Tender Value
₹3.1 L
EMD Value
₹3,500
Closing Date
21 Jul 2023, 5:00 pmClosed
SE ETC MERUT
130 D PARESHAN BHAWAN VICTORIA PARK MEERUT
REPALCEMENT OF GASKETS OF 40 MVA TRANSFORMER
2023_UPTCL_814350_2
T-09/23-24/ETC/MT
Open Tender
Electrical Works
Item Rate
60 days
MEERUT
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
SE ETC MEERUT
₹3,500
1 Aug 2023
4 Jul 2023
22 Jul 2023
4 Jul 2023
21 Jul 2023
4 Jul 2023
Amount
Complete drain out of T/F oil from the existing 40MVA T/F main tank, conservator and radiator by filling into empty oil drums/oil tanker and stacking at proper place.
Complete Dismantling of 40MVA T/F accessories including Radiator, HV/LV/Neutral Bushings, Turrets, Buchholz relay, Colling fans, oil pipe line from conservator tank to main tank, oil pipe line to OLTC and Surge Relay conservator tank etc. along with opening of associated electrical connections, stacking of all dismantled parts at proper place in switchyard including proper blanking of the open points before replacement of Gaskets
Complete Replacement of gaskets of 40 MVA T/F including removal of old/damaged Gasket by providing new gasket as per required size of good quality rubberized cork sheet of NU COCK/TALBROS make at required place of complete T/F including top covers i.e. HV & LV bushing, HV & LV turret, OSR, PRV, Buchholz relay Drain valve, conservator tank, Radiator pipe, MOG & other all accessories.
Complete, erection of 40MVA T/F by erection of radiator, conservator tank, Buchholz relay, PRV, oil pipe line, cooling fans, bushing with its turrets, HV/LV/Neutral bushing, all pipelines, radiator, oil etc. including replacement of defective nuts & bolts (top cover) radiator valve (butterfly valve).
Cleaning of Transformer`s Core and winding by hot T/F oil and removed the slug from bottom.
Creating the Vacuum inside the main tank for period for 12 Hrs. and filling of centrifuging oil step by step up to core & winding ,conservator tank, radiator.
Centrifuging of complete T/F oil (19410 Ltr. Approx.) by connecting centrifuging pipes, circulating the T/F oil through centrifuging machine to increase BDV. Centrifuging of oil in T/F and taking the IR, BDV and PPM value of the period of 04 Hrs. as per norms of transformer manufacturer till the desired value are attained, filling of centrifuging T/F oil up to required oil levels of T/F. Centrifuging machine will be provided by the contactor at his own cost.
Painting of 40 MVA T/F with suitable for gray paint.
Perfect Power Transformer Associates
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .