Tender Value
₹66.0 Cr
EMD Value
₹1.3 Cr
Closing Date
30 Jun 2026, 12:00 pmClosed
Yes (up to 5 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
CE/CON/II
16 conditions · 4 needing a document upload
Submit the scanned copy (In PDF Form) of the documents as per the requirement of financial eligibility criteria of the tender [Refer para 2.3 of tender document {Para 2.3 for tenderer(s) participating as JV firm}]. TENDERS NOT ACCOMPANIED BY THESE DOCUMENTS WILL BE SUMMARILY REJECTED.
Submit the scanned copy (In PDF Form) of the documents for evaluating the Bid Capacity (Please refer Clause 12.25 of tender document). This is applicable in all works contract having tender value of Rs. 10.00 Crore and above. TENDERS NOT ACCOMPANIED BY THESE DOCUMENTS WILL BE SUMMARILY REJECTED.
Definition of Similar Work:- 1. For Civil Engineering works (Rs. 429822684.83/-): "Any fabrication and erection work of steel structures in construction of Foot Over Bridges/ Workshops/ Sheds/ Platform Shelters/ Bridges/ Road Over Bridges". 2. For Mechanical Engineering works (Rs. 124148202.00/-): "Any work involving supply, erection and commissioning of M&Ps in Railway workshop/Sheds/Depots". 3. For Electrical Engineering works (Rs. 106360139.20/-): "Works of Design, Supply, erection, testing and commissioning of 25 KV AC OHE and/or Traction power supply installation works for Railways. The certificates for the private works shall not be accepted".
Fabrication of steel structure are to be done under RDSO approved fabrication yard of RDSO approved vendor only.
27 conditions · 15 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Notes for all schedules: Standard Schedule of Rates (SSOR) Items: Any item of work carried out by the Contractor on the instructions of the Engineer which is not included in the accepted Bill(s) of Quantities but figures in the Standard Schedule of Rates (SSOR), shall be executed at the rates set forth in the "Standard Schedule of Rates (SSOR)" modified by the tender percentage as accepted in the contract for that chapter of Standard Schedule of Rates (SSOR). However, the cumulative value of all such extra item(s) together (modified by the respective tender percentage) shall not exceed 10 % of the original contract value.
Option of Payment through Letter of Credit (L.C.): Tenderer(s) may submit option for taking payment through Letter of Credit (L.C.). [Refer para 7.1 of tender document].
Credentials if submitted in foreign currency shall be converted into Indian currency i.e., Indian Rupee as under: The conversion rate of US Dollars into Rupees shall be the daily representative exchange rates published by the Reserve Bank of India for the relevant date. Where, relevant date shall be as on the last day of month previous to the one in which tender is invited. In case of any other currency, the same shall first be converted to US Dollars as on the last day of month previous to the one in which tender is invited, and the amount so derived in US Dollars shall be converted into Rupees at the aforesaid rate. The conversion rate of such currencies shall be the daily representative exchange rates published by the International Monetary Fund for the relevant date.
Contract under EBR (IF): It is agreed by and between the parties that Railway shall continue to be held responsible for all obligations, risk and liabilities, whatsoever, arising out of or in connection with the Principal agreement and this novation agreement, whether during the progress of the work or after its completion. It is further agreed and understood by and between the parties that IRFC shall be the owner of assets, if any, arising out of execution of works as defined in the Principal Agreement, except the land whose ownership shall continue with Railway. Accordingly, the invoices shall be issued by capturing GSTIN of contractor (as the supplier) and GSTIN of IRFC (as bill to party). Also, the contractor shall submit the invoice, issued in the name of IRFC, to railway for processing payment by Railway to contractor subject to applicable TDS under the Income Tax, GST or any other applicable laws. It is further agreed by and between the Parties that IRFC shall be responsible to comply with Income Tax and GST laws in relation to filling of returns.
There are several changes in the tender document after the new GCC April 2022 is issued. Tenderer(s) are requested to go through the tender document & GCC carefully before the submission of the offer.
Clarification of Bids: To assist in the examination, evaluation & comparison and pre-qualification of the Tender, the Railway may, at its discretion, ask any Bidder for a clarification of its Bid. Any clarification submitted by a Bidder that is not in response to a request by the Railway shall not be entertained or considered. The Railway request for clarification and the response of the bidder in this regard shall be in writing. However, if a Bidder does not provide clarification of its bid by the date and time communicated in the Railway request for clarification, the bid shall be evaluated as per the documents submitted along with the bid.
All General Instructions are available in the uploaded tender document.
The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document before closing date for submission of bids (i.e. excluding the last date of submission of bids). Nominated officials are Dy CE/Con/Works & Stores/GRC, S. E. Railway, Kolkata-700043 and Dy CE/Con/Tatanagar, Office of the Dy CE/Con/Tatanagar, S. E. Railway.
Composite work for Creation of Advance maintenance facilities of Electric Loco for catering Zonal as well as foreign Railways locomotives at ELS/Tatanagar, Creation of Trip Shed for Trip inspection & maintenance activity of Electric locomotives at ELS/Tatanagar and Creation of Advance maintenance facilities for Electric locos at CTRC/Tatanagar under jurisdiction of Dy Chief Engineer (Con), Tatanagar.
4642-GRC-CE-C-II-25-2026
4642-GRC-CE-C-II-25-2026
Open
Works - General
24 Months
Unknown (Unspecified Location)
₹0
₹1.3 Cr
30 Jun 2026
2 Jun 2026
16 Jun 2026
796 items across 22 schedules · ₹62,90,67,253.04 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| filling in embankment, guide buried type abutments, bridge refuges, platforms etc. with own earth conforming to Soil SQ1/SQ2/SQ3, after preparation as applicable, benching in wherever required, spreading in grader, bringing the moisture mechanical compaction to and dressing of bank to final per RDSO Specifications: IRS-0004 with latest correction 1) Foundation preparation, additional earthwork on wherever required, shall be relevant schedule item for Payment for Earthwork under this made based on the cross section calculated (i) with original of existing bank based on initial before doing benching and (ii) the bank worked out with final prevailing guidelines. | — | — | — | — | |
| 1 | SQ2 | cum | 50.00 | 253.42 | 12,671 |
| cutting in formation, trolley drains, level crossing platforms, catch water drains, nallah & finishing to required slopes to obtain a neat standard profile inclusive of all plant & machinery, leading either to make spoil dumps or for embankment with leads within 2 km of edge of the cutting(s) lifts, ascent, descent, loading, & pumping out water, if of site and all other works for completing the work as Specification No. RDSO/2020/GE: latest updated correction slips satisfaction of the Engineer-in- (i) All usable earth arising from be led into bank formation and shall be dumped / stacked of embankment. (ii) All hard not fit for filling will be contractor and will be property (iii)Cut trees shall be property to be deposited in the railway specified otherwise in the Contract. | — | — | — | — | |
| 2 | and classifications of soil | cum | 55020.00 | 106.59 | 58,64,581.8 |
| 3 | requiring blasting | cum | 8000.00 | 252.66 | 20,21,280 |
| steel work of girders with after surface preparation blasting, followed by one coat of (IS:5666) & one coat of Zinc (IS:104) and two coats of (IS:2339) with all labour, T&P as a complete job duly all relevant specifications and under Clause 39 of IRS-B1-2001. Thickness of sprayed Aluminium be 150 microns. DFT of Zinc shall be 25-30 microns and DFT Aluminium paint shall be 12-14 | — | — | — | — | |
| 4 | during fabrication | Sqm | 25000.00 | 749.25 | 1,87,31,250 |
| Schedule total | ₹2,66,29,782.8 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCCApril-2022.pdf
ATTACHMENT
TD25-2026.pdf
ATTACHMENT
BarChart_1.pdf
ATTACHMENT
JharkhandGovtletter.pdf
ATTACHMENT
AdvanceCorrectionSlipNo1to11.pdf Advance Correction Slips
ATTACHMENT
MechanicalConditions.pdf
ATTACHMENT
AdvanceCorrectionSlipNo1to11.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .