Technical/Finance | -0.02% | ₹4.0 L+₹1.3 L (50.3%) | L4 | Admitted-Fee/PreQual/Technical/Finance |
| 5 | L5₹4.0 L+₹1.3 L (50.4%)Admitted-Fee/PreQual/Technical/Finance | +0.00% | ₹4.0 L+₹1.3 L (50.4%) | L5 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹4 L
EMD Value
₹8,000
Closing Date
14 Sept 2026, 4:00 pmClosed
Executive Engineer RnB Division Budgam
Engineering complex Budgam
Construction of Remaining Portion of Culvert and Restoration of blocked Drain/Irrigation pipes at Sebdan Chowk
2026_PWDJK_323147_3
NIT_No_72_DB_2026-27
Open Tender
Civil Works
Percentage
25 days
Sebdan Budgam
Please refer Tender documents.
3 documents required · 3 mandatory
₹200
Executive Engineer RnB Division Budgam
₹8,000
16 Sept 2026
2 Sept 2026
14 Sept 2026
2 Sept 2026
14 Sept 2026
2 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing cement concrete etc manually/by mechanical means including disposal of material within 50meters lead as per direction of EiC :1:3:6 or richer mix (i/c equivalent design mix) | 10.2 | cum | 1,725.2 | ₹17,597.04 |
| 2 | Providing and laying of 900mm internal diamter RCC Spun Pipes in proper position including removal & disposal of damaged pipes, excavation of trenches, ramming of bottom, dressing of sides,providing required cushion over & under the pipes including loading, unloading and carriage upto site of work complete. | 7.5 | RM | 8,500 | ₹63,750 |
| 3 | RCC work in walls(any thickness) including attached pilasters ,buttresses,plinth & string courses,fillets,columns, pillars, piers,abutments,posts & struts upto floor five level incl curing but excluding cost of centering ,shuttering ,finishing & reinforcement 1:1.5:3(1 cement: 1.5 coarse sand :3 graded stone aggregate 20mm nominal size) | 12.82 | cum | 9,395.7 | ₹1,20,452.87 |
| 4 | P/L in position cement concrete of specified grade including curing but excluding the cost of centering & shuttering.All work upto plinth level with 1:2:4 (1 cement:2 coarse sand:4 graded stone aggregate 20mm nominal size) | 2.38 | cum | 6,591.25 | ₹15,687.18 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns | 35.91 | sqm | 286.35 | ₹10,282.83 |
| 6 | Desilting/Dredging of drains, nallahs,canals,ponds or other water channels by mechanical means(JCB) of suitable capacity ,including excavation of silt,sludge,mud,weeds & other deposited material ,loading ,lifting ,stacking or disposal of excavated material within 100m lead by mechanical means,dressing & trimming of the bed & side slopes to the required lines & levels,dewatering if required for smooth execution & all labour ,machinery ,fuel,lubricants,operator charges,tools & tackles, & incidental works complete as directed by EiC | 6 | Hour | 1,170 | ₹7,020 |
| 7 | Engagement of unskilled labour for desilting of drains,nallahs,manual excavation in trenches for foundations drains,culverts,canals & other water channels,including removal of silt ,sludge ,mud debris ,weeds rubbish, & other deposited material ,collection ,loading into mechanical vehicles ,unloadingf at the designated disposal site ,spreading where required & disposal of all excavated material,including all leads & lifts involved & all incidental works complete,as directed by EiC | 20 | 8 Hour | 750 | ₹15,000 |
| 8 | Pumping out water caused by springs,tidal or river seepage, broken water mains or drains & the like.Complete job | 1 | Job | 5,000 | ₹5,000 |
| 9 | Carriage of different materials by MT upto site of work:
Sand for an average lead of 20km | 7.38 | cum | 409.94 | ₹3,025.36 |
| 10 | 20mm nominal size stone aggregate for an average lead of 20km | 14.59 | cum | 409.94 | ₹5,981.02 |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.25 MB
BOQ_1086753.xls
BOQ • 0.29 MB
Extension72.pdf
PDF • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .