Tender Value
₹35.7 L
EMD Value
₹35,700
Closing Date
22 Feb 2022, 11:00 amClosed
The Chief Engineer, PWD (NH), Nagaland, Kohima
O/o The Chief Engineer, PWD (NH), Nagaland, Kohima
FDR works on NH-202 under National Highways Division-IV, Kiphire Nagaland during 2021-22
2022_MoRTH_673506_1
CE/NH/FDR/2021-22/Kip
Open Tender
Civil Works - Highways
Item Rate
90 days
Kohima
Please refer Tender Documents
4 documents required · 4 mandatory
₹0
₹35,700
24 Feb 2022
14 Feb 2022
23 Feb 2022
14 Feb 2022
22 Feb 2022
14 Feb 2022
Amount
Clearance of Landslides in soil and ordinary rocks by a Bulldozer D-80 A-12, 180 Hp and disposal of the same on the valley side.
Clearance of Landslides in soil and ordinary rocks by a Bulldozer D-80 A-12, 180 Hp and disposal of the same on the valley side.
Construction of face wall and catch pit:- Earthwork in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, dressing of sides and bottom, back filling the excavated earth to the extend of required and utilizing the remaining earth locally for the road work.Ordinary soil
Plain/Reinforced cement concrete in open foundation complete as per drawing and technicalspecifications.( Using batching plant & manual placing) M 15
Stone Masonry work in Cement Mortar 1:3 in Foundation complete as per Drawing and Technical specifications:RRM
Back filling behind the Wing wall and return wall complete as per drawing & Technical specifications:
Construction of ganular sub-base by providing granular material,mixing in mechanical mix plant at OMC, carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401. Gr.II
Construction of Retaining Wall:- Earthwork in excavation of foundation of structures as per drawing and technical specification, incuding setting ,construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, back filling complete, in ordinary rock.
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications.Using Batching Plant & Manual placing M-15
Stone Masonry Work in Cement Mortar 1:3 for substructure complete as per drawing and technical Specifications. a.Coursed rubble masonry.
Backfilling behind abutment, wing wall and return wall complete as per specification. A. Granular materials
Construction of Hume Pipe Culvert :- Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. PC.C M-15
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401) Gr.III
Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row . (Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets . ) 1000 mm
Catch Pit:- Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. PC.C M-15
Stone masonry (Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
Guide Wall Apron:- Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.)
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. PC.C M-15
Stone masonry (Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
Construction of ganular sub-base by providing granular material,mixing in mechanical mix plant at OMC, carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401.Gr.II
M/s A.Neangba
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .