Superintenging Engineer
EDC Ayodhya
New 11 KV Over head H.T. line and L.T. line 70 BHP for Tubewell and 2 KW light fan Connection at Ratiya, New Overhead 11 KV line with 25 KVA Transformer to Amrit Yojana Phase-3 Ayodhya as per request of Ex. Engineer -IIIrd Nirman Khand Jal Nigam Ayo
2021_MVVNL_648320_1
87 H(F)(W)/2021-22
Open Tender
Electrical Works
Item Wise
90 days
Ayodhya
As per Tender Specification
2 documents required · 2 mandatory
₹1,180
Superintending Engineer, EDC
₹2,000
10 Dec 2021
27 Nov 2021
4 Dec 2021
27 Nov 2021
3 Dec 2021
27 Nov 2021
Amount
Carriage including loading, unloading & Proper stacking of following Stock materials from store/departmental store to Dump site distance 0 to 20 Kms. (distance approx)
S.T. Pole 11 Mtr. long
PCC Pole 8.5 Mtr long
11KV XLPE cable 3x70 sq.mm
ACSR Weasel Conductor
11 KV Cable Jointing Kit 3x70 sq mm outdoor
11 KV Staright Through Cable Jointing Kit 3x70 sq mm
11 KV Pilfer proof meatering cubical
11 KV TVM Meter
L.T. XLPE Cable 3.5x240 sqmm
Transformer 25 KVA
Other matching Materials
Dragging of S.T./PCC Pole from dump site to pit site
Fabrication and Errection of Double Pole Support on ST Pole including grouting with 1:4:8 ratio Cement, sand & Brick Ballast& including digging of pit and fixing of all accessories clamp & earthing as per RESPo Norms. (Cost of clamps borne by contractor)
Fabrication and Errection of Single Pole Support on ST/PCC Pole including grouting with 1:4:8 ratio Cement, sand & Brick Ballast& including digging of pit and fixing of all accessories clamp & earthing as per RESPo Norms. (Cost of clamps borne by contractor)
Earthing of Poles as per RESPO Norms
Grouting and Binding of Stay with in 1:4:8 ratio with cement, sand and brick ballast including cost of all grouting materials as per RESSPO Norms
Laying of underground 11 KV 3x70 sq mm XLPE Cable in Normal Soil by digging of trench 1050 mm deep, 750 mm wide including supply of required material as fine sand, Ist class bricks as per norms. (All the material will be supplied by the contractor except 11 KV XLPE cable)
Installation and Fixing of 11 KV Cable Jointing Kit 3x70 mm2 outdoor XLPE Cable Box.
Installation and Fixing of 11 KV Staright Through Cable Jointing Kit 3x70 mm2 XLPE Cable Box.
Stringing, Sagging, binding and jumpering of ACSR Weasel Conductor as per RESSPO Norms
Installation of 11 KV Pilfer Proof Metering Cubical
Installation of 11 KV TVM Meter
Supply and Fixing of G.I. Pipe 6'' dia
Mounting of 25 KVA Transformer as per RESPO Norms
Earthing by way of boring and lowering of "B" class G.I. pipe 50 mm dia 20 mtr. Long from ground upto the water lavel it will be connected to the G.S. Strip for T/F nutral connection the earth strip will be welded to the G.I. pipe the work also included top cap and clamps for pouring water the cost of all material will all labour and T n P etc. complete in all respect . (all the material will be supplied by the contractor.)
M/S ARVIND KUMAR TRIPATHI
ALOK KUMAR SINGH
M/S S K ASSOCIATES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .