| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.5 LAccepted-AOC HARDAHA BALUWA VARANASI CHANDAULE | ₹9.5 L | L1 | Accepted-AOC L1 |
| 2 | L2₹10.8 L+₹1.3 L (13.4%)Rejected-Finance 1 234 8 | ALIGARH | UTTAR PRADESH | 202001 | ₹10.8 L+₹1.3 L (13.4%) | L2 | Rejected-Finance L2 |
| 3 | L3₹11.2 L+₹1.6 L (17.2%)Rejected-Finance | ₹11.2 L+₹1.6 L (17.2%) | L3 | Rejected-Finance L3 |
| 4 | L4₹11.3 L+₹1.8 L (18.7%)Rejected-Finance | ₹11.3 L+₹1.8 L (18.7%) | L4 | Rejected-Finance L4 |
| 5 | L5₹11.6 L+₹2.0 L (21.4%)Rejected-Finance | ₹11.6 L+₹2.0 L (21.4%) | L5 | Rejected-Finance L5 |
| Sl No | Description | Qty | Unit | M/S Harish Kumar Contractor L2 | M/S SHIVA ENGG AND CONTRACTOR L6 | AVISHEK GAUR L4 | M/S SHIV CONSTRUCTION L1 | M/S YAMUNA EARTH MOVERS L3 | SHIV GANGA CONTRACTOR L5 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00 | clearing thick jungle and thorny bushes (without uprooting ) with disposal. | 800 | Sqm | 3.17 ₹2,534.4 | 3.6 ₹2,880 | 4 ₹3,200 | 0.1 ₹80 Lowest | 3.27 ₹2,616 | 3.39 ₹2,712 |
| 2.00 | Earth work in foundation in ordinary soil (loam clay or sand) including lift upto 1.5M and lead upto 30M including back filling,watering and ramming of excavated earth into the structure and the sides of foundation trenches or into the plinth with removal | 450 | cum | 72 ₹32,400 | 82 ₹36,900 | 50 ₹22,500 | 10 ₹4,500 Lowest | 74.42 ₹33,489 | 77.1 ₹34,695 |
| 3.00 | Providing & Laying of PCC ( 1:4:8) with cement :course sand zone 3 : Stone aggregates in foundation of posts including cost of Material, labour and T & P etc complete | 5.69 | cum | 4,058.46 ₹23,080.46 | 4,624 ₹26,296.69 | 3,000 ₹17,061 | 2,800 ₹15,923.6 Lowest | 4,194.86 ₹23,856.17 | 4,397.78 ₹25,010.17 |
| 4.00 | P / F of ordinary centering & shuttering for CC works including cost of all material, labour, and t&p etc. complete. | 203.04 | Sqm | 414 ₹84,058.56 | 471 ₹95,631.84 | 300 ₹60,912 | 150 ₹30,456 Lowest | 427.91 ₹86,882.85 | 443.32 ₹90,011.69 |
| 5.00 | Providing & Laying of cement concrete with 1:1.5:3 cement :course sand zone 3 : Stone aggregates or M-20 for railing & precast posts embeded with concrete including cost of all material T&P and labour etc. complete . | 20.3 | cum | 4,710.51 ₹95,642.27 | 5,368 ₹1,08,991.87 | 4,000 ₹81,216 | 3,500 ₹71,064 Lowest | 4,868.83 ₹98,856.72 | 5,026.15 ₹1,02,050.95 |
| 6.00 | finishing walls with Acylic smooth paint of exterior required shade: New work (two or more cost applied@ 1.67 ltr/10 sqm over and including priming cost of exterior primer applied @ 2.20 kg/10sqm) supply of all labour material and T&P required for proper completion of work. for two Coats. | 1,464 | Sqm | 100.8 ₹1,47,571.2 | 115 ₹1,68,360 | 100 ₹1,46,400 | 35 ₹51,240 Lowest | 104.18 ₹1,52,519.52 | 107.94 ₹1,58,024.16 |
| 7.00 | Providing & Fixing of precast prestressed 6 feet height Boundary wall consisting of 150 x150 mm vertical I- section post and 2100 x300x50mm panel of prestressed concrete M- 25,reinforced with 4 mm high strength tensile steel wire complete as per direction of Engineer in charge. | 400 | R.Mtr | 1,738.8 ₹6,95,520 Lowest | 1,981 ₹7,92,400 | 2,000 ₹8,00,000 | 1,950 ₹7,80,000 | 1,797.24 ₹7,18,896 | 1,861.97 ₹7,44,788 |
Tender Value
₹15.0 L
EMD Value
₹31,000
Closing Date
15 Jun 2026, 11:00 amClosed
Executive Engineer
L.M.B.D.G.C., Mathura
Pre-cast Boundary Wall for Security of Bajna Inspection House.
2026_UPIDC_1155497_6
03/EE/Lower Mat/2026-27
Open Tender
Civil Works - Canal
Item Rate
90 days
L.M.B.D.G.C.
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹31,000
24 Jul 2026
9 Jun 2026
15 Jun 2026
9 Jun 2026
15 Jun 2026
9 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | clearing thick jungle and thorny bushes (without uprooting ) with disposal. | 800 | Sqm | - | - |
| 2 | Earth work in foundation in ordinary soil (loam clay or sand) including lift upto 1.5M and lead upto 30M including back filling,watering and ramming of excavated earth into the structure and the sides of foundation trenches or into the plinth with removal | 450 | cum | - | - |
| 3 | Providing & Laying of PCC ( 1:4:8) with cement :course sand zone 3 : Stone aggregates in foundation of posts including cost of Material, labour and T & P etc complete | 5.69 | cum | - | - |
| 4 | P / F of ordinary centering & shuttering for CC works including cost of all material, labour, and t&p etc. complete. | 203.04 | Sqm | - | - |
| 5 | Providing & Laying of cement concrete with 1:1.5:3 cement :course sand zone 3 : Stone aggregates or M-20 for railing & precast posts embeded with concrete including cost of all material T&P and labour etc. complete . | 20.3 | cum | - | - |
| 6 | finishing walls with Acylic smooth paint of exterior required shade: New work (two or more cost applied@ 1.67 ltr/10 sqm over and including priming cost of exterior primer applied @ 2.20 kg/10sqm) supply of all labour material and T&P required for proper completion of work. for two Coats. | 1,464 | Sqm | - | - |
| 7 | Providing & Fixing of precast prestressed 6 feet height Boundary wall consisting of 150 x150 mm vertical I- section post and 2100 x300x50mm panel of prestressed concrete M- 25,reinforced with 4 mm high strength tensile steel wire complete as per direction of Engineer in charge. | 400 | R.Mtr | - | - |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.06 MB
BOQ_2164606.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .