| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
Tender Value
₹79.5 L
EMD Value
₹80,000
Closing Date
14 May 2020, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Project Director
DRDA, VPM
Strengthening of 1 road under NABARD 25in Mailam Block of Viluppuram District Pacakge 004
2020_RDTN_162132_2
VPM/NABARD25/004
Open Tender
Civil Works
Works
180 days
Viluppuram District
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹80,000
Yes
15 May 2020
8 May 2020
14 May 2020
8 May 2020
14 May 2020
8 May 2020
90 days
Amount
Strengthening the road from Avvaiyarkuppam to Alagramam road Km 0/0-1/950
Clearing the scrub jungles including all labour charges for all labour charges etc complete.km 0/0-1/950
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil for cutting side drain etc complete as per SS 20A
Picking old BT Surface upto 10cm thick
Collection & Supply and spreading of US gravel including cost & conveyance and labour charges for stacking etc., complete
Providing and laying spreading and compacting graded stone aggregate to wet mix mecadam (WMM)specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in sub base / base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material,labour charges ,rentals for machinery , fuel and all other incidental charges etc., complete
Providing and laying of prime coat using emulsion at the rate of 7kg per ten square meter over the WMM surface preparatory to another bituminous
Applying tack coat over primed WBM surface at 2.50Kg of RS-1 Bitumen Emulsion/10.Sq.m including labour for soraying, hire charges for bitumen sprayer etc., Complete
Providing and laying Premix carpet 20mm thickness using 0.18 cum of 13.2 IRC machine crushed metal 0.09 cum of 11.2mm IRC machine crushed metal with 14.60kg of bitumen for premixing 10 sqm of premix carpet and laying seperately seal coat type A using 0.09 of 6.70mm IRC HBG chips with 9.80kg of bitumen for 10 sqm including cost and conveyance of materials to the departmental metric gauge for pre measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for premix carpet and rolling by 80-100KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant,bitumen boiler , all other tools and plants employed etc., complete
Construction of CC Road @ch 0/0-0/200m
Centering for cement concrete and reinforced cement concrete for all etc
construction of unreinforced dowel jointed at expansion and construction joint only,plain cement concrete pavement thickness as per design over a prepared sub base with 43 grade cement or any other type as per clause 1501.2.2 M30 (grade) coarse
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per drawing and technical specifications
Construction of Retaining wall at Right side ch 0/285-0/305
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29 m height for plane surface in all cross bracting using MS sheets of size 90x60 cm and 10kg stiffened with angle of size 25x25x3 mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Ist footing
super structure
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Ist footing
super structure
Construction of Retaining wall at Right side ch 0/335-0/355
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29 m height for plane surface in all cross bracting using MS sheets of size 90x60 cm and 10kg stiffened with angle of size 25x25x3 mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Ist footing
super structure
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Ist footing
super structure
Construction of Retaining wall at Left side ch 0/710-0/795
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29 m height for plane surface in all cross bracting using MS sheets of size 90x60 cm and 10kg stiffened with angle of size 25x25x3 mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Ist footing
super structure
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Ist footing
super structure
Construction of 1.50 span RCC slab culvert @ ch 0/415
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29 m height for plane surface in all cross bracting using MS sheets of size 90x60 cm and 10kg stiffened with angle of size 25x25x3 mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Below Sill
Above Sill
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cement concrete 1:2:4 using 20mm HBG metal for foundation watering wherever and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening ,cutting to length ,bending to shape and tying in position and forming grills for all R.C.C works.
Reinforce cement concrete 1:11/2:3 mix using 20mm ISS metal including cost and conveyance of all materilas to site and all labour charges for mixing ,laying,and curing etc., complete for 10cum.
Construction of 1.50 span RCC slab culvert @ ch 0/580
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29 m height for plane surface in all cross bracting using MS sheets of size 90x60 cm and 10kg stiffened with angle of size 25x25x3 mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Below Sill
Above Sill
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cement concrete 1:2:4 using 20mm HBG metal for foundation watering wherever and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening ,cutting to length ,bending to shape and tying in position and forming grills for all R.C.C works.
Reinforce cement concrete 1:11/2:3 mix using 20mm ISS metal including cost and conveyance of all materilas to site and all labour charges for mixing ,laying,and curing etc., complete for 10cum.
Construction of 1.50 span RCC slab culvert @ ch 0/815
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29 m height for plane surface in all cross bracting using MS sheets of size 90x60 cm and 10kg stiffened with angle of size 25x25x3 mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Below Sill
Above Sill
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cement concrete 1:2:4 using 20mm HBG metal for foundation watering wherever and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening ,cutting to length ,bending to shape and tying in position and forming grills for all R.C.C works.
Reinforce cement concrete 1:11/2:3 mix using 20mm ISS metal including cost and conveyance of all materilas to site and all labour charges for mixing ,laying,and curing etc., complete for 10cum.
Provision for KM stone
Provision for HM stone
Provision for sign board
Provision for the Name board
Provsion of Photo graph charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Arumugam P V
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .