| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.4 CrAccepted-AOC | ₹6.4 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹6.5 CrRejected-Finance | ₹6.5 Cr | L2 | Rejected-Finance L2 |
| 3 | L3₹7.1 CrRejected-Finance | ₹7.1 Cr | L3 | Rejected-Finance L3 |
| 4 | L4₹8.1 CrRejected-Finance D 609 GOVINDPURAM NEAR 47 P A C GHAZIABAD UTTAR PRADESH | ₹8.1 Cr | L4 | Rejected-Finance L4 |
| 5 | Rejected-Technical | - | - | Rejected-Technical DISQUALIFIED |
Tender Value
₹9.5 Cr
EMD Value
₹19.1 L
Closing Date
4 Feb 2026, 5:00 pmClosed
GM(P)
YAMUNA EXPRESSWAY INDUSTRIAL DEVELOPMENT AUTHORITY
C/o 45 mtr wide Road Along Plot No.-02 and Plot No. 04 in Sector-24A, YEIDA.WC-04
2026_YEIDA_1107376_32
YEA/GM(PROJECT)/2026/455 DT-14/01/2026
Open Tender
Civil Works
365 days
YAMUNA EXPRESSWAY INDUSTRIAL DEVELOPMENT AUTHORITY
Please refer Tender documents.
5 documents required · 5 mandatory
₹6,770
₹19.1 L
19 May 2026
22 Jan 2026
5 Feb 2026
22 Jan 2026
4 Feb 2026
22 Jan 2026
Road Part,Clearing grass and removal of the rubbish up to a distance of 50 m Outside the periphery of the area cleared.
Earth work in rough excavation, banking excavaated earth in layers not exceeding 20 cm in depth, breaking clods watering, rolling each layer with 1/2 tonnes roller or wooden or steel rammer and rolling every 3rd and top most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, all leads as per ( MOST / A.R. / YEIDA ) For all kind of soil.
Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density).DSR-18/1 6.2 /P-240
Granular sub-base with close graded A, plant mix method Construction of granular sub-base by providing close graded material, mixing in mechanical mix plant at OMC, carriage of mixed material to work at motar grader on prepared surface and compacting with vibratory roller to achieve the desired density, complete as per clause 401 for grade-1 material (MORTH/(AR/YEIDA)
Wet mix macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam precification including premixing the material with water OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in sub base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per Technical Specification Clause 406 of MORTH/(AR/YEIDA)
Brick edging in full brick width and half brick depth including excavation, refilling and disposal of surplus earth lead upto 50 metres. With F.P.S. bricks of class designation 150
Providing and applying primer coat with bitumen VG:10 on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.75 kg/sqm using mechanical means
Providing and applying Tack coat on prepared surface with bitumen VG:10 in boiler and spraying the emulsion with spray set fitted on bitumen boiler including clearing , preparing the existing road surface as per specification on granular Base such as W.B.M. and W.M.M. surface not bitumen primed with 2.5 Kg Of bitumen for 10 sqm
Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required level and grade. A/R/MOST/25
Providing and carting of following dia rcc hume pipe s&s NP-3 class &specials in site of work lowering the same into trenches in depth up to alignment jointing with 1;2 cement morter in coarse sand including excavation of earth below invert level of pipe.250 mm dia Np3 pipe
Constructing masonry Chamber 60x60x75 cm, inside with 150mm class designation brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for fire hydrants, with C.l. surface box 350x350 mm. top and 165 mm deep (inside) with chained lid and RCC top slab 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation concrete 1:5:10 (1 cement: 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement: 3 coarse sand) 12 mm thick finished with a floating coat of neat cement complete as per standard design:With F.P.S. bricks DAR-18/18.36.1
Cement Concrete with 4 cm gauge approved stone ballast, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work.As in item 279 above but in proportions of 8:4:1
Class-150 (Non Modular) brick work in 1:4 cement and Coarse sand mortar in foundation and plinth including supply of all material, labour and T&P etc. required for proper completion of the work.
12mm cement plaster of mix:1:6 (1 cement : 6 coarse sand) DAR-18/13.4.2
Providing and laying at or near ground level factory made kerb stone of M-25 grade cement in position to the required line, level and curvature jointed with cement mortar 1:3 (1 cement: 3 coarse sand) including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm) including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge).DAR-18/16.69
White washing with lime to give an even shade: New work (three or more coats) DAR-18/13.37.1
Providing and applying 2.5mm thick road marking strips (retro-reflective) of specified shade/ colour using hot thermoplastic material by fully/ semi automatic thermoplastic paint applicator machine fitted with profile shoe, glass beads dispenser, propane tank heater and profile shoe heater, driven by experienced operator on road surface including cost of material, labour ,T&P, cleaning the road surface of all dirt, seals, oil, grease and foreign material etc. complete as per direction of Engineer-in- charge and accordance with applicable specifications.DAR-18/16.62
(ROYALITY)Granular sub-base with close graded A, plant mix method Construction of granular sub-base by providing close graded material, mixing in mechanical mix plant at OMC, carriage of mixed material to work at motar grader on prepared surface and compacting with vibratory roller to achieve the desired density, complete as per clause 401 for grade-1 material (MORTH/(AR/YEIDA)
(ROYALITY)Wet mix macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam precification including premixing the material with water OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in sub base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per Technical Specification Clause 406 of MORTH/(AR/YEIDA)
(ROYALITY)Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required level and grade. A/R/MOST/25
Drain Part,Excavation in foundation in ordinary soil (loamclay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth ad directed by the Engineer in charge up to a distance of 30m. from the foundation trenches including all T&P phowarah and basket etc. complete (Where Machine not reached/Move)
Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size). DAR-18 / 4.1.8
Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns, etc. for mass concrete.DAR-18 /5.9.1
Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.DAR-18 / 5.9.2
Suspended floors, roofs, landings, balconies and access platform. DAR-18 / 5.9.3
Edges of slabs and breaks in floors and walls.Above 20 cm wide DAR-16/ 5.9.16.2
Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering,shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum.Excess/less cement used as per design mix is payable/recoverable All work upto plinth level DAR-18/5.33.1
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.Cold twisted bars DAR-18 / 5.22.6
Sewer Part;Excavation in foundation in ordinary soil (loamclay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth ad directed by the Engineer in charge up to a distance of 30m. from the foundation trenches including all T&P phowarah and basket etc. complete a.0.00 - 1.50 m B.G.L
Extra 20% for under subsoil condition a.1.50 - 3.00 m B.G.L
Supply and laying of ISI marked R.C.C. NP-3 pipes of following sizes including carting, loading, unloading, at godown, including all taxes and levies & rubeer rings.of following dia;a. 350mm dia
450mm dia
Extra 20% for under subsoil condition a.350mm dia
450mm dia
500mm dia
Supplying and stacking at site.90 mm to 45 mm size stone aggregate.
Royality
Extra 20% for under subsoil condition
Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size
Extra 20% for under subsoil condition
Providing and laying in position specified grade of cement concrete excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Extra 20% for under subsoil condition
Centering and shuttering including strutting, propping etc. and removal of form for:Foundations, footings, bases of columns, etc. for mass concrete.
Extra 20% for under subsoil condition
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.Thermo-Mechanically Treated bar DSR-13/5.22.6
Extra 20% for under subsoil condition
Construction of RCC core conical manhole 1.50m internal dia at bottom and 0.56m dia top and 4.95 m deep in or under sub soli water .Brick massonary with 150 class designation FPS bricks in cement mortar 1:4(cement : coarse sand) and RCC core in cement concrete proportion 1:1 1/2 :3(1 cement: 1 1/2 coarse sand:3 graded stone aggregate 20 mm nominal size) foundation concrete 1:4:8(1 cement:4 coarse sand:8 graded stone aggregate 40 mm nominal size) over 100 mm dry stone soiling of 40 mm aggregate with 20% blinding material such as moorum etc. well consolidated with steel rammers necessary shuttering etc. inlide out side plastering 12mm thick with cement mortar 1:3(1 cement:3 coarse sand) finished with a floating coat of neat cement and making cunnette in cement concrete 1:2:4 (1 cement:2 coarse sand: 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement including providing and embedding of 12 mm poly propelene coated foot rest 300 mm centre to centre and embedded in cement concrete
EXTRA DEPTH For 1.50 m internal dia 4.95 m deep conical manhole of composite section.
Brick work with brick of class designationm-150 in foundation and plinth in cementmorter 1:4 (1cement ; 6coarse sand) D.A.R./ 2013/ P-99/ 6.1.1
2.5% maintance for road work
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.36 MB
32.pdf
Tender Documents • 1.34 MB
BOQ_2046642.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid