Engineer-in-Chief (Civil), Roads-I, Odisha
O/o the E.I.C (Civil), Odisha, Nirman Soudha, New Building, Unit-V, Bhubaneswar.
Widening and strengthening of Badachana Darpani road from 0/0 to 12/719Km (except from 5/100 to 7/977km) approach road to Chandikhol Temple from 0/0 to 0/762Km and approach road to Mahavinayak Temple from 0/0 to 0/849Km
2026_EICCL_130103_1
CE-Roads-I-03/2026-27
Open Tender
Civil Works - Roads
420 days
Charbatia Division
4 documents required · 4 mandatory
₹10,000
₹46.9 L
Yes
29 May 2026
29 May 2026
17 Jun 2026
29 May 2026
16 Jun 2026
29 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Unit - Sqm
Clearing and grubbing road land including uprooting trees rank vegetation, grass, bushes, shrubs, saplings and trees girth upto 300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable materials to be used or auctioned upto a lead of 1000metres including removal and disposal of top organic soil not exceeding 150mm in thickness as per Clause 201 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost of all labour, T&P etc complete and as per direction of Engineer-in-Charge. | 86,338 | sqm | 8.63 | ₹7,45,096.94 | NI-572-13926-1 |
| 2 | Unit - Cum
Dismantling of Cement Concrete Grade M-15 & M-20 including T&P and scaffolding wherever necessary, sorting the dismantling materials, disposal of unserviceable materials and stacking the serviceable materials with all lifts and lead upto 1000 mtr. as per Clause No.202 of MoRT&H specifications for Road and Bridge works (5th Revision) & including cost of all materials, labour, T&P, royalty etc complete in all respect and as per direction of the Engineer-in-charge. | 500.54 | cum | 662.19 | ₹3,31,452.58 | NI-572-13926-2 |
| 3 | Unit - Rmt.
Removing all types of hume pipe upto 600mm dia including earthwork and dismantling of masonry works including T&P and scaffolding whenever necessary, sorting the dismantling materials, disposal of unserviceable materials and stacking the serviceable materials with all lifts and lead upto 1000 mtr. as per Clause No.202 of specifications for Road and Bridge works of Ministry of Road Transport & Highways (5th Revision) & including cost of all materials, labour, T&P, royalty etc complete in all respect and as per direction of the Engineer-in-charge. | 120 | rm | 297.81 | ₹35,737.2 | NI-572-13926-3 |
| 4 | Unit - Rmt.
Removing all types of hume pipe upto 600mm to 900mm dia including earthwork and dismantling of masonry works including T&P and scaffolding whenever necessary, sorting the dismantling materials, disposal of unserviceable materials and stacking the serviceable materials with all lifts and lead upto 1000 mtr. as per Clause No.202 of specifications for Road and Bridge works of Ministry of Road Transport & Highways (5th Revision) & including cost of all materials, labour, T&P, royalty etc complete in all respect and as per direction of the Engineer-in-charge. | 82.5 | rm | 400.75 | ₹33,061.88 | NI-572-13926-4 |
| 5 | Unit - Cum
Earth work in excavation in all kinds of soil for road works with hydraulic excavator of 0.9 Cum bucket capacity including cutting and loading in tippers as per drawing and technical specification, including setting out, dressing of section to correct line, level, grade & camber for road work or dressing of sides and bottom for foundation of structures and loading into tippers, transporting to embankment site within all lifts and lead upto 1000mtr. and utilising the surplus earth locally for road work wherever required, backfilling the excavation earth to the extent required etc complete in all respect as per clause 301 & 304 of Specification for road & bridge work of MORT&H (5th Revision) & Direction of Engineer in charge. | 38,139.33 | cum | 74.85 | ₹28,54,728.85 | NI-572-13926-5 |
| 6 | Unit - Sqm
Scarifying and removing the existing bituminous road surface to the required depth as per approved drawing and technical specifications and disposal of scarified materials within all lifts and lead upto 1000mtr. complete in all respect as per Section 900, Clause 305.4.3, 305.8, 305.9.5, 501.8.3.2, 501.8.7.2 and 501.8.8.1 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost of all labour, T&P etc complete and as per direction of Engineer-in-Charge. | 44,273.5 | sqm | 6.06 | ₹2,68,297.41 | NI-572-13926-6 |
| 7 | Unit - Sqm
Reworking the scarified bituminous surface suitably after supplementing the base materials with sand and compacting finished surface as per approved drawing and technical specifications as per Section 900, Clause 501.8.3.2 and 501.8.8.1 of MoRT&H Specifications for Road & Bridge works (5th Revision) and as per direction of Engineer-in-Charge. | 44,273.5 | sqm | 15.37 | ₹6,80,483.7 | NI-572-13926-7 |
| 8 | Unit - Cum
Loosening to a depth of 150mm, leveling and compacting original ground supporting embankment /sub-grade as per approved drawing and technical specifications complete in all respect as per Section 900 and Clause 305, 305.3.4 of MoRT&H Specification for Road & Bridge works (5th Revision) & including cost of all labour, T&P etc complete and as per direction of Engineer-in-Charge. | 10,273.43 | cum | 36.08 | ₹3,70,665.35 | NI-572-13926-8 |
| 9 | Unit - Cum
Construction of embankment with approved materials deposited at site from road-way cutting and other structures with all lifts and leads graded and compacted to meet requirement as per approved drawing and technical specifications complete in all respect as per Section 900 and Clause 305 of MoRT&H Specification for Road & Bridge works (5th Revision) & including cost of all labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 27,108.99 | cum | 35.86 | ₹9,72,128.38 | NI-572-13926-9 |
| 10 | Unit - Cum
Construction of embankment with approved materials obtained from borrow pits by mechanical means graded and compacted to meet requirement as per approved drawing and technical specifications complete in all respect as per Section 900 and clause 305 of MoRT&H Specification for Road & Bridge works (5th Revision) & including cost & conveyance of all materials, labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 46,136.75 | cum | 274.61 | ₹1,26,69,612.92 | NI-572-13926-10 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_3.pdf
PDF • 0.11 MB
Tendernotice_2.pdf
PDF • 11.76 MB
Tendernotice_1.pdf
PDF • 0.24 MB
BOQ_593209.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid