| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.4 LAdmitted-Fee/PreQual/Technical/Finance | L1 | Admitted-Fee/PreQual/Technical/Finance | ||
| 2 | L2₹1.5 L+₹4,918.85 (3.40%)Admitted-Fee/PreQual/Technical/Finance | L2 | Admitted-Fee/PreQual/Technical/Finance | ||
| 3 | L3₹1.5 L+₹5,465.39 (3.78%)Admitted-Fee/PreQual/Technical/Finance | L3 | Admitted-Fee/PreQual/Technical/Finance | ||
| 4 | L4₹1.7 L+₹30,332.90 (21.0%)Admitted-Fee/PreQual/Technical/Finance | L4 | Admitted-Fee/PreQual/Technical/Finance | ||
| 5 | L5₹1.9 L+₹41,263.68 (28.5%)Admitted-Fee/PreQual/Technical/Finance | L5 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹2.8 L
EMD Value
₹5,600
Closing Date
6 Oct 2026, 5:00 pmClosed
Executive Engineer REW Kishtwar
Hall No 4 Executive Engineer REW Kishtwar
BOQ
2026_RDPR_326606_9
e-NIT No128 of REW KISHTWAR 2026-27 Dated.30.09.2026
Open Tender
Civil Works
Percentage
30 days
Kishtwar
NIT
2 documents required · 2 mandatory
₹600
Executive Engineer REW Kishtwar
₹5,600
17 Oct 2026
30 Sept 2026
7 Oct 2026
30 Sept 2026
6 Oct 2026
30 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Add CIB | 1 | No | 1,500 | ₹1,500 |
| 2 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas
(exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including
disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by
Engineer-in-Charge.
2.7.1 All kinds of soil : | 3.12 | CUM | 479.3 | ₹1,495.42 |
| 3 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: | 0.4 | CUM | 4,826.5 | ₹1,930.6 |
| 4 | Providing and laying in position cement concrete of specified grade including curing but
excluding the cost of centring and shuttering. All work upto plinth level with: | 6.88 | CUM | 5,733.6 | ₹39,447.17 |
| 5 | Dumping of stone including cost of stone | 12.59 | CUM | 918 | ₹11,557.62 |
| 6 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills, fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering and finishing with. | 9.51 | CUM | 7,564.8 | ₹71,941.25 |
| 7 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°,
landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral
stair cases upto five level including curing but excluding the cost of centring, shuttering,
finishing and reinforcement with | 0.79 | CUM | 9,821.85 | ₹7,759.26 |
| 8 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete upto plinth level | 94.25 | CUM | 123.2 | ₹11,611.6 |
| 9 | Random Rubble masonry with hard stone in foundation and plinth
including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarse
sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and
curing complete with: | 15.6 | SQM | 5,402.6 | ₹84,280.56 |
| 10 | c/o sand and agg | 23.91 | CUM | 630.74 | ₹15,079.73 |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.01 MB
BOQ_1104846.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .