| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹18.4 LAdmitted-Fee/PreQual/Technical/Finance AT MAIN ROAD AMBAPUA GAYATRI NAGAR PO BERHAMPUR PS GOPALPUR | BERHAMPUR | GANJAM | ODISHA | +0.00% | ₹18.4 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L1₹18.4 LAdmitted-Fee/PreQual/Technical/Finance | +0.00% | ₹18.4 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L1₹18.4 LAdmitted-Fee/PreQual/Technical/Finance | +0.00% | ₹18.4 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 4 | L1₹18.4 LAdmitted-Fee/PreQual/Technical/Finance | +0.00% | ₹18.4 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 5 | L1₹18.4 LAdmitted-Fee/PreQual/Technical/Finance | +0.00% | ₹18.4 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹18.4 L
EMD Value
₹18,500
Closing Date
29 Jul 2026, 6:00 pmClosed
Superintending Engineer Ganjam R and B div I
O/OSuperintending Engineer Ganjam R and B div I
Repair and Restroation of differentNon-Residential Buildings at Berhampur
2026_EICCL_137041_1
SE R and B Divn I BAM No 13/ 2026 27
Open Tender
Civil Works - Buildings
Percentage
30 days
Ganjam
2 documents required · 2 mandatory
₹6,000
₹18,500
Yes
1 Aug 2026
24 Jul 2026
30 Jul 2026
24 Jul 2026
29 Jul 2026
24 Jul 2026
24 Jul 2026 - 29 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Civil Work :Earth work in excavation of foundation in hard soil or gravelly soil within 50m initial lead and 1.50m initial lift including rough dressing breaking clods to maximum 5cm to 7cm & laying in layers not exceeding .0.3m depth and as per direction of the Engineer-in-Charge | 19.31 | cum | 282.89 | ₹5,462.61 |
| 2 | Supplying and filling in foundation and plinth with sand including laying the earth in layers not exceeding 23.5 cm thick ramming & watering with all leads & lifts including cost of all labour,T&P completed as directed by the Engineer-in-charge. | 1.08 | cum | 822.46 | ₹888.26 |
| 3 | Cement concrete of proportion (1:3:6) in foundation and floors using 4cm size clean hard black crusher broken granite stone metal of approved quality and from approved quarry including hoisting, lowering and laying concrete in layers not exceeding 15 cm. (6") thick to the required level ramming, watering, curing etc. complete including cost, conveyance, royalties of all materials with all labour and T&P required for the work etc. complete in all respect and as per the direction of the Engineer-in-charge. | 1.08 | cum | 6,036.12 | ₹6,519.01 |
| 4 | Fly Ash Brick masonary with Flyash Bricks of 23cm.x 11cm.x 8cm. size having crushing strength not less than 75 Kg/Cm2 in cement mortar (1:6) in F& P including splays, cuttings, circular moldings, watering & curing for 7 days, cost, conveyance, taxes & royalties of all materials, labour with T&P etc. complete in all respect. | 6.86 | cum | 5,700.23 | ₹39,103.58 |
| 5 | Fly Ash Brick masonary with Flyash Bricks of 23cm.x 11cm.x 8cm. size having crushing strength not less than 75 Kg/Cm2 in cement mortar (1:6) in superstructure including splays, cuttings, circular moldings, watering & curing for 7 days, cost, conveyance, taxes & royalties of all materials, labour with T&P etc. complete in all respect.G.F | 7.64 | cum | 5,733.56 | ₹43,804.4 |
| 6 | R.C.C. work of proportion M-20 grade having minimum compressive strength in work test of 200 Kg/Cm2 at 28 days using 20 mm and down graded size black hard crusher broken granite stone chips of approved quality and from approved quarry including hoisting lowering and laying concrete and compacting by using vibrators watering, curing for 28 days, centring & shuttering and finishing the exposed surface smooth providing grooves or beads where necessary in all floors including cost, conveyance, royalties and taxes of all materials , cost of all labour with cost of all T&P required for the work etc. complete in all respect but excluding cost and conveyance of M.S. rods or steel & binding wires and labour charges for strengthening, cutting, bending grills and placing in proper position etc complete as per direction of Engineer-in-Charge. Column base Footing | 2.52 | cum | 6,492 | ₹16,359.84 |
| 7 | Column Ground Floor | 1.44 | cum | 15,874.9 | ₹22,859.86 |
| 8 | Plinth Bend & COPING | 1.49 | cum | 7,366.41 | ₹10,975.95 |
| 9 | Cutting, straightening coiled or bent up M.S. Rod or tor steel of SAIL/ TATA / RINL (VIZAG) make including bending, binding, welding and joining if necessary and tying the grills and placing in position as required for R.C.C. Work and for providing fan hooks as required, hoisting, lowering, laying including cost, conveyances, taxes of M.S. Rod or tor steel and binding wires of 18 to 20 gauge and labour required for the work for bending, binding and tying the grills in all floors (Linear measurement will be taken and quantity will be calculated basing on the standard weight of B.I.S. for M.S. Rods or tor steel only. Wastage if any, including weight of binding wire will not be considered for measurement) etc. complete as per specification & direction of Engineer-in-charge. Ground Floor | 11.06 | qtl | 9,278.44 | ₹1,02,619.55 |
| 10 | Providing 12 mm thick cement plaster with cement mortar of mix (1:6) with screened and washed sharp sand for mortar and finished smooth to the rough surface of walls in all heights after racking out joints including watering and curing, rounding of corners, providing grooves where ever necessary with cost, conveyance, royalties of all materials with cost of all labour,labour cess, T&P, and scaffolding required for the work etc. complete in all respect as directed by the Engineer in charge. | 28.8 | sqm | 195.3 | ₹5,624.64 |
stage.html
html • 0.06 MB
finance_603252.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 1.75 MB
Tendernotice_1.pdf
PDF • 0.61 MB
BOQ_603252.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .