Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹30.0 LAccepted-AOC O G HALLI DHARMAPURI DISTRICT | KRISHNAGIRI | TAMIL NADU | 635106 | L1 | Accepted-AOC L1 | |
| 2 | L2₹31.4 L+₹1.4 L (4.52%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹35.6 L+₹5.5 L (18.5%)Rejected-AOC | L3 | Rejected-AOC L3 | |
| 4 | Not Admitted-Fee/PreQual/Technical 3 26A THIRUVASI VILLAGE NORTH STREET THUDAIYUR MANNACHALLUR TALUK TIRUCHIRAPPALLI DISTRICT | THUDAIYUR | TIRUCHIRAPPALLI | TAMIL NADU | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹34.4 L
EMD Value
₹35,000
Closing Date
6 Jun 2023, 3:00 pmClosed
The Addl. Collector (Dev) / Project Director, DRDA
DRDA, Dharmapuri
Providing approach road WBM Double Layer from Rajivi Gandhi Nagar Km.0/630-1/130 H/o.Periyapatti
2023_RDTN_320286_1
Roc.No.330/2021/R9 Tribal P26
Open Tender
Civil Works
Item Rate
120 days
DRDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹35,000
11 Dec 2023
29 May 2023
6 Jun 2023
29 May 2023
6 Jun 2023
29 May 2023
Amount
Providing approach road WBM Double Layer from Rajivi Gandhi Nagar Km.0/630-1/130 H/o.Periyapatti
Clearing the Scurb jungle remove away from the site including all labour charges etc., complete
Earth work excavation and depositing on bank with initial lead and list in all clauses as soil as per SS 20 A
Providing and Laying Gravel to 100mm compacted thick including cost & coveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%) & (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80 100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in place method),
Providing and laying 75mm compacted thick WBM Grade II using 1 cum of 75mm to 22.4mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre- measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing, including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for BOTTOM LAYER
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre- measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Hard Bed @ Ch.885-905
Earth work excavation and foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1:4:8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc
Cement concrete 1:3:6 mix using Aggregate 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre- measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Cement conerete 1:1.5:3 using 20mm H.B.G.Metal including watering wherever necessary sand laid in layers compacting etc. complete complying with standard specification and directed by the departmental officers.
Provision for Expansion Joints (Bituman Pad)
Hard Bed @ Ch.980-1000
Earth work excavation and foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1:4:8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc
Cement concrete 1:3:6 mix using Aggregate 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre- measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Cement conerete 1:1.5:3 using 20mm H.B.G.Metal including watering wherever necessary sand laid in layers compacting etc. complete complying with standard specification and directed by the departmental officers.
Provision for Expansion Joints (Bituman Pad)
Retaining wall @ Ch.1030m
Earth work excavation for foundation in all soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring,strutting and balling out water whereever necessary and refilling the sides of foundation.
Cement concrete 1:4:8 [one cement four sand and eight jelly] using 40.m.m. H.B.G.Jelly for foundation including watering where ever necessary and laid in layers not more than 15.c.m. thick compacting etc. complete complying with standard specification.
Cement concrete 1:3:6 mix using Aggregate 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum
Supplying erecting and shuttering including necessarysupports for plane surfaces in foundation and basement and in all floors for slabs and beams complying with standard specification.
Provision for Wepholes
Provision for Citizen Information Board
Provision for Sign Board
Provision for HM Stone
Provision for HM Stone
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
KULANTHAISAMY-DHANALAKSHMI
V.Senthil Kumar
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .