Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
18 Sept 2026, 12:00 pm7d left
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
SRDEN1
16 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or V whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The balance sheet and all other financial documents attested/certified by the Chartered Accountant (CA) to substantiate fulfilment of Financial Eligibility Criteria should be with UDIN, failing which the offer shall be considered as incomplete and will be summarlly rejected without any further reference as per CE/Works/HJP letter No.ECR- HQ0ENGG(CONT)/0009/2025, dt.18.11.2025.
(a) The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender. (b) (1) In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for b(1): Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. (b)(2)In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity. (b) (3) To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contractor through subcontractor fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the offer for considering subletting of that scope of work towards fulfilment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows: The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years,ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway.
In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract, with prior approval of Chief Engineer in writing. Note for Item 10.1: Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Defination of Similar Work :- Any P.Way work.
50 conditions · 14 needing a document upload
The tenderers other than Company/Proprietary firm, shall submit Annexure V(A). Annexure -V(A) shall also be submitted by the each member of a Partnership Firm /Joint Venture(JV)/Hindu Undivided Family (HUF)Limited Liability Partnership (LLP) etc. as the case may be. Non submission of above certificate(s) by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self-attested/digitally signed by which they/he are/is qualifying the Qualifying Criteria mentioned in the Tender Document.
The following documents should be specified for submission along with tender:
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Please submit bank details of the firm individual JV/partnership etc. i.e. name of the bank along with bank branch code, account number, IFSC code, PAN number and other necessary & relevant documents.
List of completed works being submitted for fulfilment of eligibility criteria for similar nature of work must give description of work,, organization for whom executed, approximate value of contract at the time of award, date of award and date of scheduled completion of work, date of actual start, actual date of completion and final vaule of contract at the time of bill finalisation should also be given.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Letter of credit as mode of payment in works tenders or service tenders is available. If is an option for the contractor to take payment from Railways through a letter of credit (LC) arrangement. The details letter of credit as annexure B is available at document section
The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person specifically authorizing him/them to submit the tender, sign the agreement, receive money, co-ordinate measurements through contractor's authorized engineer, witness measurements, sign measurement books, compromise, settle, relinquish any claim(s) preferred by the firm and sign "No Claim Certificate" and refer all or any disputes to arbitration.
The above power of attorney shall be submitted even if such specific person is authorized for above purposes through partnership deed / Memorandum of Understanding / Article of Association or such other document, failing which tender is liable to be rejected.
Documents to be Submitted Along with Tender (i) The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered Trust / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc. The tenderer(s) shall enclose the attested copies of the constitution of their concern, and copy of PAN Card along with their tender. Tender Documents in such cases are to be signed by such persons as may be legally competent to sign them on behalf of the firm, company, association, trust or society, as the case may be. (ii) Following documents shall be submitted by the tenderer:
Following documents shall be submitted by the tenderer in case of Sole Proprietorship Firm: (i) All documents in terms of Para 10 of the Tender Form (Second Sheet of GCC-2022).
Following documents shall be submitted by the tenderer in case of HUF: (i) A copy of notarized affidavit on Stamp Paper declaring that he who is submitting the tender on behalf of HUF is in the position of 'Karta' of Hindu Undivided Family (HUF) and he has the authority, power and consent given by other members to act on behalf of HUF. (ii) All other documents in terms of Para 10 of the Tender Form (Second Sheet of GCC- 2022).
Following documents shall be submitted by the tenderer in case of Company registered under Companies Act 2013: (i) The copies of MOA (Memorandum of Association) / AOA (Articles of Association) of the company (ii) A copy of Certificate of Incorporation (iii) A copy of Authorization/Power of Attorney issued by the Company (backed by the resolution of Board of Directors) in favour of the individual to sign the tender on behalf of the company and create liability against the company. (iv) All other documents in terms Para 10 of the Tender Form (Second Sheet of GCC-2022).
Following documents shall be submitted by the tenderer in case of LLP (Limited Liability Partnership): (i) A copy of LLP Agreement (ii) A copy of Certificate of Incorporation (iii) A copy of Power of Attorney/Authorization issued by the LLP in favour of the individual to sign the tender on behalf of the LLP and create liability against the LLP. (iv) An undertaking by all partners of the LLP that they are not blacklisted or debarred by Railways or any other Ministry / Department of the Govt. of India from participation in tenders / contracts as on the date of submission of bids, either in their individual capacity or in any firm/LLP or JV in which they were / are partners/members. Concealment / wrong information in regard to above shall make the contract liable for determination under Clause 62 of the Standard General Conditions of Contract. (v) All other documents in terms of Para 10 of the Tender Form (Second Sheet of GCC-2022).
The tenderer shall clearly specify that the tender is submitted on behalf of a partnership firm. The following documents shall be submitted by the partnership firm, with the tender: (i) A notarized copy of the Partnership Deed or a copy of the Partnership deed registered with the Registrar. (ii) A notarized or registered copy of Power of Attorney in favour of the individual to tender for the work, sign the agreement etc. and create liability against the firm. (iii) An undertaking by all partners of the partnership firm that they are not blacklisted or debarred by Railways or any other Ministry / Department of the Govt. of India from participation in tenders / contracts as on the date of submission of bids, either in their individual capacity or in any firm/LLP in which they were / are partners/members. Any Concealment / wrong information in regard to above shall make the bid ineligible or the contract shall be determined under Clause 62 of the Standard General Conditions of Contract. (iv) All other documents in terms of Para 10 of the Tender Form (Second Sheet of GCC-2022).
Following documents shall be submitted by the tenderer in case of Registered Society & Registered Trust (i) A copy of Certificate of Registration (ii) A copy of Memorandum of Association of Society/Trust Deed (iii) A copy of Power of Attorney in favour of the individual to sign the tender documents and create liability against the Society/Trust. (iv) A copy of Rules & Regulations of the Society (v) All other documents in terms of Para 10 of the Tender Form (Second Sheet of GCC-2022).
The Railway reserves the right to verify all statements, information and documents submitted by the bidder in his tender offer, and the bidder shall, when so required by the Railway, make available all such information, evidence and documents as may be necessary for such verification. Any such verification or lack of such verification, by the Railway shall not relieve the bidder of its obligations or liabilities hereunder nor will it affect any rights of the Railway there under.
In case of any information submitted by tenderer is found to be false, forged or incorrect after the award of contract, the contract shall be terminated. Bid Security, Performance Guarantee and Security Deposit available with the railway shall be forfeited. In addition, other dues of the contractor, if any, under this contract shall be forfeited and agency shall be banned for doing business for a period of upto five years.
The following documents should be specified for submission along with tender:
List of Personnel, Organization available on hand and proposed to be engaged for the subject work.
List of plant Machinery available on hand own and proposed to be inducted own hired to be given separately for the subject work.
List of works on hand indicating description of work, contract value, and approximate value of balance work yet to be done and date of award.
Bid Security : (1) (a) The tenderer shall be required to submit the Bid Security with the tender for the due performance with the stipulation to keep the offer open till such date as specified in the tender, under the conditions of tender. The Bid Security shall be as under: (a) For works estimated to cost up to 1 crore - 2% of the estimated cost of the work (b)For works estimated to cost more than 1 crore - 2 lakh plus ½% (half percent) of the excess of the estimated cost of work beyond 1 crore subject to a maximum of 1 crore Note: (i) The Bid Security shall be rounded off to the nearest 100. This Bid Security shall be applicable for all modes of tendering. (ii) Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' shall be exempted from payment of Bid Security detailed a b o v e . (iii) Labour Cooperative Societies shall submit only 50% of above Bid Security detailed above. (b) It shall be understood that the tender documents have been issued to the tenderer and the tenderer is permitted to tender in consideration of stipulation on his part, that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the Engineer. Should the tenderer fail to observe or comply with the said stipulation, the aforesaid amount shall be liable to be forfeited to the Railway. (c) If his tender is accepted, this Bid Security mentioned in sub para (a) above will be retained as part security for the due and faithful fulfillment of the contract in terms of Clause 16 of the Standard General Conditions of Contract. The Bid Security of other Tenderers shall, save as herein before provided, be returned to them, but the Railway shall not be responsible for any loss or depreciation that may happen thereto while in their possession, nor be liable to pay interest thereon. (2) The Bid Security shall be deposited either in cash through e-payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure VIA of GCC- 2022 and shall be valid for a period of 90days beyond the bid validity period.
For those conditions for which standard formats have been given in the uploaded document titled-Formats for uploading of various format. The information should only be submitted in these standard formats.
Rates are inclusive of all taxes/octroi, license fee, royalty charges etc. legally leviable by State, Central Govt. and/or any other local authority.
In addition to General condition of contract 2022 and Indian Railways Unified standard specification Works Materials Volume I II 2010, revised upto date, special condition attached shall also apply.
Taxes as per GST (1st july2017), Royalty etc. will be recovered as per extant instruction on the subject.
Note for Commercial compliance :-
In case of items 3 and 11 of Commercial Compliance, supportive documents/certificates from the organizations with whom they worked/are working should be enclosed.
Certificates from private individuals for whom such works are executed being executed is not acceptable.
For Standard Financial criteria and Standard Technical criteria - Tenderers are required to submitted authenticated certificate along with the tenders from officers of government or semi- government/public sector undertakings under whom the work has been executed indicating there in the name of work executed, value of works/payment details and period during which completed. Such certificates should have signature and seal of the concerned officer. In the absence of such certificate the tender may not be considered.
BOOKS OF REFERENCE: These tender documents are to be read with the followings books with versions updated/corrected/modified up to the date of tender opening: 1) Standard General Conditions of Contract April 2022 as amended by updated correction slips termed GCC 2022. 2)E.C.Railway Engineering department unified standard schedule or rates 2021 as amended by updated correction slips (termed USSOR, 2021) up to the date of tender dropping.3) DSR 2021 version 2 4) Standard specifications contained in Indian Railways Hand Book Specifications (works and materials)2010. These four books are where-in-after called the "Books of reference" and shall govern this tender as well as the contract resulting from the acceptance from this tender, to the extent that these contents do not conflict with the contains of the various chapters pd these documents.
Tenderer are advised to visit the site of work to ascertain all respect of the site condition viz accessibility, availability of approach road, nature of the soil, availability of material availably of labor etc. that may be encountered in course of execution of work.
Tenderer should see the website for the corrigendum/addendum to the NIT/tender document, if any that may be uploaded prior to tender opening (inclusive) as there will not be any separate communication for that.
The contractor shall observe all the formalities perform all the acts and abide by all the provision contained in the contract labour act-1970 and contract labor central rule , 1971 which in addition to other stipulations provided that the contractors shall obtained license from appropriate licensing officer of the area before commencement of the work and shall produced a copy thereof along with the original to the railway office, which will be returned to the contractor after variation.
If any complaint is received against the contractor regarding violation of contract laws( exposing principal employee to the risk of legal proceedings under labour laws), the guilty contractor will be black listed and their contract shall be terminated following the due procedure apart from initiating criminal proceeding against him with the help of labour department officials.(Authority : RB letter No. 2008/(LI)E/AT/CNR/3, dated: 24.01.2018)
It is responsibility of the tenderer to see corrigendum, if any, to tender notice up to the date of tender opening. IRSGCC-2022( Works Matter) uploaded for reference only. Any correction issued by competent authority up to date of opening will be applicable. Tender should quote accordingly.
Though no minimum eligibility criteria is specified for tender value upto Rs. 50 Lakhs, tenderers are advised to upload documents so their financial capacity, capability & past performance to execute the tendered work can be adjudged during evaluation of their offer. Documents testifying tenderer previous experiences for the type of job for which tender is invited with list of works carried out in the past and financial status should be produced along with the tender.
It is to be noted that tenderer digital signature on the E-tender form will be considered as confirmation that tenderer have read and accepted all the condition laid down in the documents as well as related specification of items, schedule & quantity of items in the tender, considering of techno-commercial offer form (including special condition attached to E-tender) and financial offer form, unless specific deviation is quoted in the techno- commercial offer form.
The tenderer has to submit necessary document in compliance of clause 10 to 18 (Part-II) of IRSGCC 2022(Works Matter) mandatorily, otherwise offer will be considered as incomplete offer and accordingly shall not be considered.
In reference to Sl No.2 above, any changes in rate of taxes or any new tax of cess on works contract will be dealt according to Clause 37 of IRSGCC-2022 Works Matter.
JOINT VENTURE will not be permitted for this tender.
Any conditional offer will be summarily rejected.
TBR between Daniyawan-Biharsharif (SL) Total KM=37 TKM under SSE/P.Way/Hilsa
W7ETENDER9OPENDNR26-27-1~ECR
W7ETENDER9OPENDNR26-27-1
Open
Works - General
6 Months
Patna, Bihar
₹0
₹2.2 L
24 Aug 2026
24 Aug 2026
4 Sept 2026
26 items across 1 schedule · ₹1,08,25,676.4 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Depth of 300 mm below bottom of sleeper - Plain Track : | For TRM | 2500.00 | 517.22 | 12,93,050 |
| 2 | Depth of 300 mm below bottom of sleeper Turnouts | for TRM | 600.00 | 827.55 | 4,96,530 |
| 3 | Extra to item nos. from 081011 to 081018 from 081021 to 081028 for disposal of muck a distance beyond 50m for every additional lead of 50 metres or part thereof up to 500 metres 1 TRM in station yard / cutting. | and Each at for | 1000.00 | 4.94 | 4,940 |
| 4 | Lifting and packing for regrading the existing PSC sleeper track to required height / level stages not exceeding 75mm or part thereof at time, providing permissible ramp for the track, insertion of moorum / sand / stone ballast uniformly under the existing track and placing the same to safe approved gradient, gauge, cushion including levelling and one round through packing to allow train movement restricted speed of 30 kmph for a specified length with all leads & lifts and fixing, marking, painting rail level pegs at every 30m interval. Note: Lifting of track shall be done in stages per procedure prescribed in latest edition IRPWM to get the proposed final level as approved working profile, as directed Engineer in-charge. | TRM in a of at as of per by | 2000.00 | 159.09 | 3,18,180 |
| 5 | Under Traffic Block Conditions: | cum | 12000.00 | 46.52 | 5,58,240 |
| 6 | For 52 Kg - 90 UTS or 52 Kg 72UTS Rail, Single shot crucible fitted with Automatic Tapping Thimble Technology, 3 pieces Mould (Zircon washed) and Compressed Air Petrol heating technique. | Each | 100.00 | 1,613.06 | 1,61,306 |
| 7 | For PSC Sleeper Track with Sleeper Density 1660 | of TRM | 2500.00 | 122.61 | 3,06,525 |
| 8 | Without Rail tensor | TRM | 25000.00 | 49.22 | 12,30,500 |
| 9 | Carrying out preparatory works for operation Ballast Cleaning Machine (BCM) which includes making trench in track for inserting cutter bar, supporting track on wooden block supplied Railway, removal of ballast along with muck from shoulder which is out of reach of cutter chain and putting the same in cutting width between rails. Rate includes all miscellaneous works, e.g. opening and re-fixing of joggled plates, OHE Bonds, dismantling & removing obstructions etc. | of TRM by or fish | 34500.00 | 13.5 | 4,65,750 |
| 10 | Carrying out various works during operation BCM, like filling up of ballast at deficient location from locations where ballast is excess or from adjoining tracks, required initial packing, adjustment of PSC Sleepers, provision wooden blocks supplied by department and attending track parameters etc. complete so as to make track fit for 20 kmph speed. | of TRM | 34500.00 | 34.84 | 12,01,980 |
| 11 | Removal of screened muck discharged by BCM, where muck disposal on side slope is restricted due to platform, cutting, OHE mast etc. disposing it beyond 5m from edge of cutting to 3m deep or alternatively carting it up to 50m for disposing off beyond the end of cutting platform and making up cess wherever low. | TRM and up / | 2000.00 | 26.46 | 52,920 |
| 12 | Extra to item nos. from 154030 and 154040 disposal of muck at a distance beyond 50m every additional lead of 50 metres or part thereof up to 500 metres. | for TRM for | 2000.00 | 2.47 | 4,940 |
| 13 | Removing the ballast from shoulders, left over after BCM working, screening the same removing the muck and putting back screened ballast into track, boxing the ballast profile and using released muck for cess making or throwing away within 50m lead and 3m when not required for cess repairs and directed by the Engineer-in-charge. Note: This item shall be used only when BRM is available. | TRM the to lift as not | 34500.00 | 18.34 | 6,32,730 |
| 14 | Ballast equalisation & ballast profiling after completion of deep screening work by BCM and/or after unloading of ballast by DMT (Ballast Train), as directed by Site Engineer as per IRPWM including heaping of ballast in tamping zone keeping rails & sleeper top free from ballast, spacing and squaring of sleeper, gauging, cleaning of muck, proper fixing fastening, attention during each round of sleeper tamping in relation to pre & post working Note: Payment shall be made only once in irrespective of numbers of TTRM packing round and after restoration of normal speed and restoration complete ballast profile and cess profile. | TRM of of | 34500.00 | 32.84 | 11,32,980 |
| 15 | Making cess in deep screened track by using screened muck discharged by BCM where cess is low or cutting cess to required depth up to from centre of track, where cess is high disposing off extra muck beyond 5m from edge of cutting which are up to 3m deep alternatively carting it up to 50m for disposing off beyond cutting or platforms, so as to make cess as per standard profile including providing proper slope. | TRM 4m and or it | 34500.00 | 29.28 | 10,10,160 |
| 16 | Pre, during, and post BCM works for deep screening of ballast in Points and crossings with all contractor's labour, tools and plants required to carry out the work to the standards specific time including crossing of tracks complete and as directed by the Engineer - in charge. I. Pre-BCM Operation : a) making trenches for insertion of cutter bars at various locations as per the directions of engineer charge. i.e.., one trench ahead of one rail length from SRJ and second trench near sleeper No 62 1in 12) etc., b) Filling up ballast up to sleeper level. c) Tightening of fittings/ plate screws, ERCs, Stud bolts, check rail bolts. II. During BCM Operation : a) Assistance to S&T Department Opening of cables at approach of Points Crossings, TLD Boxes/ removing of Point motor and refixing the same and covering cables after passing of BCM in block period with S&T Staff. Engineering : c) Removing of two long sleepers i.e.., sleeper No 3 & 4 and refixing the same position during block after passage of BCM. Removing obstruction i.e.., S&T CC block duly digging with crow bars and breaking with chisel/ hammer, cutting of rail pegs with gas. e) remove, excess ballast on rail table for movement of BCM and for packing purpose. Extension of cutter bar wherever required assisting machine staff. g) Removing of cutter bar/ Chain links from the trenches after screening work by BCM. III . Post BCM Operation : a) Packing switch portion including Motor long sleeper i.e.., SRJ to heel joint to reset Point train movement & initial packing of lead portion to allow train at 20KMPH and lifting the track two stages (50mm to 75mm in each wherever required for correcting the longitudinal surfacing b) Dumping of ballast in the deficient portion in crib, on main line turnout side initial packing purpose. c) Boxing / Levelling muck duly ensuring levelling of muck on cess side and lowering of cess to the deep screened depth and removing of muck in between lines and leading up to 250mts. Note: 1. technical reasons, some of the points crossings cannot be deep screened either fully or partially by BCM, in which case, the left over length will be deep screening manually. 2. The length of points and crossings assembly payment of this item should be taken from SRJ longest concrete sleeper available just beyond heel of crossing along main line. | TRM as in etc. - in ( : & b) in d) To free f) in for in lift) for of the For and for to | 600.00 | 370.76 | 2,22,456 |
| 17 | Level crossing with CC block surface | Sqm | 250.00 | 289.17 | 72,292.5 |
| 18 | BCM/FRM/UNIMAT (7.5 KVA generator and 12x500 W) | Night | 90.00 | 7,032.51 | 6,32,925.9 |
| 19 | CSM / DUO / 3X with or without DGS (7.5 KVA generator and 8x500 W) | Night | 100.00 | 6,220.22 | 6,22,022 |
| 20 | 52 Kg - 90 UTS - Outside Track | Each | 30.00 | 284.63 | 8,538.9 |
| 21 | 52 Kg - 90 UTS- On Running Line | Each | 500.00 | 316.57 | 1,58,285 |
| 22 | Outside Track | Each | 30.00 | 52.01 | 1,560.3 |
| 23 | On Running Line | Each | 500.00 | 66.12 | 33,060 |
| 24 | Level crossings with concrete blocks road surface | Sqm | 250.00 | 457.17 | 1,14,292.5 |
| 25 | Fabrication including cutting, bending/machining and fixing of check rails of all rail sections over PSC Sleepers as per Railway's approved drawings & specifications for level crossings trolley paths/inspection lines in yards duly cutting rail flanges, wherever required to correct alignment and level, drilling of holes with machine in check rails and fixing to Running and sleepers with all Railway's fittings, e.g. screws / grip expansion bolts, brackets, packing pieces, bolts, washers etc including grinding brackets if required, fixing of Railway's wooden blocks at flare ends duly cutting and plaining, crossing of tracks and as directed by engineer in-charge Note: 1. Drilling of holes PSC Sleeper and fixing of dowels shall be paid under relevant item. 2. Required P.Way materials will be supplied at SSE/P.Way stores. | TRM / rail rail of the in | 45.00 | 1,024.14 | 46,086.3 |
| 26 | JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity | Hour | 50.00 | 868.52 | 43,426 |
| Schedule total | ₹1,08,25,676.4 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
CorrigenduminGCCforGST.pdf
ATTACHMENT
CorrigenduminGCCforGST1.pdf
ATTACHMENT
GuidelineforSteelReinforcement.pdf
ATTACHMENT
2018_CE-I_CT_9Date04_06_2018_1.pdf
ATTACHMENT
2018_CE-I_CT_9Date04_06_2018.pdf
ATTACHMENT
AnnexureVIB.pdf
ATTACHMENT
BidSecurityAnnexureVIA.pdf
ATTACHMENT
IRSGCC April 2022
ATTACHMENT
AdvanceCorrectionSlipNo_5ACS-5.pdf
ATTACHMENT
CTIndianRailwaysStandardGeneralConditionsofContractApril- ACS 3
ATTACHMENT
ACS1ofGCC2022.pdf
ATTACHMENT
2022_CE-I_CT_GCC-2022Policy14.07.2022.pdf
ATTACHMENT
BidCapacityAnnexureVI_1.pdf
ATTACHMENT
CorrectionSlipNo_6ACS-6GCC-2022.pdf
ATTACHMENT
acs4.pdf
ATTACHMENT
specialconditionoftrack.pdf
ATTACHMENT
ACS-11.pdf
ATTACHMENT
ACS10.pdf
ATTACHMENT
AnnexureV_1.pdf
ATTACHMENT
LetterregardingAnxV.pdf
ATTACHMENT
ACS9.pdf
ATTACHMENT
ACS8.pdf
ATTACHMENT
2022-CE-I-CT-GCC-2022-POLICY-Pt.Idated25.09.2024.pdf
ATTACHMENT
ACS 2
ATTACHMENT
GCC_April-2022_2022_CE-I_CT_GCC-2022_POLICY_27.04.22.pdf
ATTACHMENT
2023_04_26RBCE_CE-I-CTIndianRailwaysStandardGeneralConditionsofContractApril-2022AdvanceCorrectionSlipNo_3ACS-311.pdf
ATTACHMENT
GeneralConditionGeneralObligationBaseduponGCC-2022Rev..pdf
ATTACHMENT
ACS-2toGCC-2022_2022-CE-1-CT-GCC-2022-POLICY_13.12.2022_1.pdf
ATTACHMENT
Tendernoticeno09-01TBRbetweenDHWN-BEHSSLunderSSE-P.Way-Hilsa_compressed.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .