Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.2 CrAdmitted-Finance | ₹13.2 Cr | L1 | Admitted-Finance |
| 2 | Not Admitted-Finance | - | - | Not Admitted-Finance Not qualified for AOC |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | halko infraprojects L1 |
|---|---|---|---|---|
| 1.00SURVEY, SOIL INVESTIGATION, PLANNING, DESIGNING, CONSTRUCTING MIG/LIG/SHOPS/AND AND OBTAINING ALL RELEVENT PERMISSIONS & REQUIRED COMPLETION / OCCUPATION CERTIFICATE FROM CONCERNED LOCAL AUTHORITY ON LUMP-SUM TURNKEY BASIS ON OPEN PLOT OB-9(OLD OB 8/1,8/2,8/3), NEAR SULBHA SCHOOL , TILAK NAGAR ,CHEMBUR- MUMBAI.-71, | ||||
| 1.10 | I// WE HEREBY QUOTE RATE IN (IN FIGURE) RS. __________________ PER SQ. MTR. (IN WORDS) RUPEES ______________ _____ _______ ________ PER SQ. MTR. OF BUILT UP AREA FOR THE CONSTRUCTION OF BUILDING COMPRISING RESIDENTIAL TENEMENTS, UNDER LIG / MIG / HIG AND N.R. TENEMENTS. I/WE ALSO AGREE TO EXECUTE THE WORK AS PER THE SCOPE OF WORK,SPECIFICATIONS, TERMS AND CONDITIONS OF TENDER.
Note: -
1) The Built-up Area of building shall be actual construction area of building along with lift and staircase, balcony, lift room, pump and meter room, common passages, society office, watchman cabin and Non-Residential tenements. As regards the stilt portion, the actual area under staircase, lift well, society office and servant’s toilet will be considered at 100% of the construction area. The remaining stilt area will be counted at 50% of the construction area. As regards the stilt portion, the actual area under , lift well, society office and servant’s toilet will be considered at 100% of the construction area. Any other component shall not be included in built up area calculations. The area calculations for payment shall be got certified / approved from Chief Architect & Planner MHADA. In case of any dispute regarding Built Up Area Calculation, the decision of Dy. Chief Engineer (East) / M.B. shall be final and binding on Construction Agency.
2) The housing schemes LIG, MIG, HIG and NR means Lower Income Group, Middle Income Group, Higher Income Group and Non-Residential tenements respectively.
3) ''The rate to be quoted shall be inclusive of all taxes, Labour cess and dues other levies that are imposed by Government from time to time and increase in any of the taxes, excise, octroi, duties, royalties, any other non reimbursable charges Excluding GST Charges towards MCGM and local authorities paid seperetely at the submission of demand.
Signature of Construction Agency | 4,573.95 | Per Square Meter | 28,850 ₹13.2 Cr |
Tender Value
₹8.8 Cr
EMD Value
₹4.4 L
Closing Date
16 Jan 2020, 3:00 pmClosed
EXECUTIVE ENGINEER KURLA MUMBAI BOARD
ROOM NO 341, SECOND FLOOR, GRIHNIRMAN BHAVAN, KALANAGAR, BANDRA EAST, MUMBAI 51
ON OPEN PLOT OB-9 (OLD OB 8-1,8-2,8-3), NEAR SULBHA SCHOOL , TILAK NAGAR ,CHEMBUR- MUMBAI.-71,
2019_MHADA_521798_1
EEKURLA/MB/E-TENDER-5/1/19-20
Open Tender
Civil Works - Buildings
730 days
TILAK NAGAR CHEMBUR
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,360
Online Payment
₹4.4 L
Yes
Bharatratna Gulzarilal Nanda meeting hall
7 Jan 2021
16 Dec 2019
20 Jan 2020
16 Dec 2019
16 Jan 2020
17 Dec 2019
23 Dec 2019
Amount
SURVEY, SOIL INVESTIGATION, PLANNING, DESIGNING, CONSTRUCTING MIG/LIG/SHOPS/AND AND OBTAINING ALL RELEVENT PERMISSIONS & REQUIRED COMPLETION / OCCUPATION CERTIFICATE FROM CONCERNED LOCAL AUTHORITY ON LUMP-SUM TURNKEY BASIS ON OPEN PLOT OB-9(OLD OB 8/1,8/2,8/3), NEAR SULBHA SCHOOL , TILAK NAGAR ,CHEMBUR- MUMBAI.-71,
I// WE HEREBY QUOTE RATE IN (IN FIGURE) RS. __________________ PER SQ. MTR. (IN WORDS) RUPEES ______________ _____ _______ ________ PER SQ. MTR. OF BUILT UP AREA FOR THE CONSTRUCTION OF BUILDING COMPRISING RESIDENTIAL TENEMENTS, UNDER LIG / MIG / HIG AND N.R. TENEMENTS. I/WE ALSO AGREE TO EXECUTE THE WORK AS PER THE SCOPE OF WORK,SPECIFICATIONS, TERMS AND CONDITIONS OF TENDER. Note: - 1) The Built-up Area of building shall be actual construction area of building along with lift and staircase, balcony, lift room, pump and meter room, common passages, society office, watchman cabin and Non-Residential tenements. As regards the stilt portion, the actual area under staircase, lift well, society office and servant’s toilet will be considered at 100% of the construction area. The remaining stilt area will be counted at 50% of the construction area. As regards the stilt portion, the actual area under , lift well, society office and servant’s toilet will be considered at 100% of the construction area. Any other component shall not be included in built up area calculations. The area calculations for payment shall be got certified / approved from Chief Architect & Planner MHADA. In case of any dispute regarding Built Up Area Calculation, the decision of Dy. Chief Engineer (East) / M.B. shall be final and binding on Construction Agency. 2) The housing schemes LIG, MIG, HIG and NR means Lower Income Group, Middle Income Group, Higher Income Group and Non-Residential tenements respectively. 3) ''The rate to be quoted shall be inclusive of all taxes, Labour cess and dues other levies that are imposed by Government from time to time and increase in any of the taxes, excise, octroi, duties, royalties, any other non reimbursable charges Excluding GST Charges towards MCGM and local authorities paid seperetely at the submission of demand. Signature of Construction Agency
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.45 MB
DTPPDFTILAKNAGAROB9.pdf
Tender Documents • 6.67 MB
BOQ_915014.xls
BOQ • 0.22 MB
Download all tender documents and submit your bid