Tender Value
₹4.3 L
EMD Value
₹5,000
Closing Date
31 Dec 2019, 2:30 pmClosed
AGM M AND C
AGM M AND C
Repair of quarters at kolihan nagar township
2019_HCL_32534_1
RFQ8314
Open Tender
Miscellaneous Works
Supply
365 days
KHETRI NAGAR
As per RFQ8314
4 documents required · 4 mandatory
₹0
₹5,000
Yes
10 Jul 2020
21 Sept 2019
3 Jan 2020
21 Sept 2019
31 Dec 2019
21 Sept 2019
21 Sept 2019 - 21 Oct 2019
15 mm cement plaster on the rough side of single or half brick wall of mix :1:4 (1 cement: 4 fine sand)
PROVIDING & FIXING STONE DOOR FRAME OF REQUIRED SIZE INCLUDING DOWELS,GROUTED IN CEMENT MORTAR 1:3 WITH NECESSARY HOLES FOR FIXING HINGES,DOOR BOLT ETC COMPLETE AS PER DIRECTION OF ENGINEER-IN-CHARGE.
20 mm cement plaster of mix :1:6 (1 cement: 6 fine sand)
REMENING GLASS PANES, WITH PUTTY AND NAILS WHEREVER NECESSARY: GLASS PANES WEIGHTING 7.5 KG/SQM
RENEWING GLASS PANES, WITH WOODEN FILLETS WHEREVER NECESSARY: GLASS PANES WEIGHING 10 KG/SQM
Carriage of material by mechanical transport including loading, unloading and stacking:Lime, moorum, building rubbish:Lead 1 KM.
Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge.1:3:6 or richer mix
DISMANTLING DOORS WINDOWS AND CLERSTORY WINDOWS (STEEL OR WOOD) SHRTTER INCLUDING CHOWKHATS, ARCHITRAVE, HOLDFASTS ETC. COMPLETE AND DEPOSITING THE SAME IN CENTRAL/SITE STORES. OF AREA 3 SQ.M AND BELOW
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up
Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. Cold twisted bars
Half brick masonry with F.P.S. bricks of class designation 75 in superstructure above plinth level up to floor V level.Cement mortar 1:4 (1 cement :4 coarse sand)
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) at plinth level with :Cement mortar 1:6 (1
Brick work in foundation & plinth with modular bricks Cement mortar 1:4 (1 cement : 4 coarse sand) including dismantling the existing damaged brick work and removal of debris if required
Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry, but excluding the cost of nosing of steps etc. complete.40mm thick with 20mm nomin
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1
RANDOM RUBBLE MASONRY WITH HARD STONE IN SUPERSTRUCTURE INCLUDING LEVELLING UP WITH CEMENT CONCRETE 1:6:12 ( 1 CEMENT : 6 COARSE SAND :12 GRADED STONE AGGREGATE 20 MM NOMINAL SIZE ) WITH CEMENT MORTAR 1:6 (1 CEMENT : 6 COARS SAND)
REINFORCED CEMENT CONCRETE WORK IN RAFTS, FOOTING, BASES OF COLOUMNS ETC AND MASS CONCRETE EXCLUDING COST OF CENTERING, SHUTTERING AND REINFORCEMENT ALL W
Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete
PROVIDING AND FIXING GLASS STRIPS IN JOINTS OF TERRAZO/ CEMENT CONCRETE FLOORS.40 MM WIDE AND 4 MM THICK
Centering and shuttering including strutting, propping etc. and removal of form for : Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
CENTERING AND SHUTTERING INCLUDING STRUTTING, PROPPING ETC. AND REMOVAL OF FORM WORK FOR: COLUMNS, PILLARS, PIERS, ABUTMENTS, POSTS AND STRUTS
Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge
Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge:In cement mortar
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
QURESHI CONSTRUCTION COMPANY
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .