| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAccepted-AOC | ₹1.8 Cr | L1 | Accepted-AOC Work Order can be issued to lowest quoted contractor |
| 2 | L2₹1.8 CrRejected-AOC | ₹1.8 Cr | L2 | Rejected-AOC Work Order can be issued to lowest quoted contractor |
| Sl No | Description | Qty | Unit | SG Ravi L1 | NPN PALLAVA CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum | 696 | Cum | 164.8 ₹1.1 L | 168 ₹1.2 L |
| 2.00 | Cement Concrete M7.5 (1:4:8) (Design mix) using 40 mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but soft water labour charges for mixing, Transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications. | 116 | Cum | 5,130 ₹6.0 L | 5,135 ₹6.0 L |
| 3.00 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steel reinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) | 58,960 | Kg | 92.9 ₹54.8 L | 93 ₹54.8 L |
| 4.00 | Vibrated Reinforced Cement Concrete M-20 (Design mix) using 20mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for MAT Concrete | 174 | Cum | 9,051 ₹15.7 L | 9,055 ₹15.8 L |
| 5.00 | Vibrated Reinforced Cement Concrete M-20 (Design mix) using 20mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for SIDE WALL | 332 | Cum | 15,550.4 ₹51.6 L | 15,600 ₹51.8 L |
| 6.00 | Vibrated Reinforced Cement Concrete M-20 (Design mix) using 20mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for DECK SLAB | 231 | Cum | 10,222.8 ₹23.6 L | 10,250 ₹23.7 L |
| 7.00 | Supplying and fixing in position C.I.Manhole covers (light or heavy duty) of 60 X 60cm in size in Cement Mortar 1:3 (One part of Cement and Three part of Plastering Sand (P- Sand), of best approved quality and as per standard specifications etc.,complete. | 85 | Nos | 1,863.8 ₹1.6 L | 1,890 ₹1.6 L |
| 8.00 | Provision for GST 18% | 1 | No | 27,80,039.05 ₹27.8 L | 27,86,226.84 ₹27.9 L |
Tender Value
₹1.9 Cr
EMD Value
₹1.9 L
Closing Date
5 Mar 2026, 3:00 pmClosed
Commissioner, Madhuranthagam Municipality
Commissioner, Madhuranthagam Municipality
Construction of RCC Strom Water Drain with Cover Slab at Parthasarathi Street in Madhuranthagam Municipality
2026_MAWS_667217_1
54/2025/E1
Open Tender
Civil Works - Others
Madhuranthagam Municipality
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹1.9 L
Madhuranthagam Municipal Office
10 Mar 2026
26 Feb 2026
5 Mar 2026
26 Feb 2026
5 Mar 2026
26 Feb 2026
27 Feb 2026
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum
Cement Concrete M7.5 (1:4:8) (Design mix) using 40 mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but soft water labour charges for mixing, Transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications.
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steel reinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire)
Vibrated Reinforced Cement Concrete M-20 (Design mix) using 20mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for MAT Concrete
Vibrated Reinforced Cement Concrete M-20 (Design mix) using 20mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for SIDE WALL
Vibrated Reinforced Cement Concrete M-20 (Design mix) using 20mm ISS HBG graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for DECK SLAB
Supplying and fixing in position C.I.Manhole covers (light or heavy duty) of 60 X 60cm in size in Cement Mortar 1:3 (One part of Cement and Three part of Plastering Sand (P- Sand), of best approved quality and as per standard specifications etc.,complete.
Provision for GST 18%
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
Tendernotice_2.pdf
PDF • 0.64 MB
BOQ_801547.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid