| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 LAccepted-Finance | L1 | Accepted-Finance Less Rate | |
| 2 | L2₹5.0 L+₹9,836.17 (2.00%)Rejected-Finance | L2 | Rejected-Finance Above Rate |
Tender Value
Refer Docs
EMD Value
₹5,000
Closing Date
23 Nov 2022, 3:00 pmClosed
Block Development Officer (VP)
Block Development Office (VP),Budalur,Thanjavur
Thanjavur District Work No 05 Creating and Upgradation of livelihood Activities in Renovation of Komakudi kulam(Desilting of Pond,Construction of Bathing ghat and Construction of Revetment Rough Stone Dry Packing at Vittalapuram Pnchayat of Budalur
2022_RDTN_264696_1
Rc.No.3029/2022/A3 Dated 26.10.2022
Open Tender
Civil Works - Water Works
Item Rate
180 days
Budalur
Please refer Tender documents.
9 documents required · 9 mandatory
₹0
₹5,000
Yes
15 Dec 2022
16 Nov 2022
23 Nov 2022
17 Nov 2022
23 Nov 2022
17 Nov 2022
Amount
Renovation of Komakudi kulam(Desilting of Pond,Construction of Bathing ghat and Construction of Revetment (Rough Stone Dry Packing) at Vittalapuram Pnchayat.
Clearing the light jungle and Removel away from the site including charges as the sandars specification
Earth work excavation in all soils and Sub Soil except in hard rock requiring blasting and conveyance for formation of bund with lead 0 to 100m, deploying earth moving machineries and tipper including benching, formation of bunds, breaking clods, sectioning etc., complete. ( SOR 2022-23,Pg No: 24 SI No: 54 -
Construction of Revetment (Rough stone dry packing)
Earth work excavation in hard stiff clay soil and all classess of soil and depositing on bank with initial lead and lift as per SS20B.
Sand filling with river sand good quality including cost and conveyance of all materials to site including watering and compacting etc complete.
Cement concrete with (1:4:8) mix using 40mm ISS HBG metal including cost and conveyance of all materials and labour charges etc complete.
Cement concrete with (1:3:6) mix using 40mm ISS HBG metal including cost and conveyance of all materials and labour charges etc complete.
Supplying and erecting Centering and Shuttering for soffits including necessary supports and strutting up to 3 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at about 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specification.(Payment for centering shall be given after the concrete is laid).
Gravel backing for revetments including cost and conveyance and all labour charges etc complete - 10 cum. .
Rough stone dry packing for aprons and revetments including cost and conveyance and all labour charges etc complete .
Construction of Bathing Ghat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Supplying and filling in foundation and basement with filling Sand in layers not more 15 cm thick well rammed watered and compacted .complete complying to standard specification
Cement Concrete 1:4:8 mix Using Hand Broken Granite 40 mm stone jelly for Foundation including watering whenever necessary and laid in layers not more than 15 cm thick. Compacting etc., complete complying within standard specification.
Supplying and erecting centering of sides as per standard specification and all labor charges etc.
Cement Concrete 1:3:6 Using 40 mm gauge Hand Broken Granite stone jelly for Foundation including watering whenever necessary and laid in layers not more than 15 cm thick. Compacting etc., complete complying within standard specification
Provision for Name Board
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Punniyamoorthy
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .