| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.7 CrAccepted-AOC | ₹1.7 Cr | L1 | Accepted-AOC Rates of Lowest Estimated Rates hence Date of Start Issue. |
| 2 | L2₹1.7 Cr+₹3.9 L (2.30%)Rejected-Finance | ₹1.7 Cr+₹3.9 L (2.30%) | L2 | Rejected-Finance Rates of Lowest Estimated Rates. Rates of Ist Lowest. |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not Pre Qualified |
| 4 | Rejected-Technical | - | - | Rejected-Technical Not Pre Qualified |
Tender Value
₹2.1 Cr
EMD Value
₹4.1 L
Closing Date
5 Mar 2020, 12:00 pmClosed
SUPERINTENDING ENGINEER
SUPERINTENDING ENGINEER VTH CIRCLE IRRIGATION WORKS BAREILLY
SHARDA MAIN CANAL KE KM 6.010 PER NIRMIT JAGBOODHA SYPHONE KI SURAKSHA HETU MARRMMAT EVAM SURDIKARAN KA KARYA
2020_UPIDC_439533_1
04/SE/2019-20
Open Tender
Civil Works
Item Rate
90 days
BANBASSA
Please refer Tender documents.
2 documents required · 2 mandatory
₹300
EX. ER. HEAD WORKS DIVISION SHARDA CANAL BAREILLY
₹4.1 L
Yes
23 Jan 2021
27 Feb 2020
5 Mar 2020
27 Feb 2020
5 Mar 2020
27 Feb 2020
Amount
E/W in excavation in foundation lift up to 1.50 m. and lead up to 30 m. in all type of soil with labour and T&P etc. required for proper completion of work.
Laying and filling R.B.M. in slope of pitching making profile including all cost of material, labour, T&P etc. required for completion of work.
Laying dry stone pitching 0.23 M thick with 20-40 Kg. size boulder in slope of pitching including cost of all material, labour and T&P etc. required for proper completion of work.
Shuttering for C.C. Blocks and concrete including cost of all material, labour and T&P etc. required for proper completion of work.
Laying C.C. M-20 (1:1.5:3) cement, coarse sand & shingle/grit 12 to 20 mm gauge in bed block including cost of all material, labour and T&P etc. required for proper completion of work.
Providing and dumping boulder 40-60 Kg. in scour portion including cost of all material, labour and T&P etc. required for proper completion of work.
Providing and laying hand packed boulder 20-40 Kg. in G.I. wire crate size (3.00x1.50x1.00M) in launching apron and slope erosion including cost of all material, labour and T&P etc. required for proper completion of work.
Tor Steel Reinforcement i/c cost of it’s straightening, cutting, bending, placing & binding in position i/c cost of all material, labour and T&P etc. required for proper completion of work.
R.C.C. M-25 (1:1:2) in cement, coarse sand and grit/shingle 12 to 20 mm. gauge including cost of all material, labour and T&P etc. required for proper completion of work.
Earthwork in embankment by power transported earth with a lead beyond 200 m. and up to 1.00 km. by tractor trolly including excavation, loading, unloading, royality, manual compaction & dressing with all lifts for proper completion of work.
M/S DWARIKA DHEESH CONSTRUCTIONS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .