| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹25.4 LAccepted-AOC | ₹25.4 L | 1 | Accepted-AOC Lowest Amount Quoted |
| 2 | 2₹25.5 LRejected-Finance | ₹25.5 L | 2 | Rejected-Finance HighestValue Quoted |
| Sl No | Description | Qty | Unit | C.PAULDURAI L1 | C CHELLAM L2 |
|---|---|---|---|---|---|
| 1.00Providing Extension of Delivery line FHTCs in Govt New Colony Habititation Kavery Garden , Balaji Nagar, UGS Nagar, Green City ,Sagi Nagar , Subharasi Nagar In Ramayanpatti Panchayat In Palayamkottai Panchayat Union. | |||||
| 2.00 | Supply and Delivery of 75mm PVC Pipe | 5,610 | Rtm | 73.02 ₹4.1 L | 73.1 ₹4.1 L |
| 3.00 | Earth work excavation with an initial lead and lift in hard stiff clay, black cotton, hard red earth, sub murram gravel, stone and earth mixed boulders as per SS20B. | 3,530.73 | cum | 329.4 ₹11.6 L | 329.73 ₹11.6 L |
| 4.00 | Labour charges for cement Road cutting | 3.57 | cum | 519.7 ₹1,855.33 | 520.23 ₹1,857.22 |
| 5.00 | Refilling excavated earth including all cost | 3,509.53 | cum | 45.8 ₹1.6 L | 45.85 ₹1.6 L |
| 6.00 | Laying of PVC rigid pipes with lead of 200m lowering into trench, laying in proper grade, alignment, jointing PVC coupler with specials and tested to the required pressure including conveyance of water upto 1km lead during the testing. | 5,610 | Rtm | 23.5 ₹1.3 L | 23.53 ₹1.3 L |
| 7.00 | Earth work Excavation in all classes of soil such an hard stiff clay block cotton soil including all cost and conveyence and all labour charges etc complete. | 0.06 | cum | 2,371.65 ₹142.30 | 2,374.02 ₹142.44 |
| 8.00 | Cement concrete 1:4:8 mix using 40mm HBG metal for foundation inmcluding watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 0.06 | cum | 95,538.01 ₹5,732.28 | 95,633.64 ₹5,738.02 |
| 9.00 | Cement concrete 1:2:4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 0.04 | cum | 1,18,753.6 ₹4,750.14 | 1,18,872.5 ₹4,754.90 |
| 10.00 | Supply and erecting centering charges for all concreet works including all cost etc complete. | 0.59 | sqm | 6,563.43 ₹3,872.42 | 6,570 ₹3,876.30 |
Tender Value
₹30.5 L
EMD Value
₹30,510
Closing Date
13 Feb 2026, 3:00 pmClosed
PANCHAYAT OFFICE RAMAYANPATTI
PANCHAYAT OFFICE RAMAYANPATTI
Providing Extension of Delivery line FHTCs in Govt New Colony Habititation Kavery Garden , Balaji Nagar, UGS Nagar, Green City ,Sagi Nagar , Subharasi Nagar In Ramayanpatti Panchayat In Palayamkottai Panchayat Union.
2026_RDTN_654245_2
01/2025-26
Open Tender
Construction Works
80 days
PANCHAYAT OFFICE RAMAYANPATTI
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹30,510
28 Feb 2026
10 Feb 2026
13 Feb 2026
10 Feb 2026
13 Feb 2026
10 Feb 2026
Providing Extension of Delivery line FHTCs in Govt New Colony Habititation Kavery Garden , Balaji Nagar, UGS Nagar, Green City ,Sagi Nagar , Subharasi Nagar In Ramayanpatti Panchayat In Palayamkottai Panchayat Union.
Supply and Delivery of 75mm PVC Pipe
Earth work excavation with an initial lead and lift in hard stiff clay, black cotton, hard red earth, sub murram gravel, stone and earth mixed boulders as per SS20B.
Labour charges for cement Road cutting
Refilling excavated earth including all cost
Laying of PVC rigid pipes with lead of 200m lowering into trench, laying in proper grade, alignment, jointing PVC coupler with specials and tested to the required pressure including conveyance of water upto 1km lead during the testing.
Earth work Excavation in all classes of soil such an hard stiff clay block cotton soil including all cost and conveyence and all labour charges etc complete.
Cement concrete 1:4:8 mix using 40mm HBG metal for foundation inmcluding watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:2:4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supply and erecting centering charges for all concreet works including all cost etc complete.
Supplying and fabrication of steel including cost and conveyance of bending to shape and tying in position and forming grills for all R.C.C works including cost and conveyance of all materials to site
Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum.
Cement concrete 1:4:8 mix using 40mm HBG metal for foundation inmcluding watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:2:4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supply and delivery of 75 mm x 20 mm SADDLE PIECE confirming AS PER IS 7834/1987 for tapping outlet suiting for , 3/4” clear bore and with wide plastic strap (Engineering Plastic) with SS 304 suitable bolts & nuts. Saddle to have sealing of Thermo plastic elastomeric (TPE) material around - 20mm
Common Items for HSC Connection - PBrass Ferrule as per IS 319 grade of sizes 15mm, 20mm and 25mm size and threaded as per IS:1554 BSPT, ISO:7-1 to suit the corresponding bore sizes of 15mm, 20mm and 25mm dia size ( 1/2", 3/4" and 1") in the saddle Connection as per IS :1554 BSPT, ISO:7-1 (20mm) 15 mm
Supply and delivery of 20 mm PVC pipe 10Kg per cm2
Supply and delivery of 20 mm PVC Elbow
Supply and delivery of 20 mm PVC FTA
Brass Chromium Plated Screw Down Tap 15
Earthwork Excavation for 20mm PVC pipe laying work including cost of Refilling work as per Standard Specifications 20B (in Rm)
Labour Charges for Laying & Jointing 20 mm pipe in Excavated Trench in Proper Camber
Supply and delivery of Flw control Valve of 20 LPM (Local rate)
Labour charges for Drilling,Cutting and fixing ferrules in distribution line
Cutting 20mm PVC pipe
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.14 MB
BOQ_784551.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid