| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.7 LAccepted-AOC | ₹1.7 L | 1 | Accepted-AOC Accept |
| 2 | 2₹1.7 LRejected-Finance | ₹1.7 L | 2 | Rejected-Finance Reject |
| Sl No | Description | Qty | Unit | SUBRAMANIAN CONTRACTOR L1 | Shahul hameed L2 |
|---|---|---|---|---|---|
| 1.00 | Supply and delivery and fixing of 1000 Litre HDPE tank as per IS 12701 / 1996 including loading, unloading, transportation and labour charges for fixing of the GI pipes and specials for pipe connection works including cutting, threading and fixing charges etc.,Twad 2024-25 | 1 | Nos | 8,435 ₹8,435 | 8,500 ₹8,500 |
| 2.00 | Dismantling the Plain Cement Concrete, clearing away and carefully stacking materials useful for re-use etc., complete complying with standard specification. | 3 | M3 | 378 ₹1,134 | 400 ₹1,200 |
| 3.00 | Labour For Cutting open Road for laying water mains or sewer as directed by Departmental officers.Twad 24-25 page No 195 | 3 | M3 | 995 ₹2,985 | 995 ₹2,985 |
| 4.00 | Earth work excavation for foundation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 10 mts and initial lift of 2 mts. and clearing and levelling the site, etc., complete complying with standard specification.(Data 25-26) | 43 | M3 | 110 ₹4,730 | 120 ₹5,160 |
| 5.00 | Plain Cement Concrete 1:4:8 (one cement four Parts of crushed stone M-sand and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification (The crushed stone sand to be used on cocrete work shell conform to gradation as per IS :383-1970 ) | 1 | M3 | 5,503 ₹5,503 | 5,503 ₹5,503 |
| 6.00 | Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification - 100CFT | 1.9 | M3 | 7,577 ₹14,396.30 | 7,577 ₹14,396.30 |
| 7.00 | Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. | 36 | M2 | 284 ₹10,224 | 300 ₹10,800 |
| 8.00 | Supply of Cuddapah Slab 20 / 30mm Thick | 6.5 | M2 | 376 ₹2,444 | 376 ₹2,444 |
| 9.00 | Labour Charges for fixing Cuddapah Slab to Cup-Board | 6.5 | M2 | 45 ₹292.50 | 45 ₹292.50 |
| 10.00Supply and delivery of Following Size PVC and UPVC PIPES FOR POTABLE WATER SUPPLY AS PER IS including cost of materials and conveyence,labour chares,etc., complete. | |||||
Tender Value
₹2 L
EMD Value
₹2,000
Closing Date
29 Jan 2026, 3:00 pmClosed
THE COMMISSIONER UDUMALPET MUNIICPALITY
THE COMMISSIONER UDUMALPET MUNIICPALITY
Providing UGSS Connection and Repair of Toilet Pipe lines at Eripalayam Municipal School Anganvadi,Dharapuram Road Municipal School Anganvadi,Rajalakshmi Nagar Municipal School Anganvadi,Katchery School Municipal School Anganvadi and Sarthar Road Mun
2026_MAWS_646965_1
1736/2024/E1
Open Tender
Civil Works - Others
30 days
UDUMALPET
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2,000
6 Apr 2026
24 Jan 2026
30 Jan 2026
24 Jan 2026
29 Jan 2026
24 Jan 2026
24 Jan 2026 - 29 Jan 2026
Supply and delivery and fixing of 1000 Litre HDPE tank as per IS 12701 / 1996 including loading, unloading, transportation and labour charges for fixing of the GI pipes and specials for pipe connection works including cutting, threading and fixing charges etc.,Twad 2024-25
Dismantling the Plain Cement Concrete, clearing away and carefully stacking materials useful for re-use etc., complete complying with standard specification.
Labour For Cutting open Road for laying water mains or sewer as directed by Departmental officers.Twad 24-25 page No 195
Earth work excavation for foundation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 10 mts and initial lift of 2 mts. and clearing and levelling the site, etc., complete complying with standard specification.(Data 25-26)
Plain Cement Concrete 1:4:8 (one cement four Parts of crushed stone M-sand and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification (The crushed stone sand to be used on cocrete work shell conform to gradation as per IS :383-1970 )
Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification - 100CFT
Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Supply of Cuddapah Slab 20 / 30mm Thick
Labour Charges for fixing Cuddapah Slab to Cup-Board
Supply and delivery of Following Size PVC and UPVC PIPES FOR POTABLE WATER SUPPLY AS PER IS including cost of materials and conveyence,labour chares,etc., complete.
32mm dia UPVC Pipe
25mm dia UPVC Pipe
50mm PVC Pipe (6KSC)
110mm PVC Pipe (6KSC)
Supply and delivery of Following PVC and UPVC Specials FOR POTABLE WATER SUPPLY AS PER IS including cost of materials and conveyence,labour etc., chares,complete
32mm dai UPVC Coupling
25mm dai UPVC Coupling
32mm dai UPVC Elbow
25mm dai UPVC Elbow
32mm dai UPVC Bend
25mm dai UPVC Bend
110mm dia PVC Coupling
110mm dia PVC Elbow
110mm dia PVC bend
Lowering PVC And UPVC pipes and specials to trench and laying to proper grade and alignment, jointing with PVC couplers with cement paste.
Upto 40mm dia pipe
50mm to 75mm dia pipe
90mm to 110mm dia pipe
Refilling with excavated earth other than sand with an initial head load of 100 mts. and depositing the earth as shown by the departmental officers in layers of not more than 15 cm thick well rammed, watered and consolidated etc. complete complying with standard specification. Data 25-26
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.35 MB
BOQ_775503.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid