| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹38.3 LAccepted-AOC | ₹38.3 L | 1 | Accepted-AOC lowest price |
| 2 | 2₹38.6 LRejected-Finance 241 2ND MAIN STREET LAKSHMIPURAM PALANI DINDIGUL DISTRICT 624 601 | DINDIGUL | TAMIL NADU | 624601 | ₹38.6 L | 2 | Rejected-Finance HIGHEST PRICE |
| Sl No | Description | Qty | Unit | P VIJAYAKUMAR L2 | K G CONSTRUCTIONS L1 |
|---|---|---|---|---|---|
| 1.00BT ROAD | |||||
| 1.01 | Construction of Granular Sub-base by providing close graded material,mixing in a machanical plant at OMC,carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to acheive the desired density,Complete as per clause 401. | 371 | M3 | 2,135 ₹7.9 L | 2,132 ₹7.9 L |
| 1.02 | Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH | 248 | M3 | 2,445 ₹6.1 L | 2,443 ₹6.1 L |
| 1.03 | Providing and Laying Prime Coat over WMM surface using 7Kg of Emulsion Bitumen (SS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5 | 2,475 | M2 | 90 ₹2.2 L | 87 ₹2.2 L |
| 1.04 | Providing and Laying Tack Coat over WMM surface (treated with primer) using 2.50Kg of Bitumen Emulsion (RS1) per 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 | 2,475 | M2 | 21 ₹51,975 | 19.3 ₹47,767.50 |
| 1.05 | Providing and Laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5 | 124 | M3 | 10,764 ₹13.3 L | 10,664 ₹13.2 L |
| 1.06 | Providing and Laying Bituminous Concrete 30mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 mm & below with 50.30 kgs of 60/70 Grade Bulk bitumen per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5 | 75 | M3 | 11,363 ₹8.5 L | 11,262 ₹8.4 L |
Tender Value
₹46 L
EMD Value
₹46,000
Closing Date
28 Jan 2026, 3:00 pmClosed
THE EXECUTIVE OFFICER, SHOLAVANDAN TOWN PANCHAYAT
THE EXECUTIVE OFFICER, SHOLAVANDAN TOWN PANCHAYAT
Sholavandan Town Panchayat Providing BT road at ward no 3 18 Vadipatti Road 4th cross Street and RMS Colony in Sholavandan Town Panchayat
2026_DTP_642476_1
402/2025
Open Tender
Civil Works - Roads
90 days
SHOLAVANDAN
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹46,000
11 Mar 2026
12 Jan 2026
28 Jan 2026
12 Jan 2026
28 Jan 2026
12 Jan 2026
BT ROAD
Construction of Granular Sub-base by providing close graded material,mixing in a machanical plant at OMC,carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to acheive the desired density,Complete as per clause 401.
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH
Providing and Laying Prime Coat over WMM surface using 7Kg of Emulsion Bitumen (SS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and Laying Tack Coat over WMM surface (treated with primer) using 2.50Kg of Bitumen Emulsion (RS1) per 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and Laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5
Providing and Laying Bituminous Concrete 30mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 mm & below with 50.30 kgs of 60/70 Grade Bulk bitumen per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.76 MB
TECHNICALBID46.pdf
Tender Documents • 0.83 MB
BOQ_769721.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid