Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.9 LAccepted-AOC OPPOSITE MERCEDES SHOWROOM NALAPARA BIHARBARI GUWAHATI 781029 ASSAM | RI BHOI | MEGHALAYA | 781029 | ₹23.9 L Quoted ₹24.2 L | L1 | Accepted-AOC First Lowest |
| 2 | L2₹26.6 L+₹2.4 L (9.94%)Rejected-Finance | ₹26.6 L+₹2.4 L (9.94%) | L2 | Rejected-Finance Not L1 |
| 3 | L3₹26.9 L+₹2.7 L (11.0%)Rejected-Finance | ₹26.9 L+₹2.7 L (11.0%) | L3 | Rejected-Finance Not L1 |
| 4 | L4₹27.7 L+₹3.5 L (14.3%)Rejected-Finance | ₹27.7 L+₹3.5 L (14.3%) | L4 | Rejected-Finance Not L1 |
| 5 | L5₹27.9 L+₹3.7 L (15.5%)Rejected-Finance | ₹27.9 L+₹3.7 L (15.5%) | L5 | Rejected-Finance Not L1 |
| Sl No | Description | Qty | Unit | KAKWANI BUILDERS L5 | M/S Narayan Chandra Das L6 | Tractors Machinary Components L4 | M/S MANOJ PAUL L3 | M/S P&R CONSTRUCTIONS L1 | R S TRADERS L2 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Demolition of cement concrete and paving not exc 15 cm thick (below or above ground level) complete all as specified and as directed. | 8.15 | Cum | 100 ₹815 Lowest | 300 ₹2,445 | 1,350 ₹11,002.5 | 400 ₹3,260 | 100 ₹815 Lowest | 800 ₹6,520 |
| 2.00 | Demolition of cement concrete (un-reinforced ) of any description & in any position not specifically provided for complete etc all as specified and as directed | 5.43 | Cum | 100 ₹543 Lowest | 350 ₹1,900.5 | 1,550 ₹8,416.5 | 500 ₹2,715 | 100 ₹543 Lowest | 1,000 ₹5,430 |
| 3.00 | Demolition of reinforced cement concrete (reinforcement cut as required to facilitate demolition) of any description & in any position not specifically provided for complete all as specified and as directed | 1.35 | Cum | 100 ₹135 Lowest | 450 ₹607.5 | 1,750 ₹2,362.5 | 700 ₹945 | 200 ₹270 | 1,000 ₹1,350 |
| 4.00 | Demolition of brick work /stone masonry masonry built in cement mortar of any description all as specified and directed. | 1.05 | Cum | 100 ₹105 Lowest | 200 ₹210 | 1,550 ₹1,627.5 | 600 ₹630 | 150 ₹157.5 | 800 ₹840 |
| 5.00 | Taking down shutter of any description area exc 1.00 Sqm but not exc 2.00 sqm each and refixing in same opening etc complete all as specified and as directed | 140 | Per Leaf | 100 ₹14,000 Lowest | 250 ₹35,000 | 190 ₹26,600 | 100 ₹14,000 Lowest | 120 ₹16,800 | 100 ₹14,000 Lowest |
| 6.00 | Taking down cement plaster of any description hacking for key or raking out joint on old brick work/ stone /concrete surface etc complete all as specified and as directed | 135 | Sqm | 10 ₹1,350 Lowest | 50 ₹6,750 | 90 ₹12,150 | 40 ₹5,400 | 50 ₹6,750 | 100 ₹13,500 |
| 7.00 | Demoition of Stone slabs and tiles of any description or thickness in floors, aprons , laid bedded and pointed in any mortar etc complete all as specified and as directed | 3.7 | X Sqm | 100 ₹370 Lowest | 800 ₹2,960 | 600 ₹2,220 | 500 ₹1,850 | 100 ₹370 Lowest | 1,000 ₹3,700 |
| 8.00 | Dismantling floor, hearth or wall tiling including cement mortar bedding (but not backing), removing serviceable
tiles to store and rubbish off the premise etc complete all as specified and as directed | 1,338.4 | Sqm | 12 ₹16,060.8 Lowest | 40 ₹53,536 | 85 ₹1,13,764 | 90 ₹1,20,456 | 25 ₹33,460 | 100 ₹1,33,840 |
| 9.00 | Taking up or down 15mm steel tubing and connections incl cleaning for refixing and removal to store etc complete all as specified and as directed. | 110 | RM | 200 ₹22,000 | 30 ₹3,300 Lowest | 30 ₹3,300 Lowest | 30 ₹3,300 Lowest | 100 ₹11,000 | 30 ₹3,300 Lowest |
| 10.00 | Taking up or down 20 mm steel tubing and connections incl cleaning for refixing and removal to store etc complete all as specified and as directed. | 33 | RM | 250 ₹8,250 | 290 ₹9,570 | 35 ₹1,155 | 35 ₹1,155 | 100 ₹3,300 | 33 ₹1,089 Lowest |
Tender Value
₹30 L
EMD Value
₹60,000
Closing Date
16 Apr 2026, 6:00 pmClosed
GE Narangi
GE Narangi C/0 99 APO
REPAIR/ REPLACEMENT OF FLOORING, WALL TILING IN KITCHEN/ BATHROOM/ TOILET AND CONNECTED ITEM IN MD ACCN AT PH-II AREA UNDER GE NARANGI
2026_MES_758010_1
8193/B/E8
Open Tender
Civil Works
Item Rate
180 days
Guwahati
Please refer Tender documents.
8 documents required · 8 mandatory
₹500
GE Narangi
₹60,000
Yes
24 Jun 2026
27 Mar 2026
18 Apr 2026
27 Mar 2026
16 Apr 2026
10 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Demolition of cement concrete and paving not exc 15 cm thick (below or above ground level) complete all as specified and as directed. | - | Cum | - | - |
| - | Demolition of cement concrete (un-reinforced ) of any description & in any position not specifically provided for complete etc all as specified and as directed | - | Cum | - | - |
| - | Demolition of reinforced cement concrete (reinforcement cut as required to facilitate demolition) of any description & in any position not specifically provided for complete all as specified and as directed | - | Cum | - | - |
| - | Demolition of brick work /stone masonry masonry built in cement mortar of any description all as specified and directed. | - | Cum | - | - |
| - | Taking down shutter of any description area exc 1.00 Sqm but not exc 2.00 sqm each and refixing in same opening etc complete all as specified and as directed | - | Per Leaf | - | - |
| - | Taking down cement plaster of any description hacking for key or raking out joint on old brick work/ stone /concrete surface etc complete all as specified and as directed | - | Sqm | - | - |
| - | Demoition of Stone slabs and tiles of any description or thickness in floors, aprons , laid bedded and pointed in any mortar etc complete all as specified and as directed | - | X Sqm | - | - |
| - | Dismantling floor, hearth or wall tiling including cement mortar bedding (but not backing), removing serviceable
tiles to store and rubbish off the premise etc complete all as specified and as directed | - | Sqm | - | - |
| - | Taking up or down 15mm steel tubing and connections incl cleaning for refixing and removal to store etc complete all as specified and as directed. | - | RM | - | - |
| - | Taking up or down 20 mm steel tubing and connections incl cleaning for refixing and removal to store etc complete all as specified and as directed. | - | RM | - | - |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.42 MB
8193Tender.pdf
Tender Documents • 0.61 MB
BOQ_849057.xls
BOQ • 1.21 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .