Tender Value
₹1.0 Cr
EMD Value
₹2 L
Closing Date
17 Sept 2026, 4:30 pm6d left
Minor Irrigation Department
technical assistant
Construction of check dam to Tippasandra tank draft canal at Survey number 1 of Bhaginagere kaval village, Tippasandra panchayati, Tippasandra hobli, Magadi taluk, Ramanagara District-CALL2
MI/2025-26/DA/WORK_INDENT9394/CALL-2
MI/2025-26/DA/WORK_INDENT9394/CALL-2
Open
Dam and Allied works
Two Tender Document System(Two Cover)
Minor Irrigation Division Bengaluru
7 documents required · 7 mandatory
3.2(b) To qualify for award of this contract, each tenderer in his name should have in the last five years Period (2021-22 to 2025-26) b) Satisfactory completion as a prime contractor for at least one similar work such as Construction of check dam/Pick up/Barrage/Barrage cum Bridge/Anecut/Check dam cum cause way/Bandaras/Aqueduct works of value not less than Rs.50.63 Lakhs
3.2 To qualify for award of this contract, each Tenderer in his name should have in the last five years period. (c) Executed in any one year the following minimum quantities of work: (Usually 80% of Annual Requirement for work costing up to Rs. Lakhs)1-Earthwork in excavation ,Embankment and de-silting combined qtys.-3571.0 CUM,2-cement concrete both RCC and PCC-884.0 cum, 3-Reinforcement of Steel-9.08 t, 4-Revetment/pitching-492.0 SQM
3.2 c Executed in any one year following minimum quantities of work 1Earthwork both in excavation, Desilting & Embankment combined qty3571.00CUM2Cement concrete both RCC and PCC884.00CUM3Reinforcement of Steel9.08T 4Revetment/pitching492.00SQM
Annual Turnover Certificate along with Balance sheet certified/attested by Chartered Accountants should be uploaded with 18-Digits system generated unique number UDIN Number
Bidder should quote the rates excluding GST
List of existing commitments and ongoing works
List of works for which tenders already submitted
Contractor Registration/Company Registration Certificate/PWD registration certificate
Contractor should produce the gst Registration Certificate along with latest updated gst Clearance Certificates
List of Financial Resources with Certificates
3.2 (a)To qualify for award of this contract, each tenderer in his name should have in the last five years Period (2021-22 to 2025-26) a) Achieved in at least two financial years a minimum financial turnover (In all classes of Civil Engineering Construction works) of Rs.202.52 lakhs
3.3(b) liquid assets and /or availability of credit facilities of not less than Rs. 41.57 Lakhs (Credit lines/letter of credit/certificates from banks for meeting the fund requirement etc.) in the format to be as prescribed in bid document
Details of Existing commitments and on-going works as per bid document and Details Works for which Tenders already submitted as per section 3 of Standard bid document K/W-4
QUANTITY WISE WORK DONE CERTIFICATE
Contractor should produce the updated IT clearance Certificate
₹2,540
₹2 L
4 Sept 2026
31 Aug 2026
19 Sept 2026
17 Sept 2026
10 Sept 2026
TENTATIVE PHYSICAL/FINANCIAL ACTIVITY CHART
Construction of check dam to Tippasandra tank draft canal at Survey number 1 of Bhaginagere kaval village, Tippasandra panchayati, Tippasandra hobli, Magadi taluk, Ramanagara District
MI/2025-26/DA/WORK_INDENT9394
SL NO ITEM NAME UNIT QUANTITY RATE (INR) TOTAL (INR) 1st MONTH 2nd MONTH 3rd MONTH 4th MONTH 5th MONTH 6th MONTH 7th MONTH 8th MONTH 9th MONTH
PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL PHYSICAL FINANCIAL
1 Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer - In area of light jungle as per the directions of the engineer incharge of work. 100 sqm 172.5 408.72 70504.20 172.50 70504.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70504.20
2 Cutting and removing jauliflora bushes upto 1.50 m girth excluding removal of stumps and including burning or disposing off the materials as directed with all other ancillary operations complete.as per the directions of the engineer incharge of work. Each 350 26.52 9282.00 350.00 9282.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9282.00
3 Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m. as per the directions of the engineer incharge of work. cum 868.685 106.08 92150.10 868.69 92150.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 92150.10
4 Providing rubble stone/boulder filling between or behind abutment below apron including cost of all materials, labour, hand packing, finishing top surface & all necessary works as directed and complete as per specification.as per the directions of the engineer incharge of work. cum 114.75 1329.12 152516.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.38 76258.26 57.38 76258.26 152516.52
5 Providing and laying in-situ vibrated M-15 grade cement concrete using 40 mm down approved, clean, hard, graded aggregates for plain concrete works including cost of all materials, machinery, labour, cleaning, providing mortar layer for lift joints, batching, mixing, placing in position, levelling, vibrating, finishing, curing with all other ancillary operations complete as per the directions of the engineer incharge of work. cum 85.705 6231.16 534041.57 28.57 178013.86 28.57 178013.86 28.57 178013.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 534041.57
6 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, including cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing, centering, formwork and scafolding and all other appurtenances required to complete the work as per technical specifications for check dam /pickups /irrigation tanks/waste weir/ sluice, sluice canal and other allied works like abutments/wing walls/returns/cutoff walls works & all necessary works as directed and complete as per specification.as per the directions of the engineer incharge of work. cum 1019.26 7116.72 7253788.03 0.00 0.00 0.00 0.00 169.88 1208964.67 169.88 1208964.67 169.88 1208964.67 169.88 1208964.67 169.88 1208964.67 169.88 1208964.67 0.00 0.00 7253788.03
7 Steel Fabrication - Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification - Dam & Allied Works. as per the directions of the engineer incharge of work. Tonne 11.3543 82898.40 941253.30 3.78 313751.10 3.78 313751.10 3.78 313751.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 941253.30
8 Providing impervious filling adjacent to masonry / concrete structure and filling trial pits with soil available in adjacent area in layers of 100 to 150 mm and compacting each layer to density control of not less than 95 percent using pneumatic tampers or by vibratory earth rammers including cost of all materials, machinery, labour, picking previous layer, spreading soil in layer, breaking clods, watering & all necessary works as directed and complete as per specification. as per the directions of the engineer incharge of work. cum 406.56 267.28 108665.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 203.28 54332.68 203.28 54332.68 108665.36
9 De-silting of Feeder Channel/Canal in dry condition by excavating the deposited bed material and loading the same to transport vehicle ( excluding cost of transportation ) including cost of all machinery, labour & all necessary works as directed and complete as per specification. as per the directions of the engineer incharge of work. cum 2812 56.16 157921.92 1406.00 78960.96 1406.00 78960.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 157921.92
10 Providing casing embankment using approved semi-pervious soil from soil borrow areas in layers of 250 to 300 mm (before compaction) including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, levelling, sectioning edges / sides, watering, compacting to density control of not less than 95 percent using power roller etc., complete with all lead and all lifts. as per the directions of the engineer incharge of work. cum 783 472.16 369701.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 391.50 184850.64 391.50 184850.64 369701.28
11 Providing and constructing dry rubble stone pitching with pin headers at 2 per m2 using stones and stone chips from approved source including cost of all materials, labour, hand packing / wedging stone chips, finishing and all other ancillary operations complete. 300mm thick as per the directions of the engineer incharge of work. sqm 135 455.00 61425.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 67.50 30712.50 67.50 30712.50 61425.00
12 Providing and constructing 450 mm thick hand packed rough stone revetment consisting of 300 mm thick rough stones with 400 to 450 mm long through stones at 1.5 m c / c over a backing of 150 mm thick 40 mm down graded coarse aggregate layer including cost of all materials, machinery, labour, laying to specified slope, wedging with chips, finishing etc., complete with all lead and lifts. as per the directions of the engineer incharge of work. sqm 480 764.40 366912.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 240.00 183456.00 240.00 183456.00 366912.00
13 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications as per the directions of the engineer incharge of work. m 55.8 143.52 8008.42 0.00 0.00 0.00 0.00 27.90 4004.21 27.90 4004.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8008.42
1st Milestone 2nd Milestone 3nd Milestone
LOC 4556776.363 Milestones and liquidity damages
3037850.909 MILESTONES AMOUNT Liquidity damage
Mile Stone 1 3018121.97 3,018.00 Per day 3018.12 Rs 30.18 Lakhs
Mile Stone 2 3630898.22 3,631.00 Per day 6649.02 Rs 36.31 Lakhs
Mile Stone 3 3477149.50 3,477.00 Per day 10126.17 Rs 34.77 Lakhs
EMD 10126169.70 Per day Rs 101.26 Lakhs
151892.55 Earth work 4463.69 Cum 3570.95
200000 Concrete 1104.96 Cum 883.97
Steel 11.35 T 9.08
Revetment/pitching 615.00 SQM 492.00
Annual turn over Rs 202.52 Lakhs
Line of credit Rs 41.57 Lakhs
Similar nature of work Rs 50.63 Lakhs
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
gov orders.zip
Others - OTHERS • 11.89 MB
Bhaginagere Check Dam phy-fin chart.xlsx
Others - PHY AND FIN CHART • 0.09 MB
9394 BHAGINAGERE DWG.pdf
Others - dwg • 1.53 MB
KW-4 Bid Document TIPPASANDRA INDENT 9394 CALL-2.doc
Tender Document • 1.62 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .