Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹19.3 L+₹34,398 (1.82%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹19.6 L+₹65,065 (3.44%)Rejected-AOC AURI MOR ANPARA SONEBHADRA ANPARA SONBHADRA UTTAR PRADESH 231225 | SONBHADRA | UTTAR PRADESH | 231225 | L3 | Rejected-AOC L3 |
Tender Value
₹19 L
EMD Value
₹38,000
Closing Date
30 Aug 2022, 4:00 pmClosed
SE OMC-1 ATPS ANPARA
SE OMC-I 3X210 MW ATPS ANPARA
Break down maintenance and related repairing works of ESP hopper, Rotary vane feeder body (RVF) body and rotor assembly for ESP Hopper and Fabrication WORK of ESP bottom ash system of all the three units of 3X210 MW, ATPS, Anpara
2022_RVUNL_718238_1
T07/AHD/OMC-I/ATPS/2022-23
Open Tender
Repair and Maintenance Works
Fixed-rate
365 days
ATPS ANPARA
PLEASE REFER TENDER DOCUMENTS
3 documents required · 3 mandatory
₹1,180
Dy. C.A.O., CFA AND BO, ATPS Anpara
₹38,000
24 Nov 2022
1 Aug 2022
31 Aug 2022
1 Aug 2022
30 Aug 2022
1 Aug 2022
1 Aug 2022 - 30 Aug 2022
Amount
Repairing of flushing apparatus of following sizes:
500 mm Nb with seal trough
Repairing of expansion joint of following sizes
Servicing & replacement of RVF gear box.
Removal of foreign material stacked inside body of Flushing apparatus / Cleaning by removal of foreign material & water washing of Eco, APH, Stack & ESP hopper by cutting flushing apparatus/ down comer pipe etc. of ash hopper
Dismantling of RVF rotor of ESP system
Fitting of RVF rotor with its gear box & commissioning of the same.
Replacement of worn-out gaskets/packing between different flanges /flushing apparatus /inspection joint/ expansion joint /gland packing of RVF and gland cap etc.
Replacement of damaged/worn out expansion joint 200 mm Nb to 300 mm Nb.
Fabrication and erection of inspection window of flushing apparatus.
Patching/overlapping on down comer pipe/flushing apparatus/expansion joint etc.
i. Up to 400 Cm² JOB 120
ii 401 to 900 Cm² JOB 40
iii. 901 to 2500 Cm² JOB 20
Replacement of flushing nozzle body/ jetting nozzle body and jetting tips after repairing, cutting and welding etc.
Replacement of damaged / worn out flushing apparatus of size-
700 mm Nb & 600 mmNb. Installed at 0 meter ESP site
500mm Nb Installed at 0 meter ESP site.
Replacement of damaged flushing apparatus ofAPH/ duct/ stack hopper of size 380mmNb.
Replacement of damaged / worn-out reducer/ distance piece of ESP Hopper/APH/Flue gas duct hopper,
Desilting of flushing nozzle body connected to flushing apparatus/ jetting nozzle system connected in ash trench below ash hopper.
Removal of jamming drain header connected pipe line connected to flushing apparatus economizer hopper/flue gas air heater
Size: 150mmNb.
Size : 200mmNb R/M
Replacement of fly eye nut and bolts of economizer hopper/air heater /Flue gas duct and ESP hoppers.
Fabrication of Expansion Joints of size 200 mm Dia from MS Plate.
Fabrication of Expansion Joints of size 300 mm Dia from MS Plate.
Fabrication of Distance piece size 300X 150 mm from MS plate
Fabrication of Reducer size dia 400 X 300 mm NB
Painting with one coat red oxide /primer & double coat of synthetic enamel paint
Fabrication of flushing apparatus for first, second and third row of ESP hoppers of 3X210 MW 'A'TPS Anpara as per drawing/ sample.
Repairing of rotary vane feeder (RVf) body and rotor assembly for esp hopper of 3X210 M.W ' A'TPS Anpara.
M/S NISHA ENTERPRISES
SHAKSHI ENGINEERING CO.
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .