Tender Value
₹2.4 Cr
EMD Value
₹2.7 L
Closing Date
5 Mar 2026, 3:30 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
BRIDGE
15 conditions · 4 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N crores or V, whichever is lower; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of total contractual payments in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Similar nature of work for this tender is "Any Civil Engineering Work, comprising of Construction of any type of Bridge/ Bridge Jacketing work".
Substantially Completed Work means an ongoing work in which payment equal to or more than 90% of the present contract value (excluding the payment made for adjustment of Price variation (PVC), if any) has been made to the contractor in that ongoing contract and no proceedings of termination of contract on Contractor's default has been initiated. The credential certificate in this regard should have been issued not prior to 60 days of date of invitation of present tender. 2 In case a work is started prior to 07 (seven) years, ending last day of month previous to the one in which tender is invited, but completed in last 07 (seven) years, ending last day of month previous to the one in which tender is invited, the completed work shall be considered for fulfillment of credentials. 3 If a work is physically completed and completion certificate to this extent is issued by the concerned organization but final bill is pending, such work shall be considered for fulfillment of credentials. 4 In case of completed work, the value of final bill (gross amount) including the PVC amount (if paid) shall be considered as the completion cost of work. In case final bill is pending, only the total gross amount already paid including the PVC amount (if paid) shall be considered as the completion cost of work. In case of substantially completed work, the total gross amount already paid including the PVC amount (if paid), as mentioned in the certificate, shall be considered as the cost of substantially completed work. 5 If a bidder has successfully completed a work as subcontractor and the work experience certificate has been issued for such work to the subcontractor by a Govt. Organization or public listed company as defined in Note for Item 10.1 Para 10 of the Tender Form (Second Sheet), the same shall be considered for the purpose of fulfillment of credentials.
18 conditions · 2 needing a document upload
Documents to be uploaded only in the website by the Tenderer Following Annexure duly filled and signed are to be uploaded online only prior to Closing of Tender. Original copy of all the documents to be submitted to office within 7 days whenever demanded by the Railway. Otherwise, Railway reserves rights to Reject/Accept such tender/offer without any reference to the tenderer/ tenderers. Annexure are available at Upload/View Document menu in Home Page of IREPS portal for works tender. Annexure Description 1. Annexure-I(a) Details of the Works Completed by the tenderer during the last seven years to be filled & submitted as per Annexure-I(a). 2. Annexure-I(b) Details of contractual payment received by the Tenderer during the last 3 (three) financial years including the current financial year to be filled & submitted in Annexure-I(b).3 Annexure-II Details of Plants and Machinery with the tenderer to be filled & submitted as per Annexure- II. 4. Annexure-III Details of Personnel and Organization of the Tenderer to be filled & submitted as per Annexure-III. 5. Annexure-IV Details of Works Presently on hand of the Tenderer to be filled & submitted as per Annexure- IV. 6. Annexure-V Details regarding Association of Railway Officer(s) with the tenderer to be filled & submitted as per Annexure- V. 7. Annexure-VI List of the Arbitration Cases of the Tenderer during last five years to be filled & submitted as per Annexure-VI. 8. Annexure-VII List of the Court Cases of the Tenderer during last Five years to be filled & submitted in Annexure- VII. 9. Annexure- VIII NEFT MANDATE FORM. All Payments to the agency (including the refund of the Bid Security of the unsuccessful bidder preferably) will be remitted through NEFT. The Tenderer is required to submit Bank details and A/C No. etc. in Annexure- VIII. 10. Annexure-IX GST COMPLAINT INVOICE: To be filled & submitted as per Annexure-IX. 11. Annexure-V of GCC-2022 FORMAT FOR CERTIFICATE TO BE SUBMITTED / UPLOADED BY TENDERER ALONGWITH THE TENDER DOCUMENTS as per Annexure-V of GCC-2022. Annexure V (A) by each partners of Partnership Firm/ JV/ HUF/ LLP; FORMAT FOR CERTIFICATE TO BE SUBMITTED / UPLOADED BY TENDERER ALONGWITH THE TENDER DOCUMENTS as per Annexure-V (A) of GCC-2022 12. Annexure-XI LETTER OF CREDIT: To be filled & submitted as per Annexure-XI. 13. Annexure-VIA BID SECURITY: Bank Guarantee Bond from any scheduled commercial bank of India to be filled & submitted as per Annexure-VIA. 14. Annexure-VIB Annual Contractual Turnover Data for the Previous 3/4 Years (Contractual Payment only) to be filled & submitted as per Annexure-VIA. 15. Submission of Form V & VA properly. 16. Annexure-VI of GCC- 2022: TENDERER'S CREDENTIALS (BID CAPACITY) to be submitted as per Annexure-VI of GCC-2022. (This annexure will be applicable, if tenders having advertised value more than Rs 20 crore wherein eligibility criteria includes bid capacity).
Demand for the Financial Criteria, Association of Railway Officers, List of Arbitration cases, Court cases and Mandate for NEFT are to be uploaded with a scanned copy duly filled in and signed as per annexure no. IV, V, VI, VII, VIII,IX,XI. Annexure-VI, VI A & VI B of GCC-2022 respectively. These Annexure are available in View Document menu at Home page and is downloadable. The details of the uploaded documents should be produced whenever demanded for verification on written request at any point of time of the tender and contract within 7 days Otherwise, Railway reserves rights to Reject/Accept such tender/offer without any reference to the tenderer/tenderers.
Demand for Mandate for NEFT is to be uploaded with a scanned copy duly filled in and signed as per annexure no. VIII. This Annexure is available in View Document menu at Home page and is downloadable.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Open e-tender for the work of Replacement of damaged RCC slab & jacketting work of Bridge number 386/D (16x4.57 mtr) (Span no 1,9,10,12,13,14,15) at Km 258/11-12 in New Farakka-Barharwa section of Malda Division under the jurisdiction of Divisional Engineer-I/Eastern Railway/Malda.
198-MLDT-25-26~ER
198-MLDT-25-26
Open
Works - General
12 Months
Maldah, West Bengal
₹0
₹2.7 L
5 Mar 2026
10 Feb 2026
19 Feb 2026
66 items across 4 schedules · ₹2,35,56,260.41 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Making water tight coffer dam earthen platform by any means i.e. by earth work or by filled with earth sand retained on nominal slope or ballah piling as necessary or lay any other means in a particular space i.e. in excavation etc. to enable the space to be dewatered. The rate also includes removal of earthen platform and clearing work site upto the satisfaction of Site In-charge. After the work is completed written approval of Railway Engineer should be obtained for operating this item. Ingredients of RCC including cement, labour, tools & plants and all testing as directed by the Site Engineer In-charge. | cum | 250.00 | 353.43 | 88,357.5 |
| 2 | Supplying and driving hard wood ballah piles of sal or similar types of length varying from 5m to 6m and of average diameter 150mm. The rates includes supplying and erecting of derricks, monkey, all other necessary equipments, tools, plants, fuel, labours etc. as required for completion of the work in all respect. The rate also includes application on single layer bitumen on the ballah piles before they driven in to the ground. The ballah shall be driven only when these are passed by the competent authority and driven order is given. | Metre | 400.00 | 533.69 | 2,13,476 |
| 3 | Driving Rail of section 90R/52kg/75 lbs of length 8 mtr. to 10 mtr. The rate should be included labours, cutting of rails (to be supplied by the Railway free of cost), leading of rails to the site of work upto man in distance of 100 mtr. from the unloading site. Supply of all tools & plants, fuel, lift complete Note: Approx. 2/3rd of rail length will be driven inside the earth and payment will be made for the length of rail driven in the earth only. | Metre | 400.00 | 686.29 | 2,74,516 |
| 4 | Linking of track with new rails/ existing rails at site to the proper alignment with 52Kg/ 60Kg. rails & PSC sleepers with M+7 or M+8 density including complete fitting ensuring correct spacing of sleepers, squaring, maintaining proper gauge, alignment, Cross level etc. Complete in all respect. | Track metre | 60.00 | 414.75 | 24,885 |
| 5 | Supplying of machine hard stone crushed track ballast confirming to RDS0's specification IRS-GE-1 of June'2016 (as amended vide upto date correction slips) including leading to point loading and loading the same into BOBYN type wagons F.O.R Bakudih quarry. The rate is inclusive of all cost, labour, materials, tools, and plants, equipment, machinery, all ead/lift, handling/ re-handling, loading/unloading, transportation, crossing bf Railways tracks/nalah/river/stream as required, Safety precautions in vicinity of Railway track, inclusive of all Royalties, taxes (including GST) levied by central/state Govt. & local bodies and all other incidental charges etc. complete in all respect. | cum | 50.00 | 1,707.17 | 85,358.5 |
| 6 | Assistance to Crane work as directed by site- in-charge prior to Crane work like preparation of base for prop. by dressing of earth filling and placing of sand bags at required distance from the bridge approach and cutting of holding down bolts before lifting of Girder and also after lifting of Girder for proper seating of slabs, cutting of other infringements like old pipes for shifting of Cables etc. and dismantling of Cribs prepared earlier. This includes lifting of ballast in bags in cess around bridge or assisting any other type of lifting of ballast on the bridges and approaches. Assisting, unloading, loading, lifting, loading of different Crane materials from the Crane for Crane working. unit "Each" to be read as "Operation". | Each | 2.00 | 9,016.6 | 18,033.2 |
| 7 | Dismantling of existing track including segregating and stacking of released components such as Rails, sleepers, fittings etc. at site as per instruction of Engineer In charge or his representatives. All dismantled materials like sleepers, fittings and plants etc. except Rail are to be deposited to concerned PWI/ Stores or as instructed by Site in charge. The rate is inclusive of all tolls & plants all lead, lift, transportation, complete in all respect and no extra payment will be made on any account for this work | Track metre | 60.00 | 331.85 | 19,911 |
| 8 | Extra over sand, stone dust, filter media etc filling during Block period | cum | 80.00 | 729.91 | 58,392.8 |
| 9 | Boulder pitching hand packed over ground of bank previously dressed to section with Railway boulder stacked at toe with a free lead of 100m. | cum | 40.00 | 572.43 | 22,897.2 |
| 10 | RCC M-35 grade as per Rlys approved drawing and specification for construction of bridge sub structure /super strucre /RCC jacketing of arch ,pier abutment etc.The rate includes design of concrete mix manufacture of concrete y batching plant ,cost of form work included erection and de- shuttering ,placement of concrete using concrete pump /placing boom,compaction steel reinforecement cutting ,bending and binding of reinforcement with inding wires and placing in proper position,curing of concrete up to specified period complete in all respect including all lead lift crossing road /track etc.The rate also includes cost of all ingredient of RCC in/c cement,sand aggregate ,admixture ,labour tools and plants etc.but excluding the cost of reinforcement.The contractor has to construct the approach road to the site at his own cost ,if required no extra payment will be made for this. | cum | 594.00 | 12,503.98 | 74,27,364.12 |
| 11 | Reinforcement Cement concrete of M-25 grade as per Railways approved drawing & specification for foundation of flooring, drop wall, curtain wall. The rate includes designing of concrete mix, manufacturing of concrete by concrete batching plant,cost of form work including erection & de- shuttering,batching plant,placement of concrete by concrete pump,compaction including cutting ,bending & binding of reinforcement with binding wires & placing in proper position ,curing of concrete up to specified period complete in all respect including all lead ,lift crossing road/track etc.The rate also including cost of all ingradients including cement admixture,lbour,tools,planta etc .steel reinforcement supply will be paid separately. | cum | 50.00 | 12,423.64 | 6,21,182 |
| 12 | Mobilisation of crane for erecting and placing of RCC/PSC SLABS/RCC BOX segment from road to the construction site of capacity of 250MT capacity (Minimum)-80 ft boom length.The crane will have to work at construction site.The rate includes all kind of hire charges fuel,labours and other necessary charges and repairing of road temporary time to time ,as required and as per direction of site in -charges complete in all respects.(NOTE:Here numbers means per crane) | Numbers | 2.00 | 22,82,455.42 | 45,64,910.84 |
| 13 | Transporting of all sorts of steel material including rail/girder/RCC Slab required use of track or trailer including all unloading loading lifting,descent and crossing multiple line for loading with stacking the same with a free lead of 150 mts after unloading as per instruction of site in charges (with lead above 120km and above ) 30Km for 40MT. | MT/Km | 1200.00 | 16 | 19,200 |
| 14 | Cutting of Rails 90R/52Kg/60Kg inside or outside of the track for provision gap in the rail section for erection purpose. The rate shall include all labours, tools & tackles etc. required to carry out the work complete in all respect | Numbers | 47.00 | 77.29 | 3,632.63 |
| Schedule total | ₹1,34,42,116.79 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .