Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹43.7 LAdmitted-Finance FLAT NO 1004 BUILDING NO L 11 KEDAR HOUSING SOCIETY 10TH FLOOR SECTOR NO 21 TALOJA PHASE 2 PANVEL RAIGAD NAVI MUMBAI 410208 | NAVI MUMBAI | RAIGAD | MAHARASHTRA | 410208 | ₹43.7 L | L1 | Admitted-Finance |
| 2 | L2₹53.4 LAdmitted-Finance | ₹53.4 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | WELWAYS ENGINEERS INDIA L2 | M/s ASPIRE ENGINEERING ENTERPRISES L1 |
|---|---|---|---|---|---|
| 1.00 | Manning, operation and comprehensive maintenance of complete 1 MW On Grid type Solar photo Voltaic Plant (SPV) Project at Jalandhar with SCADA system having Polycrystalline PV module 330Wp (system voltage 1500 volt) - 3176 Nos, Vacuum Circuit breaker 800 Amp - 01 No, String Combiner Box - 04 Nos, Power control unit with inverters 500 KW - 02 Nos (make ABB), Step Up Transformers 1250 KVA - 01 Nos Make Voltamp, SCADA System for solar plants with all sensors i.e. pyranometer, temp sensor, Weather monitoring sensor etc and metering equipment's installed.
Plant Description
Location - Jalandhar Cantt
Latitude - 31.2825822
Longitude - 75.6325972
DC Capacity - 1048 KWp
AC cap - 1 MW
Design and drawing documents - Available
Commissioning date - 27 Jan 2021
Operational Acceptance - Yes
DISCOM - PSPCL
Connectivity voltage - 11kV
Main Grid - 66 kV, solar connected with 11 kV at MH
The defects to be recified by the sucessful Bidder:-
(a) Ambient Temp sensor not working
(b) Module temp sensor not working.
(c) Pyranometer (Inrradiation tilt) - Data is not showing in SCADA system. | 11 | Per Month | 2,72,000 ₹29.9 L | 1,82,000 ₹20.0 L |
| 1.01(e) Module Temperature Data - Not showing in SCADA system. (f) PV modules not working. (g) String not working due to DC cable fault. (h) Module surface temperature not shown. (i) Ambient temperature not shown in scada. Major Eqpt Details:- i) Module - 3176 Nos - 330 Wp, system voltage 1500VDC, Make Waaree ii) No. of modules / strings - 40 Nos approx (DC 1000V 400A) iii) Inverter - 02 Nos - 500 Kw, Model No PVS 800, Make ABB iv) Data logger - 1 v) WMS - Pyranometer (irradiation meter - 4 Nos Make - Kipp & Zonen - Wind speed meter -1 Nos Make - Trinity - Module Temp sensor & Ambient temperature sensor - 1 Nos, IMT Technology Make - Trinity vi) ESE type Lighting Arrester- 2 Nos Make- JMV LPS vii) 11KV VCB 800Amp-01 Nos, ix) HT Cable of size 185sqmm 3 core-290 Mtrs approx x) ,DC Cable- 1176 Mtrs, xi) LT Cable of size 95 sqmm 3 core - SCB to Inverter & Inverter to Transformer - 1200 Mtr approx xii) String combiner Box - 04 Nos SCOPE OF WORKS FOR OPERATION AND MAINTENANCE 1. Reference to latest guidelines promulgated by SECI on the subject. | |||||
| 1.022. As per Performance Obligation. the contractor shall maintain minimum Capacity Utilisation Factor (CUF) of 13%. The historical performance of the plant and guaranteed annual CUF is given as under:- Guaranteed CUF of the Plants Name of the site-Jalandhar Cantt, Capacity-01 MW (a) 2021-22(27 Jan 2021 -31 Mar 2022)- 10.71% (b) 2022-23(01 Apr 2022 -31 Mar 2023)- 13% (c) 2023-24(01 Apr 2023 -31 Mar 2024)- 11.87% (d) 2024-25(01 Apr 2024 -10 Dec 2024)- 13.90% Generation (KWH) Report of the plant in last five years Name of the site- Jalandhar Cantt,Capacity- 01 MW (a) 2021-22(27 Jan 2021 -31 Mar 2022)- 169883 KWH (b) 2022-23(01 Apr 2022 -31 Mar 2023)- 1089784 KWH (c) 2023-24(01 Apr 2023 -31 Mar 2024)- 1217604 KWH (d) 2024-25(01 Apr 2024 -31 Mar 2025)- 1119296 KWH (e) 2025-26 (1 Apr 2025-31 Dec 2025)- 534696 KWH Note:- 1. The succsesfull bidder shall rectify the defects within 45 days of acceptance of the work order in the both the solar power plants such that minimum capacity utlisation factor (CUF) of 13% for plants is maintained. 2. Reducinq plant downtime. The Contractor shall ensure the plant availability upto 99%. However, the plant availability due to grid outages will be considered only if the same are certified by the competent authority/ GE. Any other outages which are not attributable to the Contractor and are certified by Department may also be considered. | |||||
| 1.033. Linear degradation of the module output (i.e., 0.75% of DC capacity at Std temp Condition per year) shall be considered for the calculation of CUF every year. 4. In order to optimize the useful life of the equipment of power plant, the Contractor shall carryout out necessary routine, breakdown and preventive maintenance as per schedules provided. The Contractor shall perform periodic overhauls and preventive maintenance required for the Plant and equipments in accordance with the recommendations of equipment manufacturers (as mentioned in PS). 5. Contractor shall carry out the performance monitoring for the Plant Facility on continuous basis and in case of any deviation, the Contractor shall perform the due diligence appropriately to find out the actual root cause of such deviation. Any test or inspection required such as thermal imaging, Current Voltage (IV) characteristics test etc. to analyse such deviation will be the responsibility of the Contractor. Thereafter, the action required to mitigate such deviation shall be undertaken by the Contractor without any additional cost. 6. The Safety, Record keeping, Coordination, Data Access, Statuary & Legal compliances, Joint Meter Reading, Spares shall also be the Contractor's responsibility. | |||||
| 1.047. The Contractor shall prepare the initial Annual Operating Plan for the Plant Facility and shall indicate the proposed resources (manpower, material, tools and tackles) that would be deployed for O&M subject to a minimum of following, the cost of same is included in quoted rates: (a) Manpower (i) Minimum one Engineer (Degree in electrical Engineering with 02 years of experience in working in O&M of Solar PV Plants or a relevant Diploma in Engineering with at least 3 years of experience of working in O&M of solar PV plants will responsible for plant operation and maintenance. (ii) 01 Nos of skilled electrician in a shift of 08 hours (Min 1 shift per day) having 10+2 with min 3 year experience in relevant field. (iii) 03 Nos of unskilled Labour in day shift of 08 hours (iv) 01 No unskilled labour in a shift of 8 hours (Min 2 shifts per day i.e. Evening, Night) (iv) The contractor shall employ only such personel who are adequately qualified and experienced in Solar PV Project. The contractor shall submit adhar linked t bank statement for monthly payment made to employed personnel, ESI as applicable within one week after acceptence of work . In case of absenteeism, a recovery of Rs 700 per Helper and Rs 1000 per electrician and Rs 1300 per Engineer will be levied. THe quoted rate include cost of reliver reqd for weekly off for employed manpower for electrician and helper. | |||||
| 1.05(b) Tools/Plants/Testing Equipments As per site and OEM recommendations within quoted rates. (c) Spares: The Contractor shall maintain required Spare Plant Equipment., Spare Parts, Tools and Plants, Consumables required for comprehensive operation and maintenance of the plant faciltiy. The Contractor shall make arrangement to procure required spare parts, or equipments as required, overhauling of parts, tools and equipment, required to operate and maintain the Plant in accordance with the recommendations of individual Original Equipment Manufacturer (OEM) at his/ her own cost. Minimum spares required to be maintained by the succesful bidder. Notes: The scope also include washing/cleaning of Solar PV Modules fortnightly basis as per pre-planned schedule as got approved from deptt by contractor and cost of T&P (wiper long handle, grass cutting machine, ladder etc), Labour required at site is deemed to be included in quoted rates. The contractor shall have to purchase LEVEL- I AMC plan for Inverter - 2 Nos from ABB within overall quoted rates. b) Checking electrical parameter of the installed power plant.Any job other than above indicated jobs would be covered under warranty of Solar Plant installed. | |||||
| 1.06c) Keeping the area neat and clean and free from vegetation growth all over ground in solar plant(Note: Recovery to be deducted at the rate of Rs 1000/day if not found clean during visit) d) Material and Labour for replacement of defective power condition units(PCU)/Inverters /String invertor with maximum power point tracker/Tracking (MPPT) feature,cable and other electrical works shall be included in the O&M Quoted Cost. e) Cost of equipment and spare parts shall be included in the O&M quoted Cost. f)The Operator shall operate and maintain the Plant in accordance with the provisions of this O&M Plan/O&M Procedures and Good Industry Practices. g) Operator shall observe and strictly comply with the Applicable Laws for the operation and maintenance of the Plant in accordance with the provisions of this O&M . h) Measurement & monitoring of the electricity production through appropraite monitoring systems for the period of the Term of the contract. A) Operations j) The following will be monitored : i) Measurement and calculations of the Plant current and nominal performance . ii) Any unusual conditions found during operations/inspections. iii) Any system disturbances/outages iv) Monthly report of the solar plant generation is to be provided by Contractor. | |||||
| 1.07B) Maintenace i) The Operators shall be responsible for ensuring smooth operations of all components. ii) To inspect and maintain periodically the plant equipment as per the preventive and curative maintenance schedule. iii) The operators shall carry out PV module cleaning Twice every month min or as required for effective generation as required. iv) Spares such as MCB,MCCBs,Fuses,DC Fuses,Al cards such as input/output Card ,power supply card ,processor card ,PV Modules, Glands,lugs,MC4 connectors,tie connectors,clamps,cable Ties and all other consumables/spares which are required for uninterrupted O&M of the Plant should be kept readily available at Site . The quoted rate include cost of the all such items reqd (except mentioned in Sr No 2 to 10) in rate quoted for Item No 1. v) The Contractor shall provide an inventory report items consumed to the departmment on a monthly basis. vi) The Contractor has to use the mandatory spares(s) available at site for replacing defective part(s) of equipment for minimizing system outage temporarily and top up the quantity of spares so that the required quantity of spares shall be made available at site at all times and shall be handed over to the department at the end of O&M Period .The cost of spares is deemed to be incl in the quoted cost. | |||||
| 1.08vii) The Contractor is bound to provide mentioned manpower. However, the above mentioned manpower is minimum. If highe number of manpower is required to ensure smooth functioning of plant. the cost of same will be deemed to included in quoted rates. Contractor shall get duty roster and shift timing approved from deptt well in advance required for smooth maintenance. The rate quoted include cost of items reqd for maintenance inclusive of daily,weekly,quarterly ,half yearly maintenance including all consumable material and chemicals as required and other spares required. viii) Earthing Register has to be maintained by the Contractor.The earthing values of all Earting mentioned in Appx'A' of LA and Solar Earthing is mandatory and any earthing material required to recharge of the earth pit shall be borne by the Contractor. The cost of New Earthing alongwith connected accessories like earthing strip,excavation etc if required to executed at site is deemed to be incl in the quoted rates. Note: if the Earthing Value comes to be more than 3 Ohm .The Contractor has to recharge and make good the earthing value.If required he has to execute new earth pit at no extra cost to the department .In case of Non compliance a penalty of Rs 500 Per day per earthing shall be levied .And the same shall be recovered from his Payment. | |||||
| 1.09ix) The Operators shall perform the services in relation to the Plant in accordance with the safety manageement plans.SOPs and procedures as applicable and/or in accordance with accepted industry practise.The operators shall adhere to the health and safety standard. In this respect the Department shall not be liable for any accidents or untoward events. x) The Contractor,for any major equipment fail such as Inverters/Solar Module/ACDB shall repair/replaced the equipment on free of cost basis. The Old Inverter and Solar PV Module shall not be a property of Contractor and has to be deposited by him in the MES Store. Preventive Maintenance Schedule & Checklist 1) PV Module cleaning after 15 Days min. 2) Module Interconnects Tightness -Visual Check Monthly 3) Integrity of Cable Terminations in Junction Box in Visual Check-Monthly 4) Visual Inspection of Cracked ,Chipped and Broken Modules-Monthly 5) Visual Inspection of Rodent Attacks on Cable Conduits -Monthly 6)Visual Inspection of Junction Box & Combiner Box enclosures -Monthly 7) Hardware on Structures - Monthly 8) Vertical Post Structures Rigidity -Visual Check Quarterly 9) Earthing Strip Check Visual Check-Monthly 10) DC and AC termination checks and retightening as required in Inverters -Visual Check-Half Yearly 11)Cleaning of Filters in Suction Side of Inverters -Monthly MANDATORY SPARES: | |||||
Updated dates
Tender Value
₹49 L
EMD Value
₹98,000
Closing Date
30 May 2026, 6:00 pmClosed
Garrison Engineer (East) JRC
Garrison Engineer (East) JRC
COMPREHENSIVE REPAIR/ MAINTENANCE OF SPV POWER PLANT 01 MW UNDER GE (EAST) JALANDHAR CANTT
2026_MES_754909_2
GE/JULL/ET-74/2025-26
Open Tender
Electrical and Maintenance Works
273 days
Garrison Engineer (East) JRC
As per tender document
8 documents required · 8 mandatory
₹500
Garrison Engineer (East) JRC
₹98,000
Yes
8 Jun 2026
9 May 2026
2 Jun 2026
9 May 2026
30 May 2026
16 May 2026
Manning, operation and comprehensive maintenance of complete 1 MW On Grid type Solar photo Voltaic Plant (SPV) Project at Jalandhar with SCADA system having Polycrystalline PV module 330Wp (system voltage 1500 volt) - 3176 Nos, Vacuum Circuit breaker 800 Amp - 01 No, String Combiner Box - 04 Nos, Power control unit with inverters 500 KW - 02 Nos (make ABB), Step Up Transformers 1250 KVA - 01 Nos Make Voltamp, SCADA System for solar plants with all sensors i.e. pyranometer, temp sensor, Weather monitoring sensor etc and metering equipment's installed. Plant Description Location - Jalandhar Cantt Latitude - 31.2825822 Longitude - 75.6325972 DC Capacity - 1048 KWp AC cap - 1 MW Design and drawing documents - Available Commissioning date - 27 Jan 2021 Operational Acceptance - Yes DISCOM - PSPCL Connectivity voltage - 11kV Main Grid - 66 kV, solar connected with 11 kV at MH The defects to be recified by the sucessful Bidder:- (a) Ambient Temp sensor not working (b) Module temp sensor not working. (c) Pyranometer (Inrradiation tilt) - Data is not showing in SCADA system.
(e) Module Temperature Data - Not showing in SCADA system. (f) PV modules not working. (g) String not working due to DC cable fault. (h) Module surface temperature not shown. (i) Ambient temperature not shown in scada. Major Eqpt Details:- i) Module - 3176 Nos - 330 Wp, system voltage 1500VDC, Make Waaree ii) No. of modules / strings - 40 Nos approx (DC 1000V 400A) iii) Inverter - 02 Nos - 500 Kw, Model No PVS 800, Make ABB iv) Data logger - 1 v) WMS - Pyranometer (irradiation meter - 4 Nos Make - Kipp & Zonen - Wind speed meter -1 Nos Make - Trinity - Module Temp sensor & Ambient temperature sensor - 1 Nos, IMT Technology Make - Trinity vi) ESE type Lighting Arrester- 2 Nos Make- JMV LPS vii) 11KV VCB 800Amp-01 Nos, ix) HT Cable of size 185sqmm 3 core-290 Mtrs approx x) ,DC Cable- 1176 Mtrs, xi) LT Cable of size 95 sqmm 3 core - SCB to Inverter & Inverter to Transformer - 1200 Mtr approx xii) String combiner Box - 04 Nos SCOPE OF WORKS FOR OPERATION AND MAINTENANCE 1. Reference to latest guidelines promulgated by SECI on the subject.
2. As per Performance Obligation. the contractor shall maintain minimum Capacity Utilisation Factor (CUF) of 13%. The historical performance of the plant and guaranteed annual CUF is given as under:- Guaranteed CUF of the Plants Name of the site-Jalandhar Cantt, Capacity-01 MW (a) 2021-22(27 Jan 2021 -31 Mar 2022)- 10.71% (b) 2022-23(01 Apr 2022 -31 Mar 2023)- 13% (c) 2023-24(01 Apr 2023 -31 Mar 2024)- 11.87% (d) 2024-25(01 Apr 2024 -10 Dec 2024)- 13.90% Generation (KWH) Report of the plant in last five years Name of the site- Jalandhar Cantt,Capacity- 01 MW (a) 2021-22(27 Jan 2021 -31 Mar 2022)- 169883 KWH (b) 2022-23(01 Apr 2022 -31 Mar 2023)- 1089784 KWH (c) 2023-24(01 Apr 2023 -31 Mar 2024)- 1217604 KWH (d) 2024-25(01 Apr 2024 -31 Mar 2025)- 1119296 KWH (e) 2025-26 (1 Apr 2025-31 Dec 2025)- 534696 KWH Note:- 1. The succsesfull bidder shall rectify the defects within 45 days of acceptance of the work order in the both the solar power plants such that minimum capacity utlisation factor (CUF) of 13% for plants is maintained. 2. Reducinq plant downtime. The Contractor shall ensure the plant availability upto 99%. However, the plant availability due to grid outages will be considered only if the same are certified by the competent authority/ GE. Any other outages which are not attributable to the Contractor and are certified by Department may also be considered.
3. Linear degradation of the module output (i.e., 0.75% of DC capacity at Std temp Condition per year) shall be considered for the calculation of CUF every year. 4. In order to optimize the useful life of the equipment of power plant, the Contractor shall carryout out necessary routine, breakdown and preventive maintenance as per schedules provided. The Contractor shall perform periodic overhauls and preventive maintenance required for the Plant and equipments in accordance with the recommendations of equipment manufacturers (as mentioned in PS). 5. Contractor shall carry out the performance monitoring for the Plant Facility on continuous basis and in case of any deviation, the Contractor shall perform the due diligence appropriately to find out the actual root cause of such deviation. Any test or inspection required such as thermal imaging, Current Voltage (IV) characteristics test etc. to analyse such deviation will be the responsibility of the Contractor. Thereafter, the action required to mitigate such deviation shall be undertaken by the Contractor without any additional cost. 6. The Safety, Record keeping, Coordination, Data Access, Statuary & Legal compliances, Joint Meter Reading, Spares shall also be the Contractor's responsibility.
c) Keeping the area neat and clean and free from vegetation growth all over ground in solar plant(Note: Recovery to be deducted at the rate of Rs 1000/day if not found clean during visit) d) Material and Labour for replacement of defective power condition units(PCU)/Inverters /String invertor with maximum power point tracker/Tracking (MPPT) feature,cable and other electrical works shall be included in the O&M Quoted Cost. e) Cost of equipment and spare parts shall be included in the O&M quoted Cost. f)The Operator shall operate and maintain the Plant in accordance with the provisions of this O&M Plan/O&M Procedures and Good Industry Practices. g) Operator shall observe and strictly comply with the Applicable Laws for the operation and maintenance of the Plant in accordance with the provisions of this O&M . h) Measurement & monitoring of the electricity production through appropraite monitoring systems for the period of the Term of the contract. A) Operations j) The following will be monitored : i) Measurement and calculations of the Plant current and nominal performance . ii) Any unusual conditions found during operations/inspections. iii) Any system disturbances/outages iv) Monthly report of the solar plant generation is to be provided by Contractor.
ix) The Operators shall perform the services in relation to the Plant in accordance with the safety manageement plans.SOPs and procedures as applicable and/or in accordance with accepted industry practise.The operators shall adhere to the health and safety standard. In this respect the Department shall not be liable for any accidents or untoward events. x) The Contractor,for any major equipment fail such as Inverters/Solar Module/ACDB shall repair/replaced the equipment on free of cost basis. The Old Inverter and Solar PV Module shall not be a property of Contractor and has to be deposited by him in the MES Store. Preventive Maintenance Schedule & Checklist 1) PV Module cleaning after 15 Days min. 2) Module Interconnects Tightness -Visual Check Monthly 3) Integrity of Cable Terminations in Junction Box in Visual Check-Monthly 4) Visual Inspection of Cracked ,Chipped and Broken Modules-Monthly 5) Visual Inspection of Rodent Attacks on Cable Conduits -Monthly 6)Visual Inspection of Junction Box & Combiner Box enclosures -Monthly 7) Hardware on Structures - Monthly 8) Vertical Post Structures Rigidity -Visual Check Quarterly 9) Earthing Strip Check Visual Check-Monthly 10) DC and AC termination checks and retightening as required in Inverters -Visual Check-Half Yearly 11)Cleaning of Filters in Suction Side of Inverters -Monthly MANDATORY SPARES:
Material & labour in replacement for Polycrystalline Solar Photovoltaic PV modules not less than 330Wp, 72 cells approx, system voltage 1500 VDC, MNRE approved suitable for existing solar plant. Note: Old unsv PV modules will be deposited in MES store yard.
Supply, laying, testing, jointing in replacement of annealed tinned copper conductor cable 1.8 KV DC EBXL Halogen free XLPO/ XLPO 120 degree centigrade, UV resistant ZH-FRLS single core 4 sqmm solar sheathed industrial solar cable complete all as specified and directed
Supply, laying, testing, jointing in replacement for annealed tinned copper conductor cable 1.8 KV DC EBXL Halogen free XLPO/ XLPO 120 degree centigrade, UV resistant ZH-FRLS single core 6 sqmm solar sheathed industrial solar cable complete all as specified and directed.
Supply and fixing in replacement for MC4 connector, IP-68, 1000V DC, rated current 30 Amp min to connect 6 Sqmm solar cable complete all as specified and directed. Make ELCOM or equivalent
Supply and fixing replacement MC4 connector 2 in 1 ( Y connector) in replacement for, IP-68, 1000V DC, rated current 30 Amp min to connect 6 Sqmm solar cable complete all as specified and directed. Make ELCOM or equivalent
Material & labour for Ambient Temperature sensor complete with housing, cable etc confirming to Model No Ta-ext-RS 485-MB of make IMT Technology complete
Material & labour for Solar PV module Temperature sensor complete with housing, cable etc with RS 485 port suitable for existing Solar plant, SCADA system of make IMT Technology complete
Material and labour in replacement for Air Filter, CC-CM518 x 540, AIR-TEX G-150 model, component/ part No 64665324 of ABB suitable for PVS 800 inveters complete.
Material and labour in replacement for Air Filter, AIR-TEXT, 518 x 540, AIR-TEX G-150 model, component/ part No 64666533 suitable for PVS 800 inveters complete.
Material and labour for RS-485 cable having overall double screen, PVC sheathed complete 2 pair, 0.5 Sqmm min complete.
Material and labour in replacement for Glavanized steel C Channel mounting structure for mounting solar panel complete
Material and labour in replacement for testing and commissioning of 11KV outdoor type CT PT Combo metering unit having BIL 28KV at 1minute power frequency with 75KV impulse withstand voltage with short time thermal current rating 18 KA at 3 sec min. having CT ratio 100/5A , burden 10VA , accuracy class 0.2 , having 3 Nos of PT's with ratio 11000V/110V, burden per phase 50 VA ,Accuracy class 0.2,voltage factor 1.2cont. & 1.5 for 30 seconds completely.
M&L in replacement Earthing complete with galvanised steel earth plate electrode 60cmx60cmx6mm thickness buried directly in ground (earth pit not less than 2.25 meters deep below ground level) with top edge of the plate not less than 1.5 meters below normal ground level, connected to galvanised earth strip 32x6 mm as earthing strip by means of GI bolts, nuts, check nuts and washers incl surrounded on all sides by 15cm thick layer of charcoal dust, salt, incl earth strip protected by 40mm dia GI light grade pipe, PCC pit of 1:2:4 & reinforced PCC top cover 50mm thick, earth pit angle frame of size 25mmx25mmx3mm with excavation and earth work in any type of soil, light grade GI watering pipe 20mm dia with funnel and wire-mesh complete all to as shown in electrical plate no 3 of SSR Part I 2009 connected main switch board or as reqd at site all as specified and testing on completion. (Note: The rate quoted include the cost of GI strip & GI protection pipe light 40mm dia bore light grade upto 7.5 metres. PCC Chamber shall be constructed at least 0.50 mtr away from on the earth pit electrode and pipe for watering shall be provided in slanting manner . (2) If the results are not found satisfactory, then 2nd earthing will be re-done without any cost payable to Contractor.
Material and labour for Earth continuity conductor or main earth lead fixed on wall on batten or recess or chases or burried in ground or drawn in conduit / pipe or fixed to pole or any other indicated as required on ground for 25x3 mm aluminium strip complete all as specified and as directed.
M&L for PCC 1:2:4 type C-2 using 40mm graded mechanically crushed stone aggregates for making good disturbed surfaces of roads / hard standing, etc. and finishing the top surfaces even and smooth without using extra cement complete all as specified and as directed
M&L for Checking of Earth Resistance test of existing Galvanised iron/copper conventional/Chemical Earthing for getting suitable resistant test complete all as specified and directed by Engr-in-Charge. Note :- (a) Contractor will Check Earth Resistance of test points and will be recorded in Register, same will be put up to the Engineer-in-Charge through concern JE E/M. (b) Necessary T&P will be provided by the Contractor. (Tester should be caliberated from NABL accredited labs). (c) Contractor will be responsible for pouring of water in the Earth Pits Weekly at his own arrangement with Water Tanker, etc. (d) Checking of Earth Pits existing and improve it by watering, adding of chemical etc. (Chemical will be measured and paid separately) (e) Contractor will be responsible for marking of Earth Check date and due date on existing Plate with paint as specified by Engineer-in-Charge. (f) Contractor will be responsible for cleaning of bushes, grass, sand etc inside and all around upto 1.50 Metre Area of existing Earth Pit with tightening of Strip. (g) Cost of register for noting earthing results, location wise shall deemed to be included with the unit rate. Proforma of detail column will be printed as per the direction of Engineer-in-charge. (j) The contractor is responsible for mainting the value of chemical earthing as per station norms as directred by Engr-in-Charge. (k) Grid if any nos of earth pits having one test point shall be considered as one point for measurement.
Supply and fixing of Earthing identifier marker of size 25x25 mm flat iron and 5 mm thick length of flat iron 75 cm long which is 60 cm FI above the Ground level and 15 cm length FI below the Ground level and fixed with PCC 1:2:4 (12.5 mm graded aggregate) in post holes and the TOP of the flat iron arabolic/ semicirculer/ traingular/rectangular shape MS plate 1.6 mm thick of size 30 cm width and 20 cm height to welded/fixing to the flat iron including two coat of synthetic enamel paint over a coat of primer on steel surface cutting for Equipment Earthing/Lighting Earthing/L2 Earthing etc complete all including Earth Plate No/Description of Earthing/Type of Earthing on Plate with white paint including earth plate no and earthing resistance with earthing check date and earthing check due date complete all specified and directed by Engineer in charge.
S & F in repair of 40 mm dia of GI tubing, light grade with all fittings including fixing arrangement with screws, reducer and clamps fasnig as protection of wire on wall/ roof with suitable type of clamp and proper fixing of insulator up to 15mtr building height etc complete all as specified and directed.
M&L for arresting leakages in GI pipe line of size 15/20mm bore by cutting, threading, cleaning including inserting of new fittings viz. nipples, unions, ferrule, reducer, elbows, tee, sockets, bends, pipe lengths, etc. as required including necessary arrangement to work viz. staging, etc. along heights of buildings (G+3) complete all as specified and as directed
S&F in repairs 15 mm bore gun metal globe or gate valve with iron wheel head, screwed both ends for iron pipe and fixed including necessary cutting into existing pipe, threading, inserting new piece of GI pipe of existing size, and earthwork in any type of soil or breaking/cutting into road/interlocking tiles/cement concrete, etc. and making good the disturbed surfaces as per existing complete all as specified and as directed
S&F in repair GI water tubing 15 mm bore 'medium grade', galvanized, with all fittings jointed and laid in trenches/wall/ceiling /plinth and make good as per existing complete all as specified and as directed by Engr-in-Charge.
S&F in repair GI water tubing 20 mm bore 'medium grade', galvanized, with all fittings jointed and laid in trenches/wall/ceiling /plinth and make good as per existing complete all as specified and as directed by Engr-in-Charge.
S&F in repair GI water tubing 25 mm bore 'medium grade', galvanized, with all fittings jointed and laid in trenches/wall/ceiling /plinth and make good as per existing complete all as specified and as directed by Engr-in-Charge.
M & L for construction of cement concrete earth pit chamber in PCC 1:3:6, type C-1, 450 X 450 X 50 mm thick Pre-cast RCC cover in cement concrete 1:2:4, type B-1, duly reinforced with 8 mm dia mild steel TMT bars with fair finished concrete surfaces including necessary formwork and earth work as required/ordered at site, complete all as specified and as directed.
M&L for replacement of Pre-cast RCC Cover with Handle 2 Nos and hole of dia 40mm in Cement Concrete 1:2:4 (20mm graded stone aggregate) of size 540x540x60mm, reinforced with and including 10mm dia TMT Bars @ 250mm Centre to Centre in both ways, complete all as specified and as directed.
S & F LED street light fitting 60 watts,made up of pressure die-cast aluminium housing with toughened glass/PC embedded lens with Pressure Die Cast Aluminium Housing with mandatory secondary optics lenses, with SS screws, IP-66, luminaire efficacy more than 100 Lm/W min, CCT 5700K ANSI, CRI>70, THD<10%, PF >0.95, LED source : Hi power LED 3 to 5W, having external potted Constant Current driver moisture resistant (installed in separate independent compartment) with internal surge protection 4KV having under voltage, over voltage, phase to phase protection and short circuit protection and auto recovery mode, operating range 150 V to 270 V AC at 50Hz, Auto Cut off >300 V and with separate external Surge protection device 10 KV suitable for fitting on 40 mm dia bore pipe bracket including making connections with PVC insulated 3 core copper conductor cable 0.75 Sqmm min of suitable length complete all as specified.
S&F junction box complete with fixing accessories. The Junction Box shall be insulated and made out of Polycarbonate/Thermoplastic with glass fiber reinforced. The Polycarbonate J. Box shall be environment friendly, recyclable, UV resistant, halogen & silicon free, anti acid & anti corrosive. The Junction Box Minimum Size 160 x 200 x 98mm minimum. The Junction Box with Knock out on four side wall. The Junction Box shall be rated for Degree of Ingress Protection IP 66 in accordance with IEC 60529. The gasket material shall be Polyurethane and the gasket shall be internally embedded. The Junction Box shall be complies with requirements of the standards IEC 60998-1& IEC 60998-2-1, with one number 10 Amp MCB SP 10KA. Make :- Cat Part No. KM 9250 Hensel,/ Schneider/GE Power/ABB or euivallent as approved by GE.
Supply and fixing in replacement bracket made out of 40 mm dia bore GI pipe light grade tubing 1.2 metre long, and bent to shape at 120 degree angle with reqd holes for passing connection cable, fixed with clamps nuts and bolts, washer complete all as specified . (Clamps, nut, bolts and washers will be measured and paid separately).
M & L for preperation of old painted surface of steel tubular poles 9/11 meter long and two coat of aluminium oxide paint complete & numbering of poles in black colur all as specified & directed by Engineer-in-charge.
M&L Replacement of PVC insulated PVC sheathed copper conductor cabe of 0.75 Sqmm, 3 core complete for street light and making connections all as specified and directed.
S & F in replacement 35 watt Solar street light compact fully integrated intelligent designed luminaire integrated with lithium ferro phosphate battery, solar panel & charger built into the luminaire 100 % solar powered , solar panel disk to dawn operation with short circuit protection, reverse voltage polarity protection and PV reverse voltage polarity protection, luminaire efficiency 150 lm/W , maintenance of lumen output, opeartiong temp range -10C to 50 C all as specified and directed by engr-in charge
S & F standard Electric Shock chart as per BIS 1986 in size 50 x 70 Cm Hindi English Langauage Multicolour printing 80 GSM Litho Paper laminated on both sides with 30 Micronthick plastic film framed in good quality wooden glass frame
S & F standard Fire Incident chart as per BIS 3034 in size 50 x 70 Cm Hindi English Langauage Multicolour printing o 80 GSM Litho Paper laminated on both sides with 30 Micronthick plastic film framed in good quality wooden glass frame
Supply and laying Rubber mat of sizes 20 MM thickness x 1 Mtr width and 2 Mtr length as per IS 15652-2006, (superseding IS 5424) suitable for electrical shock safety upto 11 KV Voltage all as specified and directed for electrical purpose
Supplying, laying, jointing and testing and commissioning 185 sqmm, 3.5core XLPE insulated, screened, PVC bedded galvanised steel strip or wire armoured electric power cable heavy duty multi stranded aluminium conductor and PVC sheathed LT cable 1100 volts grade conforming to IS-7098 laid in trenches/ ducts/ fixed on poles/wall/laid under roads/paths/drain/culverts or passing through pipes complete all as specified and directed.
Supplying, laying, jointing and testing and commissioning 95 sqmm, 2core XLPE insulated, screened, PVC bedded galvanised steel strip or wire armoured electric power cable heavy duty multi stranded COPPER conductor and PVC sheathed LT cable 1100 volts grade conforming to IS-7098 laid in trenches/ ducts/ fixed on poles/wall/laid under roads/paths/drain/culverts or passing through pipes complete all as specified and directed.
Supply , Laying DWC pipe size 90 mm OD/75 Mm ID by excavated method complete all as specified and directed
Excavation in trenches in soft/loose soil not exceeding 1.50 mtr wide and not exceeding 1.50 mtr in depth for laying of cables and getting out complete all as specified and directed by Engineer-in-Charge.
Returing, filling in, including spreading, leveling watering and well ramming inlayers not exceeding 25 cms thick each layer compete all as specified and directed by Engineer-in-Charge.
Removal of surplus soil to a distance not exceeding 50 mtr and depositing where directed at a level not exceeding 1.5 mtr above the starting point complete all as specified and directed by Engr-in-charge.
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.25 MB
Tender74.pdf
Tender Documents • 1.21 MB
BOQ_856175.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid