| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.6 LAccepted-AOC | ₹7.6 L Quoted ₹26.8 L | L1 | Accepted-AOC bomd |
| 2 | L2₹26.9 LRejected-Finance | ₹26.9 L | L2 | Rejected-Finance reject |
| 3 | L3₹29.5 LRejected-Finance | ₹29.5 L | L3 | Rejected-Finance reject |
| 4 | L4₹32.9 LRejected-Finance | ₹32.9 L | L4 | Rejected-Finance reject |
Tender Value
₹40 L
EMD Value
₹4 L
Closing Date
15 Apr 2026, 12:00 pmClosed
SE Ayo Amb Circle Ayodhya
SE Ayo Amb Circle Ayodhya
Construction of Ramnagar mukhya marg se molnapur rasulpur hote huye barmasa prathmik vidylay tak link road
2026_CEUFZ_1133899_1
2419/1(1)-Com-Ayo.Amb. Circle/26 Dated 01-04-2026
Open Tender
Civil Works
180 days
EE CD PWD Ambedkarnagar
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,714
₹4 L
Yes
EE CD PWD Ambedkarnagar
20 May 2026
7 Apr 2026
15 Apr 2026
7 Apr 2026
15 Apr 2026
7 Apr 2026
13 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
Earth work in cutting or in embankment in ordinary soil, excavation to be in the form of regular pit not exceeding 1/2 metre (20'') in depth and earthwork in embankment to be 20 cm (8'') layers including ramming and dressing the surface to required levels and slopes and also including 1.5 mts lead. The earth form cutting to be used in making embankment or to be desposited on spoil banks withen 30 m. (100 ft.) distance as directed by the Engineer-in-charge Excluding Royalty. | - | Cum | - | - | |
Earth work in excavation in trench for foundation in ordinary soil i/c lift upto 1.50 mtr. & lead upto 50.00 mtr and dressing of sides and ramming of bottom and disposal of surplus excavated earth as directed bu the E/I within a distance of 50 m. (as per SI No. 251) | - | Cum | - | - | |
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. | - | Cum | - | - | |
Providing, laying and spreading Material on prepared sub grade, adding cement @4% by weight to the spread material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the deisred unconfined compressive strength and to form a layer of base/sub base. | 1 | Cum | - | - | |
Providing and applying tack coat with Bitumen (VG-10) using bitumen distributor at the rate of 0.35 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. | - | Sqm | - | - | |
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A as per Technical Specification Clause 508 | - | Sqm | - | - | |
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C, as per Technical Specification Clause 510 | - | Sqm | - | - | |
Brick edging 7 cm wide on both sides of the road With Staraight over burnt bricks complete as per PWD specification no. 20.15 | - | Km | - | - | |
Earth work in cutting or in embankment in ordinary soil, excavation to be in the form of regular pit not exceeding 1/2 metre (20'') in depth and earthwork in embankment to be 20 cm (8'') layers including ramming and dressing the surface to required levels and slopes and also including 1.5 mts lead. The earth form cutting to be used in making embankment or to be desposited on spoil banks withen 30 m. (100 ft.) distance as directed by the Engineer-in-charge Excluding Royalty. | - | Cum | - | - | |
Construction of Hume Pipe Culvert
Earth work in excavation in foundation as per SI no. 251 (Excluding royelty) | - | Cum | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.12 MB
Tendernotice_2.pdf
PDF • 0.58 MB
BOQ_2116579.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid