| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹92.2 LAccepted-Finance DOOR NO 7 345 SURVEY NO 7 345 P P COLONY | PONDICHERRY | PUDUCHERRY | 605001 | L-1 | Accepted-Finance L-1 Low Price | |
| 2 | L-2₹94.9 L+₹2.7 L (2.92%)Accepted-Finance | L-2 | Accepted-Finance L-2 More Price |
Tender Value
₹92.3 L
EMD Value
₹96,000
Closing Date
17 Aug 2020, 3:00 pmClosed
Project Director
DRDA, Ranipet District
Ranipet District Implementation of Jal Jeevan Mission to provide Functional Household Tap connection to Rural Households in Bagaveli,Ananthalai Village Panchayats in Walajah Panchayat Union for the year 2020-21 Package No.43
2020_RDTN_173417_1
Rc.No.4158-2020,Dt 16.7.2020
Open Tender
Civil Works
Item Rate
180 days
DRDA, Ranipet
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹96,000
1 Sept 2020
25 Jul 2020
17 Aug 2020
25 Jul 2020
17 Aug 2020
25 Jul 2020
Amount
Walajah package no.43
katteri
Pipe connection arrangement for house service connection in katteri
supply and lying main line
cost of supply pf 90 mm dia pvc pipe 6 ksc
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
laying of 90 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
bagaveli
Pipe connection arrangement for house service connection in bagaveli
supply and lying Deliveryling line
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
supply and lying main line
cost of supply pf 90 mm dia pvc pipe 6 ksc
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
laying of 90 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
anathalai
Pipe connection arrangement for house service connection in anathalai
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
providing main pipe line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
supplying of 80 mm GI pipe including all labour charges etc
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
laying and 80 mm GI Pipe all labour charges
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
pumping main at OHT water meter
Construction of Road for Restoring the Cut Portion
Dismantling cement concrete 1:2:4 work including all labour charges etc complete
Dismantling cement concrete work 1:4:8 including all labour charges etc complete
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
Automatic chlorination
kolathur
Pipe connection arrangement for house service connection in kolathur
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
providing main pipe line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
supplying of 80 mm GI pipe including all labour charges etc
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
laying and 80 mm GI Pipe all labour charges
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
pumping main at OHT water meter
Construction of Road for Restoring the Cut Portion
Dismantling cement concrete 1:2:4 work including all labour charges etc complete
Dismantling cement concrete work 1:4:8 including all labour charges etc complete
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
Edapalayam
Pipe connection arrangement for house service connection in edapalayam
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
providing main pipe line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
supplying of 80 mm GI pipe including all labour charges etc
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
laying and 80 mm GI Pipe all labour charges
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
pumping main at OHT water meter
Construction of Road for Restoring the Cut Portion
Dismantling cement concrete 1:2:4 work including all labour charges etc complete
Dismantling cement concrete work 1:4:8 including all labour charges etc complete
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
Ganapathynagar
Pipe connection arrangement for house service connection in ganapathy nagar
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
Construction of Road for Restoring the Cut Portion
Dismantling cement concrete 1:2:4 work including all labour charges etc complete
Dismantling cement concrete work 1:4:8 including all labour charges etc complete
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
pothigai nagar
Pipe connection arrangement for house service connection in pothigai nagar
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
providing main pipe line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
supplying of 80 mm GI pipe including all labour charges etc
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
laying and 80 mm GI Pipe all labour charges
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
pumping main at OHT water meter
Construction of Road for Restoring the Cut Portion
Dismantling cement concrete 1:2:4 work including all labour charges etc complete
Dismantling cement concrete work 1:4:8 including all labour charges etc complete
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
aruthathi colony
Pipe connection arrangement for house service connection in aruthathi colony
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
thiruvalluvar nagar
Pipe connection arrangement for house service connection in thiruvalluvar nagar
supply and lying Deliveryling line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
Supply and Delivery of 63mm dia PVC pipe as per IS 4985/part I/2000 including all conveyance chargess 4ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and Fixing of 63mm dia PVC Specials as per IS 4985/part I/2000 including all conveyance chargess 6ksc ISI standard PVC pipe including all labour charges etc Complete
Supply and fixing of 63mm PVC Tee including all conveyence charge etc.
Supply and fixing of 63mm PVC Elbow including all conveyence charge etc.
Supply and fixing of 63mm PVC bend including all conveyence charge etc.
supply and fixing of 50 mm GI pipe as per IS 4985 part 1 2000 including all conveyance charges 6ksc ISI standard PVC pipe including all labour charges etc complete
laying of 63 mm PVC pipe all labour charges etc coplete
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
Distribution line starting at OHT water meter
providing main pipe line
Earth work excavation and depositing on bank with initial lead and lift of 10M& 2M for pipe Laying Works With Standard trench width and depth etc Completed
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
supplying of 80 mm GI pipe including all labour charges etc
supplying 90 mm HDPE PN 6pipe 100 as per ISI 4984 /2016 including all labour charges etc Complete
laying and 80 mm GI Pipe all labour charges
Refilling the Excavated earth in pipe line trench including all labour charges etc complete
pumping main at OHT water meter
Construction of Road for Restoring the Cut Portion
Dismantling cement concrete 1:2:4 work including all labour charges etc complete
Dismantling cement concrete work 1:4:8 including all labour charges etc complete
Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Cement Concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete
GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column "BB" for all works in this package}
Narasimhan Kondapalayam
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .