| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.3 LAccepted-AOC NO 23 MARIAMMAN KOVIL STREET MANAPET BAHOUR COMMUNE PUDUCHERRY | PONDICHERRY | PUDUCHERRY | 605001 | L1 | Accepted-AOC 1st lowest | |
| 2 | L2₹8.5 L+₹24,390 (2.95%)Rejected-Finance | L2 | Rejected-Finance 2nd lowest |
Tender Value
₹8.9 L
EMD Value
₹17,892
Closing Date
25 Aug 2022, 4:30 pmClosed
Executive Engineer
Office of the Executive Engineer, BRS, PWD, Puducherry
Construction of L drain from Mariamman Koil to Beach at Pudukuppam in Ariyankuppam Commune, Puducherry
2022_PWDC1_10845_1
No.21/PW/EE/BRS/2022-23
Open Tender
Civil Works - Others
Item Rate
90 days
Ariyankuppam
Please refer Tender documents.
3 documents required · 3 mandatory
₹525
₹17,892
17 Oct 2022
19 Aug 2022
26 Aug 2022
19 Aug 2022
25 Aug 2022
19 Aug 2022
Amount
Earthwork in excavation of foundation of structure as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work - by mechanical means - depth upto 3m (Ordinary soil)
Supplying and filling with quary rubbish including spreading watering and consolidation etc., complete.
Cement concrete 1:4:8 mix with stone aggregate 40mm nominal size in foundation upto a depth of 1.5 metres below ground level and upto height of 1.5 above ground/bed level.
Plain cement concrete m-15 mix with stone aggregates 20mm nominal size mechanically mixed and vibrated in foundation upto a depth of 1.50 metres below ground level and/or 1.50 metres above ground/bed level.
Cement concrete 1:3:6 mix with stone aggregates 20mm nominal size mechanically mixed and vibrated in foundation upto a depth of 1.5 metres below ground level and 1.5 metres ground/bed level.
Centring and shuttering including strutting , propping etc. and removal of form work for - foundations, footings, bases for columns
12mm cement plaster finished with a floating coat of neat cement of mix - 1:4 (1 cement :4 fine sand)
Steel work welded in built up sections / framed work , including cutting,hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required - in gratings, frames, guard bar, ladder, railings, brackets,gates and similar works
Desilting the canal by removing silt, slush and debries from the bed of the drain removing the grass , buses etc., complete in unhygenic and foul condition including disposal of the same within an average lead of 1KM without polluting the environment by manual means
Painting with synthetic enamel paint of approved brand and manufacutre to give an even shade - Two or more coats on new work
V Azakesan
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .