| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.6 LAccepted-AOC | ₹5.6 L | L1 | Accepted-AOC L1 Accept |
| 2 | L2₹5.7 LRejected-Finance PUDUKKOTTAI | PUDUKKOTTAI | TAMIL NADU | ₹5.7 L | L2 | Rejected-Finance Reject |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Others-Withdraw the Contractor |
| Sl No | Description | Qty | Unit | MEENAL L2 | S. MARIMUTHU L1 |
|---|---|---|---|---|---|
| 1.00Providing Cement Concrete Pavement (60Metre) with Pipe Culvert at Samathuvapuram BG Road in Thulaiyanur Panchayat | |||||
| 2.00 | Earth work excavation in all clauses of soil such as hard stiff clay, hard gravelly soil as per SS 20 B for narrow foundation. | 10.8 | cum | 135 ₹1,458 | 131 ₹1,414.80 |
| 3.00 | Filling with M.Sand including cost and conveyance of sand to work site including all labour charges for filling etc complete. | 11.25 | cum | 1,790 ₹20,137.50 | 1,787 ₹20,103.75 |
| 4.00 | Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges etc ., | 18.6 | cum | 5,750 ₹1.1 L | 5,533 ₹1.0 L |
| 5.00 | Supplying & Erecting centering for sides & soffiots to Concrete works including cost and conveyance of all materials to worksite and all labour charges etc., complete | 69.13 | Sqm | 600 ₹41,478 | 547.5 ₹37,848.68 |
| 6.00 | Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete | 7.5 | cum | 6,850 ₹51,375 | 6,837.5 ₹51,281.25 |
| 7.00 | Cement Concrete 1:1.5:3 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete | 13.5 | cum | 7,400 ₹99,900 | 7,386 ₹99,711 |
| 8.00 | Supply and fixing of Bituminous Tar Pad 12mm thick every 5m for expansion joint etc., Complete. | 2.48 | Sqm | 235 ₹582.80 | 230 ₹570.40 |
| 9.00RCC Pipe Culvert | |||||
| 10.00 | Earth work excavation in all clauses of soil such as hard stiff clay, hard gravelly soil as per SS 20 B for narrow foundation. | 17.68 | Sqm | 275 ₹4,862 | 263 ₹4,649.84 |
Tender Value
₹5.7 L
EMD Value
₹5,700
Closing Date
12 Mar 2026, 3:00 pmClosed
Bdo,Thirumayam
Pt.union Office,Thirumayam
Providing Cement Concrete Pavement (60Metre) with Pipe Culvert at Samathuvapuram BG Road in Thulaiyanur Panchayat
2026_RDTN_670707_1
Tym/QuarryFund/Work---10
Open Tender
Civil Works
Thirumayam
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹5,700
29 Apr 2026
5 Mar 2026
12 Mar 2026
5 Mar 2026
12 Mar 2026
5 Mar 2026
Providing Cement Concrete Pavement (60Metre) with Pipe Culvert at Samathuvapuram BG Road in Thulaiyanur Panchayat
Earth work excavation in all clauses of soil such as hard stiff clay, hard gravelly soil as per SS 20 B for narrow foundation.
Filling with M.Sand including cost and conveyance of sand to work site including all labour charges for filling etc complete.
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges etc .,
Supplying & Erecting centering for sides & soffiots to Concrete works including cost and conveyance of all materials to worksite and all labour charges etc., complete
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
Cement Concrete 1:1.5:3 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
Supply and fixing of Bituminous Tar Pad 12mm thick every 5m for expansion joint etc., Complete.
RCC Pipe Culvert
Earth work excavation in all clauses of soil such as hard stiff clay, hard gravelly soil as per SS 20 B for narrow foundation.
Filling with M.Sand including cost and conveyance of sand to work site including all labour charges for filling etc complete.
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges etc .,
Cement Concrete 1:3:6 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Supplying & Erecting centering for sides & soffiots to Concrete works including cost and conveyance of all materials to worksite and all labour charges etc., complete
Cost & Supply of RCC Pipe 900mm dia (NP3)
Supplying and filling Gravel including cost and conveyance of gravel at site and all labour charges for filling ect., complete.
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 1 & 16 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.70 MB
Tym_doc--10.pdf
Tender Documents • 0.18 MB
BOQ_806021.xls
BOQ • 0.45 MB
Download all tender documents and submit your bid