| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | H4₹46.3 L−₹3.2 L (6.31%)Accepted-AOC VILL PO KOTA VIA PANAGARH BAZAR DIST BURDWAN WB PIN 713148 | BURDWAN | BURDWAN | WEST BENGAL | 713148 | H4 | Accepted-AOC Contract awarded to M/s National Construction Co being lowest bidder | |
| 2 | H1₹50.0 LRejected-Finance | H1 | Rejected-Finance Higher rate quoted than H4 | |
| 3 | H2₹48.4 L−₹1.6 L (3.28%)Rejected-Finance | H2 | Rejected-Finance Higher rate quoted than H4 | |
| 4 | H3₹48.1 L−₹1.9 L (3.81%)Rejected-Finance BIDHAN NAGAR MANKAR ROAD PO PS BUD BUD DIST PURBA BARDHAMAN PIN 713403 | BUD BUD | PURBA BARDHAMAN | WEST BENGAL | 713403 | H3 | Rejected-Finance Higher rate quoted than H4 |
| Sl No | Description | Qty | Unit | NATIONAL CONSTRUCTION CO H4 | S.D.ENTERPRISE H3 | HAZRA ENTERPRISE H1 | M/S DYNAMIC INDIA (PROJECT) CONSTRUCTION H2 |
|---|---|---|---|---|---|---|---|
| 1.00 | Demolition of Brickwork or stone/ boulder masonry, built in cement mortar or cement lime mortar including all quoins, arches, pillars, etc, but excluding ashlar facings, dressed stonework and precast concrete articles complete all as sepcified and directed. | 15 | Cum | 468 ₹7,020 Lowest | 510 ₹7,650 | 540 ₹8,100 | 500 ₹7,500 |
| 2.00 | Demolition of cement concrete reinforced as in chajja & similar suspended work (other than ground floor) complete all as specified and directed. | 2 | Cum | 675 ₹1,350 Lowest | 699 ₹1,398 | 730 ₹1,460 | 700 ₹1,400 |
| 3.00 | Demolition of cement concrete as in ground floors and pavings not exceeding 15 cm thick below or above ground level (unreinforced) complete all as specified and directed. | 22 | Cum | 655 ₹14,410 Lowest | 688 ₹15,136 | 750 ₹16,500 | 700 ₹15,400 |
| 4.00 | Excavating over areas in soft/loose soil, n exc 1.5 m deep and getting out, complete all as specified and as directed. | 155 | Cum | 388 ₹60,140 Lowest | 410 ₹63,550 | 420 ₹65,100 | 420 ₹65,100 |
| 5.00 | Excavating in trenches , n.exc 1.5 m wide and n.exc 1.5 m depth for foundation etc or for shafts, wells, cesspits ,manhole pier hole, laying of cables, pipes etc n.exc 10 sqm on plan and n.exc 1.5m in depth and getting out in any kind of soil
Note : Manual excavation to be done. During excavation if any damage occured to existing cable any type/ water pipe line, it will be contractor responsibilty to get it repair and make functional by providing jointing kit etc without any extra cost. Contractor has to repair it within 24 hrs so that essential service can not be effected due to such damage.If contractor fails to repair it within 24 hrs penalty @ Rs 500/- will be charged to contractor. In this GE decision will be final, conclusive and binding. | 85 | Cum | 390 ₹33,150 Lowest | 412 ₹35,020 | 430 ₹36,550 | 420 ₹35,700 |
| 6.00 | All as per BOQ Item No 5.00 here-in-before but of depth exc 1.5m and not exceeding 3.00 mtrs complete all as specified. | 25 | Cum | 425 ₹10,625 Lowest | 430 ₹10,750 | 450 ₹11,250 | 430 ₹10,750 |
| 7.00 | Returning, filling in, including spreading, levelling, watering and well ramming in layers not exc 25 cm, complete all as specified and as directed. | 93 | Cum | 100 ₹9,300 Lowest | 105 ₹9,765 | 120 ₹11,160 | 120 ₹11,160 |
| 8.00 | Removing excavated material in soft/loose soil n exc. 50m and depositing where directed at a level n exc. 1.5 m above the starting point, complete all as specified and as directed. | 174 | Cum | 120 ₹20,880 Lowest | 133 ₹23,142 | 135 ₹23,490 | 130 ₹22,620 |
| 9.00 | M&L for pavings, with mix of fly ash, clinker & stone dust in the proportion of 1:3:6 (ie 10% fly ash, 30% clinker and 60% stone dust ) laying in layers n. exc 10cm thick, watering, ramming and compacted with hand/power roller 8 to 12 tonn roller to required camber and gradient complete all as directed by Engineer-in-Charge. | 180 | Cum | 1,600 ₹2,88,000 Lowest | 1,622 ₹2,91,960 | 1,650 ₹2,97,000 | 1,620 ₹2,91,600 |
| 10.00 | Forming embankments including raising (or lowering) earth, spreading in layers n exc. 30 cm thick; watering, ramming/rolling and finishing to required size, shape, etc., n exc. 1.5 m high from base complete all as specified and as directed. | 80 | Cum | 350 ₹28,000 Lowest | 355 ₹28,400 | 380 ₹30,400 | 366 ₹29,280 |
Tender Value
₹43.7 L
EMD Value
₹83,400
Closing Date
23 May 2026, 6:00 pmClosed
GE PANNGARH
GARRISON ENGINEER PANAGARH, MILITARY ENGINEER SERVICES, PO-PANAGARH, DISTT- BURDWAN, STATE-WEST BENGAL PIN-713420
All as per BOQ
2026_MES_763100_1
8500-566/E8
Open Tender
Civil Works
Works
180 days
PANNGARH
As per tender docus
6 documents required · 6 mandatory
₹500
GE Panagarh
₹83,400
27 Jul 2026
2 May 2026
25 May 2026
2 May 2026
23 May 2026
16 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolition of Brickwork or stone/ boulder masonry, built in cement mortar or cement lime mortar including all quoins, arches, pillars, etc, but excluding ashlar facings, dressed stonework and precast concrete articles complete all as sepcified and directed. | 15 | Cum | - | - |
| 2 | Demolition of cement concrete reinforced as in chajja & similar suspended work (other than ground floor) complete all as specified and directed. | 2 | Cum | - | - |
| 3 | Demolition of cement concrete as in ground floors and pavings not exceeding 15 cm thick below or above ground level (unreinforced) complete all as specified and directed. | 22 | Cum | - | - |
| 4 | Excavating over areas in soft/loose soil, n exc 1.5 m deep and getting out, complete all as specified and as directed. | 155 | Cum | - | - |
| 5 | Excavating in trenches , n.exc 1.5 m wide and n.exc 1.5 m depth for foundation etc or for shafts, wells, cesspits ,manhole pier hole, laying of cables, pipes etc n.exc 10 sqm on plan and n.exc 1.5m in depth and getting out in any kind of soil
Note : Manual excavation to be done. During excavation if any damage occured to existing cable any type/ water pipe line, it will be contractor responsibilty to get it repair and make functional by providing jointing kit etc without any extra cost. Contractor has to repair it within 24 hrs so that essential service can not be effected due to such damage.If contractor fails to repair it within 24 hrs penalty @ Rs 500/- will be charged to contractor. In this GE decision will be final, conclusive and binding. | 85 | Cum | - | - |
| 6 | All as per BOQ Item No 5.00 here-in-before but of depth exc 1.5m and not exceeding 3.00 mtrs complete all as specified. | 25 | Cum | - | - |
| 7 | Returning, filling in, including spreading, levelling, watering and well ramming in layers not exc 25 cm, complete all as specified and as directed. | 93 | Cum | - | - |
| 8 | Removing excavated material in soft/loose soil n exc. 50m and depositing where directed at a level n exc. 1.5 m above the starting point, complete all as specified and as directed. | 174 | Cum | - | - |
| 9 | M&L for pavings, with mix of fly ash, clinker & stone dust in the proportion of 1:3:6 (ie 10% fly ash, 30% clinker and 60% stone dust ) laying in layers n. exc 10cm thick, watering, ramming and compacted with hand/power roller 8 to 12 tonn roller to required camber and gradient complete all as directed by Engineer-in-Charge. | 180 | Cum | - | - |
| 10 | Forming embankments including raising (or lowering) earth, spreading in layers n exc. 30 cm thick; watering, ramming/rolling and finishing to required size, shape, etc., n exc. 1.5 m high from base complete all as specified and as directed. | 80 | Cum | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.42 MB
PS566.pdf
Tender Documents • 1.10 MB
BOQ_854768.xls
BOQ • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .